Service Solicited - 2024 - Idaho Power - Idaho Power Customer Cost Quote - Shooting Sports ParkIDAHO POWER.. An IDACORP Company CUSTOMER COST QUOTE FOR IDAHO POWER FACILITIES Customer or Project Name: CITY OF EAGLE - 7650 N WILLOW CREEK RD - SHOOTING PARK Construction Costs Line Installation Costs 1. Line Installation/Upgrade Charge $41,779 2. Customer Credits (Betterment, Metering, Salvage) $0 3. Customer Performed Construction Work Credit $0 4. Net Line Installation Cost Unusual Conditions 5. Unusual Conditions $54,761 6. Unusual Conditions Bank Letter of Credit (Only for over $10,000) $0 7. Net Unusual Conditions $54,761 Terminal Facilities Costs 8. Terminal Facilities $4,853 9. Terminal Facilities Allowances $(3,813) 10. Terminal Facilities Salvage $0 $41,779 11. Net Terminal Facilities Cost $1,040 12. Underground Service and Attachment Charges $0 13. Engineering Charge $1,116 14. Permits $100 15. Relocation or Removal $32 16. Miscellaneous Charges/Adjustments $0 17. Net Construction Costs 18. Prepaid Charges (Line Items 4, 7, 11, 12, 13, 14, 15, 16) $98,828 (Engineering, Permits & Right -of -Way) $0 19. Vested Interest Charge $0 20. Customer Payment Due Prior to Construction Scheduling This cost may not include all construction costs. see page 3 if additional service charges apply. Notes: Due to labor shortages and pandemic -related supply chain issues, Idaho Power anticipates a possible shortage of certain materials and equipment necessary to complete the Work (as defined below) which may delay completion of the Work. $98,828 Customer understands that charges for relocation, transfer or removal of non -Idaho Power equipment attached to Idahc Power facilities are not included in this Customer Cost Quote. It is the customer's responsibility to coordinate this work with the affected utility. All charges associated with this work are the responsibility of the Customer. For utility contact information, please call 208-388-2886. Customer understands that Idaho Power determines the metering requirements at such time that Customer submits a service request and requested electrical load during final design of the Project as contemplated herein. Notice: This Customer Cost Quote shall be binding on both Idaho Power Company ("Idaho Power") and Customer for a period of 60 days from the quoted date indicated below, subject to changes in information provided by the Customer or changes in Idaho Power's ability to obtain satisfactory rights -of -way or to comply with governmental regulations, including but not limited to the rules, regulations, and tariffs of the Idaho Public Utilities Commission ("IPUC") and the Public Utility Commission of Oregon ("OPUC"). Customer must make payment of the quoted amount not less than (30) days prior to the start of the construction work set forth in this agreement ("Work"). However, Idaho Power does not represent or warrant that the Work will commence within 30 days of receipt of payment. The start of the Work is subject to Idaho Power's ability to obtain the necessary labor, materials and equipment. Internal use Page 1 of 3 Service Request Number: 00526540 Customer Account Number: Work Order Number: Design Number: Version: 27661702 0000172370 001 By Initialing below, Customer acknowledges and agrees to the following: Customer initials Customer initials Customer initials The Customer has