Minutes - 2024 - Conservation Advisory Committee (CEP) - 11/14/2024 - RegularTHE CITY OF EAGLE
CONSERVATION ADVISORY COMMITTEE
MINUTES
November 14, 2024, 5:30 PM
1. CALL TO ORDER: Chairman Baun calls the meeting to order.
2. ROLL CALL: BAUN, BESSAW, JOHNSON, KOSCIUCH, PELLANT.
Present: Baun, Bessaw, Johnson, Kosciuch, Pellant. A quorum is present.
Bessaw makes a motion to amend the agenda to move item 4B above reports. Seconded by
Pellant. ALL AYE...MOTION CARRIES.
B. Fiscal Year 2025-2029 Capital Plan Update': Staffwill review the fiscal year 2025-2029
Capital Plan, adopted on October 22, 2024.. (NBS),.,;
Director of Long -Range Planning, Nicoel Baird Spenc,ez,providies ac'presentation on the Fiscal Year
2025-2029 Capital Plan and requests projects, fromCottonniftee ihould they have any. Project
requests can be submitted online.
3. REPORTS: '+vlteeF"j`
A. Committee: Baun discusses Fish and game signs, PPRC attendance, RPPC Plan status, and
Office of Emergency Management Grant opportunities.
B. Staff: Planner Hailey Durham reviews the CEP C of 0 list. The letters requesting yearly
dues will be sent within the next two weeks.
4. NEW BUSINESS:
A. ACTION ITEM- Minutes of August 8, 2024.
Bessaw makes a motion to approve the minutes of August 8. Seconded by Pellant. ALL
AYE...MOTION CARRIES.
B. Fiscal Year 2025-2029 Capital Plan Update: Staff will review the fiscal year 2025-2029
Capital Plan, adopted on October 22, 2024. (NBS)
This item was moved to the top of the agenda.
C. Review the Charlie Wood Park Concept Parcel Use Recommendation Report.
Baun provides an overview of the process of the Charlie Wood Park project and reviews the Concept
Parcel Use Recommendation Report.
General discussion amongst the Committee regarding potential projects on the site including a wetlands
project.
D. Review City Owned Properties for Potential CEP Projects.
The Committee reviews the City owned properties map and looks for potential CEP opportunities.
E. Schedule Future Meetings for 2025.
The Committee agrees to meet quarterly beginning January 2025 on the 2nd Thursday of the month at
5:30 p.m.
5. ADJOURNMENT:
Baun Moves to adjourn. Seconded by Bessaw. ALL AYE...MOTION CARRIES.
Hearing no further business, the Conservation Advisory Committee meeting was adjourned.
fully submitted:
HO Y CSTCSITS, Id-CMCT
DEPUTY CITY CLERK
APPROVED:
CHA E BAUN,
CHA AN
AN AUDIO RECORDING OF THIS MEETING IS AVAILABLE FOR DOWNLOAD AT
W W W.CITYOFEAGLE.ORG.
CITY OF EAGLE
FISCAL YEAR 2025-2029
CAPITAL PLAN
Nichoel Baird Spencer MCRP, AICP
Director of Long -Range Planning & Projects
nbaird@cityofeagle.orq
THE CITY OF
EAGLE
BENEFITS OF A CAPITAL PLAN
Expands the City's vision to 5-year planning window for capital projects, capital maintenance
& capital liability
Decreases demand on a single fiscal year
Creates an annual process for the public involvement: to hear, understand and request
projects- Transparency in Budgeting
Creates a City-wide/Cross departmental list of priorities
Evaluates competing demands for resources based on City's prioritization and the City's long-
term goals and objectives (is one project worth all the funding)
Helps position the City for outside funding & partnership options
Provides a means for the implementation of strategic and comprehensive plans within the
City's fiscal capacity
Decreases vulnerability during economic crisis & emergencies
WHAT IS THE CAPITAL PLAN?
Sets forth the
strategies, projects
and priorities which
the City of Eagle will
pursue over the next
five years.
This is a fiscally constrained plan
Only FY 25 is "funded"
The first year of the Plan align with the City's
adopted FY25 Budget.
The remaining years focus on City's priorities
(what do we want) and fundings options
(what can we afford and &when).
Allows elected officials, staff, partner
agencies, and the public to work in a
coordinated fashion to implement projects
(Grants, Public -Private Partnerships, Local $,
Cost share agreements & capital planning).
