Resolution - 2023 - 23-27 - Adopting Fy 2024-2028 Capital Plan - 09/26/2023 RESOLUTION NO. 23-27
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF EAGLE, IDAHO, ADOPTING
THE FISCAL YEAR 2024 TO 2028 CAPITAL PLAN DATED SEPTEMBER 26, 2023; AND
PROVIDING AN EFFECTIVE DATE.
WHEREAS, the City of Eagle is a municipal corporation operating under the laws of the
state of Idaho; and
WHEREAS, the City of Eagle desires to provide the City - citizens, land owners, elected
official, and staff - a road map for major investments and maintenance within the City that is
transparent,collaborative,and fiscally constrained;and
WHEREAS, the City of Eagle has determined that capital investments and maintenance be
reviewed,prioritized,and updated annually on a city-wide basis;and
WHEREAS, the City of Eagle, recognizes the need to save and set-aside funds across
multiple fiscal years to properly fund new improvements, save for maintenance of existing
infrastructure,and establishes a fund for emergencies that impact the City's infrastructure; and
WHEREAS, The Capital Plan illustrates the City's intent to leverages expenditures from
the City's Capital Fund, Park Fund, Pathway Fund, Police Impact Fee Fund, and outside sources
equaling $28.7 million for City's Fiscal Year 2024-28 budget; and
WHEREAS, the City of Eagle has drafted and developed the prioritized Capital
Plan through a series of open public meetings and workshops to guide and prioritize investment
for Fiscal Year 2024-2028 as set forth in Exhibit A; and
WHEREAS, the City of Eagle brought forward the plan at a public open house on July 12,
2023,and accepted public comment through July 31, 2023,
WHEREAS after taking public comment on hereinafter referred to as "Plan"on September
26, 2023; and
WHEREAS,the Plan contain the following information:
(a) A description of the annual project development process;
(b) A detail of the annual increase of in the City's Capital Liability associated with the
development and improvement to the City's capital portfolio;
(b) A general description of all project requests between Fiscal Year 2024 and Fiscal
Year 2028;
(c) A detailed funding plan, including available outside funding sources, for capital
projects and maintenance in Fiscal Year 2024 through Fiscal Year 2028,
1 of 2
k:\council\resolutions\draft resolutions\23-27 fy24-28 capital plan.doc
(d) A Fiscal Year 2024 capital projects and maintenance list consistent with the City of
Eagle FY 2024 Appropriation Ordinance No. 906
(e) A description and prioritization of unfunded capital projects and maintenance for five
(5) Fiscal Years (2024-2028)
(f) A recognition of the City's existing capital plans associated with impact fees under
Idaho Code 67-6802; and
WHEREAS, the City Council, after careful consideration, hereby finds and declares that
a capital plan to guide City investment and development in capital projects and operation and
maintenance of existing City investment is in the best interests of the community, therefore
deems it advisable to adopt the Fiscal Year 2024-2028 Capital Plan,
NOW, THEREFORE, BE IT RESOLVED BY THE MAYOR AND COUNCIL OF THE
CITY OF EAGLE, IDAHO that the "Fiscal Year 2024-2028" dated September 26, 2023,
attached hereto as Exhibit A, is hereby adopted by the City.This Resolution will be in full force and effect upon its adoption and approval this lQ day of
, 2023.
CITY OF EAGLE, IDAHO
J rce, Mayor
A EST:
,,,,
Tracy E. born, City Clerk •,•`••p4�EACL�
.� .• ••
• •4oRAT '.•(SEAL) G: •
U i •
* . S�
'. ••.nz rKro�:��Q
T,q pF
•I7Y11111f 1 .
2 of 2
k:\council\resolutions\draft resolutions\23-27 fy24-28 capital plan.doc
CITY OF EAGLE
FY 2024 TO FY 2028
Page | 1
Page | 2
COVER/FEATURED PROJECT: This year’s featured capital project is Eagle Road Pedestrian and Bicycle
Bridge. The project was 10‐years in the planning and development process. Completed a year earlier
than planned leveraging federal funds that reduced the City’s construction liability from $2.8M to
approximately $200K. Completed in May of 2023, this project provides a dedicated off‐highway
crossing of the north Channel of the Boise River parallel to State Highway 55. This bridge increases
connectivity city wide by providing safe access to Downtown Eagle, Eagle City Hall, Eagle Senior Center,
the Eagle Public Library, and all the Eagle public schools north of the river to residents south of the
River.