received the Underground Residential Conduit Installation brochure/packet or will access the information available online at https://docs. idahopower.com/pdfs/ServiceBilling/customerservice/newConstruction/U GResConduitl nstall. pdf Final Grade: Customer understands that as of the above -named project will be ready for facilities to be installed by Idaho Power. All roadways and cable routes must have all grading and sub grading completed by this date. The project must be properly referenced and have grade stakes installed at all Idaho Power device locations and as might be necessary to establish proper elevations and burial depths for Idaho Power facilities. The Customer will be responsible for the total cost of damage to Idaho Power facilities resulting from any subsequent changes in property, any needed relocation, repair, or lines, lot lines, elevations, grades, excavations, or profiles causing improper locations or burial depths of above -ground equipment, below -ground equipment, cable, or conduit. Unusual Conditions: As defined in Idaho Power's line installation tariff, Rule H, Unusual Conditions are construction conditions not normally encountered, but which Idaho Power may encounter during construction which impose additional, project -specific costs. These conditions include, but are not limited to: frost, landscape replacement, road compaction, pavement replacement, chip -sealing, rock digging/trenching, boring, nonstandard facilities or construction practices, and other than available voltage requirements. The total cost for all Unusual Conditions, in connection with the work as set forth on this Customer Cost Quote will be based on the actual costs incurred by Idaho Power related to the conditions encountered during performance of the Work. Upon completion of all Work, Idaho Power will refund to Customer any Unusual Conditions amount set forth on this Customer Cost Quote sheet but, not incurred by Idaho Power. Prior to commencement of the work, Customer shall identify for Idaho Power the location of all underground pipes, lines, and other facilities (collectively, the "Underground Lines") that may be on Customer's property where Idaho Power is working. Customer agrees to be responsible for identification and location of all Underground Lines and shall indemnify, defend, reimburse and hold harmless Idaho Power and its successors and their respective directors, officers, members, employees, representatives and agents for, from, and against any and all claims, liabilities, losses, damages, expenses, suits, actions, proceedings, judgement and costs of any kind (collectively, "Damages"), whether actual or merely alleged and whether directly incurred or from a third party, arising out of or relating to Customer's failure to properly or adequately identify and locate the Underground Lines, except to the extent finally determined by a court of law that such Damages resulted from the gross negligence or willful misconduct of Idaho Power, its agents, subcontractors, employees, officers or directors. Public Entity Indemnity Limitation. Idaho Power acknowledges that Customer is a public entity and, as such, Customer's liability is at all times limited as required by Idaho law, including Idaho Code Title 59, Chapter 10, the Idaho State Constitution, and the Idaho Tort Claims Act, Idaho Code Sections 6-901 through 6-929 and