THIS PLAN...
=Provide the public a list of expected projects
Prioritizes projects for funding
=Mirrors current FY Budget
=Establishes an anticipated cost for projects
=Helps the City save for future construction &
need Maintenance
=Leverages impact fees, General Fund and
outside funding options
=Guarantee a project beyond an approved
contract
=Commit the City to construction in a specific
year
=Commit continued funding of maintenance
= Guarantee priorities are constructed in the
order of the plan
NOT A CAPITAL /AIPROVEA'/ENTPLAN
City has three (3) adopted CIPs for the collection of parks,
pathways, police impacts these funds. Projects within these plans
are prioritized as part of the Capital Plan.
Doesn't meet the requirements of Idaho Code 67-8208
Isn't used to collect impact fees just coordinate expenditure
Doesn't establish an adopted LOS
Doesn't include a complete inventory the existing City assets
Water & Fiber as enterprise funds are not part of this plan
PLANNING FOR EXISTING & NEW CAPITAL
Capital Maintenance"Existing'
Replacement Upgrade, or renovation of an
existing capital investment that has a cost of
of more and a lifespan of 5-years or
more. For every $ of Capital it is estimated
the City should set aside 3¢ annually.
Flood damage, vehicle replacement,
replacement of park structures
Funding Guideline f `4: $1.5 million in
GF/year (plus increased capital liability)/year
Capital Projects "New"
New project, facility, or investment that has a
cost of 75K or more and a lifespan of 5-
years or more.
Exam New parks & Trails, expansion of
existing facilities, may include preliminary
planning & engineering
Funding Guideline: $1 million
Capital Liability: The City's increased cost/responsibility to maintain improve or
replace a piece of infrastructure. Can occur as part of .;apital maintenance or a
capital project.
FY 24 IN REVIEW - MAINTENANCE
FY 2024 Capital Maintenance Year End Review
Project #
Project Title
Budget
Spent
% Complete
Comments
8 7 9 % of
PW CM-1
Heritage Park
$ 1,050,000.00
$ 2,360.00
0.22%
Pre -Engineering & Savings for construction in Fee 25
PW CM-15
OK Playground
$ 212,120.28
$ 212,120.28
100%
COMPLETED
project funds
IT CM-7
Servers
$ 103,500.00
$ 56,674.27
54.76%
COMPLETED under budget
PW CM-17
Jackson House
$ 100,000.00
$ 14,510.00
14.51%
Historic House Survey Completed, carry forward for
specific needs
expended saved
as 0
5%
TRL CP-4
N. Channel Bank Repairs
$ 100,000.00
$ 98,776.75
98.78%
COMPLETED under budget
planned
ITCM-3
Backbone lnfrastructure
$ 128,000.00
$ 44,323.23
34.63%
COMPLETED under budget
increase from
PW CM-13 Vehicle Replacement
$ 50,000.00
$ -
0.00%
Savings for future FY
PW CM-16 Equipment Replacement
$ 1,200.00
$ 1,200.00
100.00%
previous year
COMPLETED under budget
TRL CM-11 FEMA Trail Repair #4 OR Merrill Greenbelt
$ 59,804.72
$ -
0.00%
City Council mod #2 & #3 reduced by $84,505, Project
deferred until completion of PT&OS Plan
PW CM-8
IT CM-8
Library Roof
$ 250,000.00
$ 249,407.00
99.76%
COMPLETED under budget FY 24
Carry forward to FY 25
Chambers Recording
$ 80,000.00
$ 47,049.80
58.81%
TP CM-1 Floodway /City Property Protection
PW CM-15 2023 & 2024 Trail Maintenance
$ 10,000.00
$ 40,000.00
$ 10,000.00
$ -
100.00%
0.00%
COMPLETED
Carry forward to FY 25
Maintenance
Implementation
Grade:
B
$ 2,184,625.00
FY 24 Budget
Savings for future
Incomplete/Carry
Forward Projects
Cost Savings/Under
Budget
$ 736,421.33
Spent FY 24
33.71%
% of Budget
$ 1,183,130.00
$ 132,754.92
54.16%
6.08%
$ 132,318.75
6.06%
FY 24 IN REVIEW - PROJECTS
FY 2024 Capital Projects Year End Review
77% of
ro'ect funds
Project #
Project Title
Budget
Spent
% Complete
Comments
GEN CP-1
Three Cities River Crossing Study (3CRX)
$ 100,000.00
$ -
0%
Working with ITD & COMPASS On scope of work for a expended/saved
study
TP CP-3
Eagle Road Ped/ Bike Bridge
$ 300,000.00
$ 301,725.03
100.58%
as planned
COMPLETED- Final billing in FY 24, Modification #5
Funded from Trails impact fees & TRL CP-4 to balance
TP CP-1
PW CP-2
TP CP-6
P&R CP-2
Eagle & State Street (ACHD Project)
City Owned Shop
Olde Park -Design & Savings
Regional Sport Park
$ 1,010,309.00
$ 450,000.00
$ 600,000.00
$ 780,000.00
$ 129,222.72
$ -
$ 216,382.82
$ 739,976.54
12.79%
0.00%
36.06%
94.87%
Construction in FY 24 & FY 25 Shifting/Changing
Savings for Future FY
Final Engineerin: Savin: for FY 25 construction priorities. Two
Multi -year Construction with a cost share agreement
P&R CP-8
TP CP-2
Foothills Shooting Sports Park
$ 800,000.00
$ 610,812.14
76.35%
substantially Complete
major projects
incomplete.