Page | 3
WHY WE PLAN:
OVERVIEW
This plan is a road map, establishing a process to fund necessary capital maintenance and desired new
capital projects of the City over the next five years. The City’s Council goal in the development of a city‐
wide capital plan was to:
“Provide the City (citizens, elected officials, and staff) a road map for major investments
and maintenance within the City that is collaborative and fiscally constrained.”
The idea of a City‐wide capital plan has been an aspiration of the City since the early 2000’s. Each of the
City’s comprehensive plans since 2004 has had a similar goal:
“Economic Sustainability: A community focused on the ability for the City to continue to
fund, improve and support itself, including infrastructure, parks, and trails without the
uses of building permit fees, impact fees and zoning fees.” ‐ Page 1 Eagle is HOME Plan
Often capital facilities plan only focus on the construction of new facilities – the leveraging of impact fees,
grants, and one‐time funds to construct public projects, but neglects to properly detail and plan for the
cost of operation, maintenance, and replacement of existing infrastructure and facilities over time. One
of the key tenants of this plan is to provide the City a complete picture of the cost of both constructing
new infrastructure and the cost and necessary savings for the City to properly maintain and plan for the
replacement of existing infrastructure as well. This plan relies on annual appropriations through the City’s
budget process and a commitment by the acting Mayor and City Council to implement.
Up until 2021, the City had funded projects inconsistently through a scatter‐shot approach, those wanting
funding requested it directly and individually to the Mayor and/or City Council, but projects were not
compared against each other in a formal manner to determine which projects were of the most
significance to the City, nor was the cost of capital maintenance factored into the decision to construct or
as part of the annual City budgeting process. For a few years, the City used a “strategic annual goal” or
“capital fund” to set aside funds across multiple years, but this process was not used by all departments
nor implemented consistently.
As required, the City has adopted a single‐year budget that addresses needs within a single fiscal year,
relying solely on one‐time and general fund dollars to fund capital projects, capital maintenance, and the
Page | 4
day‐to‐day operations of the City. The City’s general fund functions as a clearing house for all city revenue.
Some monies pass through the general fund to restrict accounts (impact fees, enterprise funds, and
bonds) while most funds are held in the general fund as a savings account and only transferred out to
specific accounts on an as needed basis. At the end of each fiscal year, unspent dollars are swept into
the general fund for reallocation in the next budget year. The goal is to limit the sweeping of unspent
money for capital projects and to hold those funds in a separate account from the general fund.
The Fiscal Year 2024 to Fiscal Year 2028 Capital Plan is the City of Eagle’s fourth year completing a city‐
wide prioritized fundings plan for capital. Evaluating all requests for capital maintenance and new capital
projects against each other to determine the greatest need and benefit for the community.
The capital fund is one of the largest budgeted funds within the City of Eagle, in FY2024 the fund holds
$11.32 million including project specific maintenance, capital projects, and reserves (for future projects).
Unlike other accounts funds within the City budget, the capital fund is not swept back into the general
fund each year, this allows for the carrying forward of funds allowing the City to save and plan for large
projects across multiple years. The movement of funds within the capital plan, fund, and budget require
City Council deliberation and approval, the goal is to increase transparency for citizens about the plan and
project opportunities.
In addition to the Capital Fund, this plan also leverages monies from the three impact fees collected by
the City: Parks, Pathways and Police. This document, while a great step forward toward the City’s goals,
is not intended to address the required elements of Idaho Code 67‐65: The Local Land Use Planning Act
or Idaho 67‐8208: Capital Improvements Plan. This document relies on regular updates of the parks,
pathways, and police capital plans and impact fee studies under Idaho Code. This document is intended
to take those priorities and leverage general fund dollars, outside funding/match, and the impact fees
collected by the City. To that end the City will in future fiscal years this plan will update as the City’s
master planning documents and impact fee capital plans update.
It is important to note, the City’s Capital Plan does not commit or assure funding in future years, nor does
it assure a timeline for completion of a project. The Plan is evaluated yearly based on current needs and
opportunities and is intended to serve as a guide to help direct priorities within the City’s annual
appropriation approval process.