any indemnification or hold harmless provision shall be void to the extent such provision violates applicable laws. Nothing in the agreement shall be deemed to constitute a waiver by Customer of any privilege, protection, or immunity otherwise afforded it under the Idaho Constitution, Idaho Tort Claims Act, or any other applicable law or a waiver of its sovereign immunity, which is hereby expressly retained. Internal use Page 2 of 3 Service Request Number: 00526540 Customer Account Number: Work Order Number: Design Number: Version: 27661702 0000172370 001 The Customer acknowledges Idaho Power's Rule C (Service and Limitations), Section 7 (Right of Way) on file with the IPUC OPUC: "The Customer shall, without cost to Idaho Power, grant Idaho Power a right-of-way for Idaho Power's lines and apparatus across and upon the property owned or controlled by the Customer, necessary or incidental to the supplying of Electric Service and shall permit access thereto by Idaho Power's employees at all reasonable hours." By signing this Customer Cost Quote, Customer grants to Idaho Power a perpetual right-of-way over the Customer's property for the installation, operation, replacement and maintenance of power facilities to provide electrical service to the Customer and any future owners of the Customer's property. Construction Costs available for refund (Vested Interest limited to 5 years or 4 additional applicants) $88,184 Customer Payment Due Prior to Scheduling Construction $98,828 Customer initials Underground Service Attachment Charges to be billed separately The Customer understands that Underground Service Attachment Charges will be billed separately on the first month's power bill after service installation has been completed. In addition, the Customer has reviewed and acknowledges their responsibility for these costs. Idaho and Oregon cost information are available online at: ID: https://docs.idahopower.com/pdfs/ServiceBilling/customerservice/newConstruction/IdahoCostlnfo.pdf OR: https://docs.idahopower.com/pdfs/ServiceBilling/customerservice/newConstruction/OregonCostlnfo.pdf Statutory Certifications. In accordance with Idaho Code Section 67-2359, Idaho Power Company hereby certifies that it is not currently, and for the duration of this Customer Cost Quote will not be, owned or operated by the Government of China as defined in said code section. In accordance with Idaho Code Section 67-2346, Idaho Power Company hereby certifies that it is not currently engaged in, and for the duration of this Customer Cost Quote will not engage in, a boycott of goods and services from Israel or territories under its control as defined in said code section. Please sign and return all relevant forms along with the amount stated on the Customer Cost Quote to: Customer Signature Idaho Power Representative IDAHO POWER COMPANY 10790 Franklin Rd Boise, ID 83709 Date (6\-AvA Quote Date 08/16/2024 Internal use Page 3 of 3 Service Request Number: 00526540 Customer Account Number: Work Order Number: Design Number: Version: 27661702 0000172370 001 1•"411DAHO WARMER. Idaho Power Company Service Request Page: 1 Date: 8/16/2024 An IDACORP Company Service Request Number: 00526540 CITY OF EAGLE - 7650 N WILLOW CREEK RD - SHOOTING PARK Work Order Number: 27661702 Eng Hours: 00012 Request Type: RS Eng Fee Amount(Att98): 1,116.00 Rate Sch.: 07 Eng Fee