Aikens Street Extension- SAVINGS ONLY
$ 680,000.00
$ 53,569.23
7.88%streetlights
Saving for FY 25 Construction, City purchased
PW CP-13
City Hall Safety
$ 425,000.00
$ -
0.00%
Carry forward to FY 25, see change in scope in FY 25
TP CP-12
P&R CP-11
Linder Road Expansion (SH 44 to FF)
Parks, Trails & Open Space Master Plan
$ 400,000.00
$ 287,000.00
$ 12,325.00
$ -
3.08%
0.00%
Preliminary design, Saving for Construction FY 26
RFP prepared, waiting for staff assignment
P&R CP-7
Charlie Wood Park Prospectus
$ 20,000.00
$ -
0.00%
Project deferred until completion of PT&OS Plan
PW CP-11
Pamela Baker Park
$ 5,458.00
$ 332.50
6.09%
Pump purchased from impact fees, installation FY 25,
Idaho Power returned $5,458 in over changes from FY
23
FY 24 Projects
Implementation
PW CP-9
Mace Park
$ 500,000.00
$ 132,638.04
26.53%
Under Construction- Fall 2024 Completion
TP CP-8 & 9
PW CP-17
Ped/Bike Studies (FF &BL Rds)
Fleet Expansion
$ 200,000.00
$ 50,000.00
$ -
$ -
0.00%
0.00%
Project deferred to ACHD Grade:
Savings for future FY
LIB CP-1
Library Master Plan- SAVINGS ONLY
$ 50,000.00
$ 6,657,767.00
FY 24 Budget
$ -
$ 2,196,984.02
Spent FY 24
0.00%
33.00%
% of Budget
Savings for future FY
C �'
Savings for future
Incomplete/Carry
Cost Savings/Under
Budget
$ 2,928,809.23
$ 1,528,573.28
$ (1,725.03)
43.99%
22.96%
-0.03%
FY 24 INCREASED LIABILITY
FY 2024 Increased Capital Liability
Project No.
Project Description
Project Cost
Annual Set-
Aside/Project $
Project
Specific Increase
PW CM-15
OK Playground
$ 212,120.28
$0.03
$ 6,363.61
TRL CP-4 N. Channel Bank Repairs
$ 98,776.75
$ 2,963.30
PW CM-8 Library Roof
$ 249,407.00
$ 7,482.21
P&R CP-8 Foothills Shooting Sports Park
$ 610,812.14
$ 18,324.36
TOTAL PROJECT COST: $ 1,171,116.17
NEW LIABILITY: $ 35,133.49
FY 2026 the staff will request an increase to the annual capital maintenance set -aside of $1.6M due to
increased capital maintenance due to construction.
THE PLANNING PROCESS
Six (6) outreach meeting with the Committees. Commissions &
Boards.
October to December 2023 - online project submittal process
Eagle City Council held 1 Quarterly reviews:
Q1 2024- Does Council wish to continue?
Four (4) workshops between February & June of 2024:
February 21, 2024,
March 14, 2024,
April 3, 2024,
June 19, 2024
Focus on Changes in Funding
A Public Open House on September 1 8th with Public Comment open
through September 30th — Comment presented at Oct. 2nd mtg.