Page | 5
GOALS
To better guide and support the City’s planning efforts that City has established the following goals and
objectives for capital planning. Goals will be used to guide the annual prioritization and funding process.
GOAL 1: PROVIDE TO THE PUBLIC A CLEAR, REALISTIC, AND FISCALLY CONSTRAINED 5‐YEAR
CAPITAL IMPROVEMENT PLAN.
a. Prioritize maintenance and operation of existing infrastructure ahead of system expansion.
b. Establish annual fiscal goals for saving/set asides to fund depreciation, replacement, and
planned construction.
c. Ensure that projects are properly developed through the scoping process‐ project development,
planning, savings, then construction/purchase.
GOAL 2: ESTABLISH A PROCESS FOR THE DEVELOPMENT OF PUBLIC FACILITY PLANS THAT
ADDRESS EXISTING SERVICES, DEFICIENCIES, AND FUTURE NEEDS.
a. Ensure each City service has completed and maintains a facility inventory, 5+ year master
facilities plan, and has an adopted level of service.
b. Ensure all facilities comply with state and federal service regulations.
c. Establish implementable and enforceable level of service standards.
d. Ensure development does not degrade the City’s adopted level of service without proper
mitigation.
GOAL 3: ENHANCE THE QUALITY OF LIFE IN EAGLE THROUGH THE PLANNED PROVISION OF
CAPITAL FACILITIES AND PUBLIC SERVICES THAT ARE PROVIDED EITHER DIRECTLY BY THE CITY
OR THROUGH COORDINATION WITH OTHER PUBLIC AND PRIVATE ENTITIES.
a. Work with the community to determine community needs and desires for services.
b. Prioritize maintenance of existing community investment ahead of expansion.
GOAL 4: PROVIDE NEEDED CAPITAL FACILITIES IN AN ECONOMIC, EFFICIENT, AND EQUITABLE
MANNER.
a. Use the capital planning process to identify city needs (project and maintenance), funding
opportunities, and partnership opportunities that serve all the citizens of Eagle.
b. Projects should be prioritized based on needs ahead of desires.
c. Use the City’s fiscal impact tool to help guide changes in land use to ensure both short term and
long tern fiscal sustainability (ability to fund infrastructure without the use of one‐time fees).
Page | 6
GOAL 5: ENSURE THAT ADEQUATE PUBLIC FACILITIES AND SERVICES FOR NEW
DEVELOPMENTS ARE AVAILABLE OR CONDITIONED TO BE PROVIDED AT THE TIME OF FINAL
LAND USE APPROVAL (FINAL PLAT/BUILDING PERMIT) SUCH THAT SERVICE PROVISION FOR
NEW DEVELOPMENTS WILL NOT LOWER EXISTING SERVICE LEVELS.
a. Condition development to pay their proportionate share of capital cost and the cost for system
expansion.
b. Maintain, update, implement the City’s development impact tool to evaluate the cost and
benefits of development on the City’s capital plan and operations.
c. Educate the public and elected official about the fiscal impact of different types of land uses.
d. Work to ensure that development does not degrade the adopted level of service for City
provided services‐ consider mitigation agreements, dedications, and other mechanisms to
ensure the equitable and consistent level of service.
GOAL 6: COORDINATE TRANSPORTATION IMPROVEMENT PLANS, PROGRAMS, AND
PARTNERSHIPS WITH THE EAGLE URBAN RENEWAL AGENCY, ACHD & ITD TO ENSURE THE
CITY’S VISION FOR FUTURE AND GROWTH‐RELATED ROAD PROJECTS ARE ACHIEVABLE.
a. Identify and plan for opportunities for cooperation.
b. Work to align goals, policies, and projects with partnering agencies.
c. Identify projects that will require a Cost‐share agreement and plan appropriately for this
contribution.
Page | 7
THE CAPITAL PLANNING PROCESS
The process used to develop the preliminary capital plan is collaborative and inclusive of all departments.
The capital planning process is designed to engage staff, elected officials, appointed officials, and the
public in the annual process with the goal of recognizing, reviewing, and prioritizing the needs of the City.
