Service Solicited - 2025 - HECCO Engineers - Change Order No. 2 Heritage Park RestroomOwner: Engineer: Contractor: City of Eagle, Idaho HECO Engineers Bricon. Inc. CHANGE ORDER NO.: 2 Owner's Project No.: Engineer's Project No.: Contractor's Project No.: N/A- EG22-0420 Project: Heritage Park Restroom Contract Name: Heritage Park Restroom Date Issued: October 17, 2025 Effective Date of Change Order: October 21, 2025 The Contract is modified as follows upon execution of this Change Order: Description: See attached Attachments: Contract Change Order Description Chanpa in Cnntrart Prira Chnnaa in Cnn+rnr+Timac Original Contract Price: Original Contract Times: Substantial Completion: October 15, 2025 $ 565,900.00 Ready for final payment: October 30, 2025 _ , from previously approved Change Increase from previously approved Change Orders No.1 to Orders No. 1 to No. 1: No. 1: Substantial Completion: 7 days $ 0.00 Ready for final payment: 7 days Contract Price prior to this Change Order: Contract Times prior to this Change Order: Substantial Completion: October 22, 2025 $ 565,900.00 Ready for final payment: November 6, 2025 Increase this Change Order: Increase this Change Order: Substantial Completion: 27 days $ 3,298.57 Ready for final payment: 27 days Contract Price incorporating this Change Order: Contract Times with all approved Change Orders: Substantial Completion: November 18, 2025 $ 569,198.57 Ready for final payment: December 3, 2025 Recommended �byl Engineer (if required) By: .... . d W . A00— Title: Project Engineer Date: 10/17/25 Authorize wner By: Title: Date: Accepted by Contractor (frh&xlj�k- U Sophie Redenbaugh Vice President 10/17/2025 Approved by Funding Agency (if applicable) N/A N/A N/A EJCDC® C-941, Change Order EJCDC® C-941, Change Order, Rev.1. CopyrighY�' 2018 National Society of Professional Engineers, American Council of Engineering Companies and American Society of Civil Engineers. All rights reserved. Page 1 of 2 CONTRACT CHANGE ORDER DESCRIPTION City of Eagle CONTRACT: Heritage Park Restroom OWNER: City of Eagle CHANGE ORDER NO DATE: October 17 2025 PROJECT NO: EG22-0420 DECREASE INCREASE Description of Changes In Contract In Contract Price Price 1. Automatic Flush Valve: Automatic Faucet — Change flush valves for the restroom toilets to automatic flush valves; $888.97 Change faucets for the restroom sinks to automatic faucets. Increase in the contract amount. 2. 2" Fiber Conduit — Due to lack of availability, the City provided 2" fiber conduit to the Contractor for ($210.00) installation. This amount is a decrease in the contract amount. • 210 LF @ $1.00/1-F 3. Drinkine Fountain Water Line — It was discovered during construction that service to the drinking fountain was not through the restroom building. This eliminates the need ($240.00) for piping from the new building to the drinking fountain as shown on the plans and the amount is a decrease in the contract amount. • 16 LF @ $15/1-F 4. Paver Repair 2"d Street (at Tree Well) — Removal of existing adjacent pavers as needed, regrading of the $2,859.60 existing base, installation of sand, and reinstallation of pavers. 5. Time Extension — Extend the contract 27 days due to delays associated with equipment changes/lead times/scheduling. Due to production lead time, the delivery of the rolling counter door may extend beyond the dates associated with this extension. No change in contract price associated with this extension. TOTALS I ($450.00) I $3,748.57 TOTAL CHANGE ORDER AMOUNT I I $3,298.57 EJCDC® C-941, Change Order EJCDC® C-941, Change Order, Rev.1. CopyrightO 2018 National Society of Professional Engineers, American Council of Engineering Companies and American Society of Civil Engineers. All rights reserved. Page 2 of 2