STEP 1:
DATA
GATHERING Collect data about the facilities and services the City
provides:
• Annual budget expenditures and revenue sources
• Annual operation & maintenance practices
• Major Capital Maintenance and upgrades
• Calculate increase Capital Liability
City Committees, Commissions &
Boards Ideas
STEP 2:
CITY-WIDE
PROJECT
SCOPING
STEP 3:
CITY
COUNCIL
REVIEW
STEP 4:
ADOPT &
BEGIN AGAIN
FY 2025-2029
Project Scoping:
• Preliminary Scoping by City Departments
• First Review by the City Council
• Staff Prioritization & Scoring
City Council Review:
• Review of all projects submitted
• Review of staff Scoring
• Review of Public F aitic pation
arison
Draftin•of Fiscally Constrained Plan` .�
City Adoption:
• The Plan is a guide, adopted by resolutio
• Plan mirrors the City's FY24-25 Budget
Begin Again:
• Process begins in the Fall of each year is
• Prioritize 5-years of projects (FY 25-29)
• Refine Public Engagement m ,�
City of Eagle
Capital Planning Process
FY 2025 TO FY 2029 CAPITAL PLAN
rrojects prioritization includes:
1) City Council's Prioritization
Committee, Commission, & Board Recommendation (October & November 2021)
Staff Scoring updates
Council Project by project prioritization (2 rounds)
2) Year Requested
Staff Updated project request years based on current conditions
3) Leveraging & Inclusion CIP
Plans completed in compliance with Idaho Code 67-82
Parks, Pathways & Police
4) Availability of Funding
Plan is fiscally constrained limited to $7.5M in maintenance & $5M in Projects across 5 years
Prioritization is influenced by the availability of outside funding
5) Compliance with Planning Goals
Highest ranked projects
get priority funding in the
year requested.
1
Lel
ce
li
FY 2025-2029 Capital Maintenance
Fiscal Year 2025 Maintenance (In City's FY 24-25 Budget)
CM P
Description
Details
Amount Requested
Funding Description/Comments
f
3
a
Heritage Park
Department: LRP&P & PW
Staff: Eric Ziegentuss
Heritage Park Renovation Construction
Year Requested: 2024
priority: Planned Replacement
Amount Requested: $3M
FY 25.29 PLAN YEAR: 2025
$ 3000000
M in Carry Forward & 51.9M in FY 25.
Renovation and expansion of Heritage Park
Renov$1.04ation
including new restroom facility, splashpad, and
new park layout.
uu
Jackson House
Department Publik Works
Staff: Eric Z egenfuss
Jackson House
Year Requested: 2023
Priority: Planned FY 2023
Amount Requested: $1001C
PLAN YEAR: Multiple
$ 84,490
$84.490 in Carry Forward. Restoration of roof &
Chimney, completion of an adaptive reuse study.
m
f
itAmount
Vehicle Replacement
Department Pub&[ Works
2024 Vehicle Replacements
Year Requested: 2024
priority: Annual Replacement
Requested: SSOK
PLAN YEAR: 2025
5 100,000
$50KCany Forward & $50K new general fund.
Replacement of City Vehicles. Kept in capital
plan due to need to save across FYs
u.
3
a
2024 & 2025 Trail Maintenance
Department Public Works
Staff: Eric Ziegenfuss
2023 Trail Maintenance
Year Requested: 2024
priority: Annual Planned Replacement
Amount Requested: $40K
FY 25-29 PLAN YEAR: 2025
$ 58,000
$38K Carry Forward & $20K new General Fund.
Trail upkeep and maintenance. Last year in Capital
M aintenance, will move to department budget in
FY 26
a
g
o
Friendship Playground
Department Public Works
Staff: Eric Zlegenfuss
Friendship Park Playground Replacement
Year Requested: 2024
Priority: Planned Replacement
Amount Requested: $130K
FY 25-29 PLAN YEAR: 2025
$ 130,000
Replace play equipment in Friendship Park
U9 CM•3
Library Concrete Maintenance-
,W
Department: Library & Publik Works
Staff: Steve Baumgartner & Eric Zsegeofuss,
$300K
Immediate Priority
PLAN YEAR: MultipleLakemoor
$'�
New project added by CC at 10-24. added due to
significant issues with liability and tripping
hazards. As proposed this action will Remove
Floodway Protection (TP CM.1) in FY 25, Remove
Trail (TRL CM-6) until after PT&OS Plan,
Reduce Capital Reserves by $99,500.