All identified projects are placed into one of three categories for project funding. The Capital Plan focuses
on two of these categories: Capital Projects and Capital Maintenance:
One of the functions of the capital planning process is to provide the City Council and funding partners
the best quality and most implementable projects possible. Projects that have been properly scoped and
developed tend to be completed on time, on budget, and are more likely to receive outside
funding/support. Projects should be scoped and properly thought through to address timeline,
participants (staff and public), cost (construction and planning), and the on‐going operation and
maintenance costs to the City.
Project development within the capital plan is a phased process that starts with the annual project request
list and continues through budgeting, construction, and maintenance; each phase builds on the previous
providing additional information and specificity to the scope of work.
The Capital Plan is developed in three main phases with increasing specificity: project identification,
project scoping, and project prioritization.
Capital Project:
Example Projects/Investments:
*New parks,
*New trails,
*Expansion of existing facilities
*Extending water main lines
Capital Maintenance Project: Operational Maintenance:
New project, facility, or investment that costs
more than $20,000 and has a life span of 5 years
or more. Customarily these projects are
associated with maintaining minimal levels of
service associated with growth or the
annexation of new lands. These projects often
have a dedicated funding source (i.e.
development impact fees) or are eligible for
outside funding and/or money (i.e. state and
federal transportation grants, etc.)
The replacement, upgrade, or renovation of an
existing capital project, facility, or investment
that has a cost of $10,000 or more and has a
lifespan of 5‐years or more. This does not
include ordinary maintenance necessary to
ensure continued day‐to‐day/annual use of the
facility.
The ordinary maintenance of a City facility and or
investment to ensure continued day‐to‐
day/annual use for its intended purpose and
function. These funds should be part of the
appropriate departments’ budget request.
NOTE: This fund is not specific to a project but is
establishes a saving for future capital
maintenance projects that would be in a future
year or that are unexpected expenditures.
NOTE: These requests should be part of the
annual department budget request. There will be
no change to this request process.
Example Projects/Investments: Example Projects/Investments:
*Computer replacements
*Replacement of existing fleet vehicles
*Renovation/replacement of specific park
*Replacement of flood damaged trails
*Upgrade booster pumps in wells
*Replacement of lid on reservoir
*Painting of buildings
*Screen protectors
*Sprinkler heads
*Printer toner/Ink
*Replacement of onsite customer meter
equipment
*Repair of chlorine equipment
*Water sampling
Project
Prioritization
Project
Identification
Project
Scoping
Page | 8
Phase 1: Project Identification: Annually each department, the public, and the City’s committees,
commissions, and boards will be part of the initial identification of capital projects and maintenance
requests.
Projects at this phase are conceptual and require a minimal amount of information. Additional
information can be added to the project as the project move through the process, but it is important to
note a project request must at a minimum include a project scope, timing, and estimated cost of
development. Each department will be responsible for developing projects in consultation with their
recommending or governing committees, commissions, or board. These projects can be developed year‐
round but are vetted in the annual capital planning process beginning in October of each year. The City
Council will receive a list of requests (capital and maintenance) by department for review. The Council
may choose to have a workshop to review the projects request list and provide direction as to which
projects move forward into project scoping.
Phase 2: Project Scoping: At the project scoping phase, departments will need to address/provide
additional project specific information including:
• Project need,
• Economic benefit,
• Annual operation and maintenance costs,
• Replacement/depreciation cycle,
• Potential for outside funding, and
• Phasing or sequencing that is required (or could be considered).
Projects should have a 5 to 7‐year timeline for construction or replacement, though projects with longer
construction timelines, significant development cost or existing infrastructure with planned replacement
beyond the 5 to 7‐year cycle may be considered and/or calculated into the annual capital maintenance
set‐aside.
In Early December, each department will be asked to score the projects based on the Preliminary Project
Request Scorecard. The scorecard evaluates:
Long Term Planning: Master Plans are prepared to provide the City with a valuable aid for
continuing efforts to meet and exceed goals set forth by City departments, committees, and the
citizens at‐large. Master Plans include those documents that have been prepared internally to
assure consistent adherence to industry best practices, as well as those documents that have been
created with the assistance of outside consultants. A component of master planning includes
public discussion and/or citizen engagement.
Public Health & Safety: Health/public safety includes police service, safe roads, safe drinking
water, and flood control. A police station would directly impact the citizens, scoring high in this
category. New softball fields may not directly affect the health/public safety of the citizens,
therefore scoring low.