Amount(Att16): Reply By: Eng Fee Service Agreement No: Eng Fee Service Agreement Date: Customer No: Feeder: S P VY 12A Service Location: 7650 N WILLOW CREEK RD EAGLE, ID 83616 Required in Service Date: 7/30/2024 Planning Center/Team: EAGLE Contact Detail: CUST CITY OF EAGLE 208-939-6813 PO BOX 1520, EAGLE ID 83616 IPCO CASEY BELVOIR (208) 388-2910 10790 Franklin Rd, BOISE ID 83709 RFND CITY OF EAGLE 208-939-6813 PO BOX 1520, EAGLE ID 83616 Attribute Information RES/COM eziegenfuss@cityofeagle.org CBelvoir@idahopower.com Service Voltage 120/240 No. Of Meters 1 Number of Phases 1 Meter Location KW Motor Load: Ct Loc Largest Motor Primary OH/UG U G 1 Phase KW Demand 15 KW Service OH/UG UG 3 Phase KW Demand Sry Owner I P C O Vested Int. Connected Load 15 KW Panel Amp Size 200 Commercial Deposit Amount Service Pole Riser SIC Number Description INSTALL UNDERGROUND PRIMARY LINE EXTENSION TO SERVE NEW 25 KVA 120/240 PADMOUNT TRANSFORMER. BORE 1-2" CONDUIT ACROSS WILLOW CREEK RD. INSTALL 464 SPLICE VAULT WITH HILLSIDE BARRIER OUTSIDE OF R.O.W., CUSTOMER TO PROVIDE TRENCH PATH ALONG EAST SIDE OF R.O.W. OTHERWISE COMPACTION WILL BE REQUIRED. IF TRENCHING IS OUTSIDE OF R.O.W. THEN NO COMPACTION IS REQUIRED. CUSTOMER RESPONSIBLE TO STAKE R.O.W ALONG WILLOWCREEK RD. AND AT ENTRANCE TO SHOOTING PARK, ALSO NEED TO PROVIDE FINAL GRADE FOR TRANSFORMER LOCATION. 10' EASEMENT ALONG R.O.W. MUST BE OBTAINED PRIOR TO CONSTRUCTION. Any changes to the project including but not limited to increases in load, timing of load schedule, location of service, and requested voltage may result in additional charge or delay of service. It is necessary to communicate changes as soon as possible. Client Signature — Date 8/16/2024 Idaho Power Representative Signature Date EASEMENT REQUIRED a:slr,' DATE OBTAINED: TO BE OBTAINED:PRIOR TO CONSTRCTION FROM CITY OF EAGLE 60' AVIAN CONSTRUCTION N2 1 ♦ SCOPE OF WORK: \ BORE 1-2" APPROX. PTg1 REMOVE PROTECTIVE CAP, INSTALL PRIMARY ELBOW 75' ACROSS ROAD PT#2 INSTALL 464 SPLICE VAULT & PAD, HILLSIDE BARRIER, BORE 1-2" ACROSS ROAD, d SPLICE \ PTO3 TRENCH ALONG EAST SIDE OF ROADWAY, INSTALL 1-2" CONDUIT, INSTALL 25 KVA }i2 TRANSFORMER, CONCRETE PAD, 1-2" SERVICE STUB, 1-2" PRIMARY STUB TO EAST OF TRANSFORMER. CUSTOMER TO CLEAR SAGE BRUSH & MAKE PATH FOR TRENCHING OUTSIDE OF R.OW. OR \ COMPACTION WILL BE REQUIRED. ALL TRENCHING THAT IS INSIDE ROAD RIGHT OF WAY OR CROSSING ROADWAYS WILL REQUIRE 95% ', lyCOMPACTION CONTACTS: CUST: ERIC 208.949.4390 eziegenfussOcityofecgle.org '' �+Q , IPCO: CASEY 208.388.2910 r E—, U ' z� UNDERGROUND CABLE NOTES POINT NUMBER FROM TO CONDUCTOR CU CABLE SIZE CABLE LENGTH TRENCH LENGTH CONDUIT CU CONDUIT SIZE CONDUIT LENGTH COMPACTION LENGTH BORE LENGTH 2 HE3 PV1 DCP10 1/0-B 566 - DDB2 2 - - 75 3 PV1 WC136 DCP10 1/0-B 1925 1901 DDB2 2 1901 •- - B0 MI HE3 ! 3 WC136 STUB 5 DDB2 2 5 - Q0000Q L_ tr) GO W LI_ L_ — CC L_ OL'i = .Q O = V Il 0 3FrF0 z z � HE43 Lot: 43.758099 \ 50 B Lon: —116.369084 GISO# 4463261 \ ` (1) 1 :1 DEVELOPER TO STAKE RUNNING LINE, FINAL HE3 GRADE AND DENCE LOCATIONS. ALL TRENCH SPOILS TO BE LEFT ON SITE. f 1 SWPP:— . _ . COWIN r: Date: Job Title: CITY OF EAGLE - 7650 N WILLOW CREEK RD - NEW RESIDENTIAL Feeder Map Fib Noma: EAGL1301 Surveyed or GPS: GPS Joint Use Attachment: NO Pre -Built Date: _ Suites Designed: — Construction Date: — Opero5ng Voltage: 7.2kV T FDR By: — Designer: C LB 1221 Design No: 0000172370 Work Order No: 27661702 Dew' — Additional Description: INSTALL SINGLE PHASE PRIMARY UNDERGROUND LINE EXTENSION Dos 1 Twn 05N Rog 01E Sec 20 BM AcFMBy: — Additlonel Description:State — INCLUDES 2" BORE -- PERMIT REQUIRED -- ID County Ada Date: — IDAHO POWER Co. WORK ORDER MAP SCALE: 1" = 100 Sheet 1 of 3 MATCH SHEET 3 \\ EASEMENT REQUIRED a^"® DATE OBTAINED: kJ) d ". \\ \ TO BE OBTAINED:PRIOR TO CONSTRCTION \\ \ FROM CITY OF EAGLE \ \ \ 60" AVIANCONSTRUCTION \,49\\\ � \ \ mod\ \ \ \\ \ \\ \ \ \ \\ \\ \\\ \ \ \\\ \ \ DEVELOPER TO STAKE RUNNING LINE. FINAL GRADE AND DEVICE LOCATIONS. ALL TRENCH SPOILS TO BE LEFT ON SITE. MATCH SHEET 1 swap:— Customer Date: Job CITY OF EAGLE - 7650 N WILLOW CREEK RD - NEW RESIDENTIAL Feeder Map File Name: EAGL1301 Surveyed or CPS: GPS JointSure Use or CPS:ent: S Pre-BuBt Date: Built as Designed: --- Construction Date: -- Opemtingvoltage: 7.2kV i " FOR By: — 1 1 Designer: CLB 1 22 1 I 7 Design No: OOOO 1 7Z3! O WokOrderNO: 27661702 Date. _ Additional Description: INSTALL SINGLE PHASE PRIMARY UNDERGROUND LINE EXTENSION Qua 1 Twn 05N Rng 01 E Sec 20 BM ArcFM By — Additional Description:state INCLUDES 2" BORE -- PERMIT REQUIRED -- ID count' Ada Date: — IDAHO POWER Co. WORK ORDER MAP SCALE: 1" = 100 Sheet 2 of 3 'THIS WORK ORDER DOES NOT INCLUDE YOUR UNDERGROUND SERVICE CHARGES. YOUR ACCOUNT WILL BE BILLED SEPARATELY ACCORDING TO THE "UNDERGROUND RESIDENTIAL CONDUR INSTALLATION REQUIREMENTS" ONCE THE SERVICE WORK HAS BEEN COMPLETED. /4 °icy'' Bh` 80" AVIAN CONSTRUCTION FIRE-RESISTANT BARRIER WHERE R IS NOT PRACTICAL ETWEETO OBTAIN THE SPECEASEMENT REQUIRED i EW PI MI MANED ME`ECCOMBUSTIBLE THE BUILDING SURFACES OR OPENINGS, THE CUSTOMER MAY PROVIDE FIRE-RESISTANT BARRIERS MADE OF WC136 / Z�S B ANLL APPLIBCABLE BUILDINUSTIBLE G CODS ES AND D MEETING DATE OBTAINED. = N3 POWER REQUIREMENTS. v NOTES: HE TO BE OBTAINED:PRIOR TO CONSTRCTION/ VARY • AT1 HEIGHT AND LENGTH OF THE BARPoER TO FIT TXE NEEDS OF EACH APPLICATION. FROM CI TY OF EAGLE %J FROM • ALLOW SPACE FOR REASONABLE VARIATIONS IN IT BE ESIZE OF REPLACED NETHE EQUIPMENT FUTU E. SHOULD [T] • THE 10' CLEARANCE IS MEASURED M 'LINE -OF -SIGHT' BETWEEN THE NEAREST 7 POINT ON THE EQUIPMENT AND THE WALL OR OPENING. NON-COMRUSTIRI F WA IS WITH 0PFNING0 A 10' CLEARANCE IS REQUIRED IN FRONT. TO EACH SIDE AND VERTICALLY OF ANY DOOR. WINDOW THAT OPENS. AIR INTAKE VENT OR FIRE ESCAPE ROUTE LOCATED ON A NON- COMBUSTIBLE WALL OR SURFACE. rDMPIISTIBI F WAI I (. I\ A 10' CLEARANCE IS REQUIRED FOR COMBUSTIBLE WALLS OR SURFACES. NOTE: • THESE DIMENSIONS MAY BE REDUCED IF THE CUSTOMER PROVIDES A SURABLE FIRE BARRIER. DEVELOPER TO STAKE RUNNING LINE. FINAL AAND DEVICE LOCATIONS. ALLLL TRENCH SPOILS TTOO BEELEFT ON SITE. SHEET 2 H SWPP:__ - - - Customer Date: Job TNIe: CITY OF EAGLE - 7650 N WILLOW CREEK RD - NEW RESIDENTIAL Feeder Map Fib Noma: EAGL1301 Surveyed or GPS: Gp N Joint Use AttachmentO Pre -Built — Buit es Designed: — Construction Date: — Operating voltage: 7.2kv s FOR By: — esi Dgner C L B 1221 Design No: 0000172370 wokQderNo: 27661702 Det"i — Additional Description: INSTALL SINGLE PHASE PRIMARY UNDERGROUND LINE EXTENSION Oua 1 Twn 05N Rng 01E Sec 20 BM AcFMBY _— Additional Description: — INCLUDES 2" BORE —PERMIT REQUIRED -- Stele ID Candy Ada Date: — IDAHO POWER Co. WORK ORDER MAP SCALE: 1" = 100 Sheet 3 or 3