FY 2025 CM Request:
$ 3,672,490
Total FY 25
Maintenance Budget:
$3.67M
NEW General Fund:
$962K (26.2%)
Carry Forward:
$2.7M (73.8%)
Reserves:
$100K (2.7%)
Outside Funding:
$0K (0.0%)
Changes Post Public Open House
W CM-): Heritage Park full build out &
expansion in FY 25
LIB CM-3:
Estimated
Emerging
Library Concrete Replacement
at $300K
safety need
LakemeeF4Fal:
Library Concrete Maintenance -
New
Resulted in defunding:
TRL CM-6: Lakemoor Trail ($1 10K)
TP CM-1: FY 25 Floodway Protection ($10k)
Reserve Transfer: $99,500
Department: Library & Public Works
Staff: Steve Bumgatber & Eric Ziegenfuss,
$300K
Immediate Priority
PLAN YEAR:Multiple
300,000
Removed in FY 2S to fund library concrete
replacement
Reduced to pay for police contract & Library
Concrete. Defer until PT&OS Plan is completed
New project added by CC at 10-24. added due to
sigifcant issues with liability and tripping hazards.
As proposed this action will Remove Floodway
Protection (TP CM-1) in FY 25, Remove Lakemoor
Trail (TRL CM-6) until after PT&OS Plan, Reduce
Capital Reserves by $99,500.
Funding Option 1:
Remove Floodway
Protection (TP CM-1)
in FY 25, Remove
Lakemoor Trail (TRL
CM-6) until after
PT&OS Plan, Reduce
Capital Reserves by
$99,500. Will result in
Reserves at 98% of
desired levels.
125 to FY 2029 Funded Ca • ital Projects at a Glance
Project Name
FY25 1 FY26 1 FYZ7 1 FY28
9
LL J
OCP
J
CP-2
Regional Sports Park - Phase 1
SIP
*
'l`
PW CP-13
City Hall Facility Projects
efit,
Project Completed
2
Police Weaponry
fa
Based on Need
rt CP-z
Police Level of Service Study
Project completed
T&P CP-12
Linder Road (SH-44 to FF)
���
Pro ect Completed
PW CP-17
Fleet Expansion
liar
Sir
ifk
-.NI)
LIB CP-1
Library Facilities Master Plan
lit
4P°
40'
,,
it i
Project
Complete
GEN-CP-1/ T&P CP-10
Three Cities River Crossing (3CRX)
rr
Oil
Project Completed
T&P CP-1
Olde Park Extension
Vali,
fret:
Project Completed
T&P CP-2
Aikens Street Extension
Project Completed
P&R CP-11
Mace Park
*.iii.
Project Completed
Cli
N
1
T&P CP-1
State & Eagle Intersection
fa4
Project Completed
P&R CP-8
Foothills Shooting Sport Park
',°
`
f'
*
f
P&R CP-9
Parks, Trails & Open Space Master Plan
OA
Project Completed
r !
N
P&R CP-10
Pamela Baker Park - Irrigation Pump Only
2
4t
lit
SP
IP
PW CP-2
City Owned Shop
VA
I°
*
*
P&R CP-10
West Park (Terra View)
``
Project Summary shows progression is
measured in three categories:
Planning/Engineering/Design
Savings
Construction/Purchase
Q
`J
L)
FY 2025 to FY 2029 Funded Capital Projects at a Glance
Project No. Project Name
P&R CP-2
PW CP-13
L CP-2
CP 2
PW CP-17
GEN-CP-1/ T&P CP-10
Regional Sports Park - Phase 1
FY25
City Hall Facility Projects
Police Weaponry
Police Level of Service Study
Linder Road (SH-44 to FF)
Fleet Expansion
Library Facilities Master Plan
Three Cities River Crossing (3CRX)
Olde Park Extension
P&R CP-11
P&R CP-8
Aikens Street Extension
P'*
Mace Park
State & Eagle lntersection
Foothills Shooting Sport Park
P&R CP-9
P&R CP-10
PW CP-2
P&R CP-10
Parks, Trails & Open Space Master Plan
Pamela Baker Park - Irrigation Pump Only
City Owned Shop
West Park (Terra View)
Change in Scope
Savings Only
Archery Only
Total FY 25
Projects Budget:
$7.732 M
NEW General Fund:
$1.43M (18.4%)
Carry Forward:
$3.48M (45.1%)
Impact Fes:
$232K (3%)
Reserves:
$450K (5.8%)
Outside Funding:
$2.13M (27.6%)
Funded From Reserves- savings only
Added back: Developer built, Impact fee only funding
Changes Post Public Open House
PW, CP-1.
LIB CP-3:
3•, Change in Scope, no change in funding
Library Master Plan
Estimated at $50K in FY 27 & FY28
P&R CCu-_
u
r1
a
CO
Returned to program as park impact fee only
City Hall Facility
Projects
Library Facilities
Master Plan
$ 425,000
Department: Clerk/Treasure & Public
Works
Staff: Tracy Osborn, Kellie Rekow, & Eric
Ziegenfuss
$425K
Med-High Staff Score
Construction FY25
$ 150,000
West Park (Terra
View)
$2.05M
Department: Library
Staff: Steve Baumgartner
$150K Study Only
No Public Score
High Staff Score
TBD
Department: LRP&P, Public Works &
Planning
Staff: Nichoel Baird Spencer, Eric
Ziegenfuss, & Bill Vaughan
$2.056 Million Requested
Impact Fee Eligible
Med-Hi:h Public Priori
Merger of three City Hall facility projects into a single FY 24 expenditure -
City Hall safety improvements, Clerks Office Reconfiguration & Glass in
Rec Center. FY 25 the project will remove the gloss in rec center and add
City Hall Furniture.
425,000.00
Begin saving for a Library Master Plan that will help direct investment,
expansion and the provision of services. This savings was set aside by
the Library Board before the Library became a City Dept. The project
will need to be ranked in future years for funding.
Merged with West Side Park with Terra View, update based on CC
approval. IF approved in a separate agreement the City could fund up
to $2.056 M through a reimbursement of impact fees. Primarily funded
through Impact fee reimbursement for the Terra View development.
$ 425,000.00
100,000.00
$ 50,000.00
$ 2,056,000.00
FY25
FY26
FY27
FY28
FY29
50,000.00
50,000.00
$
Timing of funding will be dependent an
reaching an agreement with the developer and
the build out of the project. Impact Fees from
this development could be reimbursed to the
master developer to fund the City's share of
construction.
FY 2026 TO 2029 PROJECTS
Things are hrirder to predict....
Changes in Fiscal Outlook
Changes in Cost of Construction
Changes in priorities
Unanticipated Partnerships & Opportunities
Changes in Leadership
UNPLANNED CAPACITY
Plan is guided by annual planned general fund investment:
$1.5M for Capital Maintenance
Capital Maintenance Unplanned Capacity
FY 25
FY26
riz7
FY28
FY29
(750,000)
$1 M for Capital Projects
0,000
369,000
123,000
840,000
c,apitalPri
d Capacity
FY25
FY26
7
FY28
FY29
(425,000.00)
$
(71 5.000.00)
650,000.
$
650,000.00
$
700,000.00
THE FY 25-29 PLAN ADOPTION STATUS
City Council adoption — October 22, 2024
Starting implementation of plans for:
• Heritage Park
Engineers scope @ October 22, 2025 CC mtg
- Bid solicitation tentatively schedule Feb. 2025
Construction substantial completion October 2025
Parks, Trails & Open Space Plan
Preliminary Review of Scope on Sept. 16
Waiting on Mayor's direction for staff assignment
• Jackson House Re -Use Study
Scope of Work @ October 22, 2025 CC mtg
- Sport Complex
2025 Capital Campaign Goal: $
• Police LOS Study
• 3CRX Scope
• DT Mobility Phase 2 (including Aikens)
100% design plans
Bid November 2024
■ Olde Park Place Extension
Property acquisition underway
■ Mace Parking
Substantial Completion Oct 31
Paving 10/17
Archery Range
Late October Ribbon Cutting
No funding for future phases planned
Pamela Baker Park
Irrigation conversion
West Park
Impact fee reimbursement under negotiation
Friendship Park
TBD- construction in Spring of 2025
Trail Maintenance
Projects determined by PW
* Maintenance Projects
Next Step:
November 2025 — Project Solicitation Process
Meetings with Committees, Commissions & Board