Infrastructure: This item relates to infrastructure needs for the City of Eagle, including sidewalks,
lighting, parking facilities, municipal buildings, and recreational facilities, to name a few. This item
Page | 9
also includes partnerships or projects related to streets and highways in which the City is
partnering with ACHD or ITD.
Leveraged Funding: Capital improvement projects may be funded through sources other than
City funds. Grants through various agencies, public private partnerships, and donations can all be
sources of external funding for a project. The use of City dedicated funding non‐general fund
sources may be considered (impact fees, water fund, etc.).
Operational Budget: Some projects may impact the operating budget for the next few years or
for the life of the facility. A new facility will need to be staffed and supplied, therefore having an
impact on the operational budget for the life of the facility. Replacing a streetlight with a more
energy efficient model may decrease operational costs.
Quality of Life: Quality of life is a characteristic that makes the City a favorable place to live and
work. A large park with amenities to satisfy all community members would greatly impact the
quality of life. Regional projects that require local funding for a larger regional user group may be
considered.
Location & Timing: The timing and location of the project is an important attribute of the project.
If the project is not needed for many years, it would score low in this category. If the project is
close in proximity to many other projects and/or if a project is urgent or may need to be
completed before another one can be started, it would score high in this category.
Sustainability/Innovation: Projects that move the City towards more sustainable and energy
saving, produce solutions to solve new problems, and meet new challenges that come from being
a rapidly growing City (i.e., demographic, social, technological, and economic changes) that helps
the departments to adapt quickly and embrace change.
Phase 3: Project Prioritization: Project prioritization is a fiscally constrained process. For purposes of
capital planning, the City will use the following annual funding guidelines for City funds (this does not
include dollars carried forward from a previous fiscal year, grants, or funds that pass through the City
budget from an outside source):
$1.5M for Capital Maintenance Set‐Aside
$2.0M for Capital Projects (including restricted funds i.e., impact fees)
These thresholds may vary year to year based on economic climate and City Council
directives.
Projects may include engineering and design work, the development of construction plans, savings for
future investments, and/or construction of a physical project. The order and prioritization may be
influenced by the ability to fund with local dollars, the opportunity to leverage outside funds,
emergencies, or other factors that the Council sees as pertinent in a specific fiscal year. The year 1 of the
Capital Plan should mirror the next fiscal year’s appropriation but does not guarantee funding in years 2
through 5.
When constructing projects that will receive reimbursement post construction, the Council can direct
where reimbursements are to be placed within the City’s budget and if they are to be earmarked for
Page | 10
maintenance or for another project. The Council, through the Capital Plan, may establish triggers for the
commencement of a project. These triggers/conditions may be fiscal or based on the completion of other
work/agreements.
Once projects have been scoped and scored this information will be taken to the public for review and
comment. For the Fiscal Year 2024 Plan, the City held a public open house and utilized a townhall
meeting and several community group meetings to garner public comment.
The project prioritization process is
led by the City Council but will
include the results of the public
outreach efforts and the staff
scoring process. The Council will
utilize a paired comparison process
to help develop a prioritization list.
The paired comparison process
allows the Council to compare and
prioritize each project against every
other project scoped.
The Council may choose to have a
workshop to review the projects
request list and provide direction as
to which projects move forward.
The Council has prioritized Capital
Maintenance (the general upkeep
and maintenance of existing city facilities) over capital projects (new projects, facilities, or purchases).
The City Council will annually determine the appropriation of funds for both capital projects and capital
maintenance set‐aside as part of the municipal budgeting process. The Capital plan is a guide, similar to
the comprehensive plan, the goal is to educate and engage our citizens on the fiscal constraints that the
City faces while also creating a process for project request and active engagement in the prioritization of
projects.
Annually, the Council will conduct a public hearing to adopt the capital plan and to allow the public to
comment on the final project list before adoption. Adoption of the Capital Plan should be timed to
coordinate with the annual budget appropriation each fall.
Page | 11
FISCAL YEAR 2023: REVIEW & PROJECT STATUS
CAPITAL MAINTENANCE STATUS
Each year, the Capital Maintenance project list is based on need and the planned replacement schedule
of current capital infrastructure, but the capital maintenance set‐aside/budget is based on the amount
the City needs to set‐aside annually to ensure sufficient fundings across the entire capital network, even
if a project is not scheduled for that year. The Capital Maintenance set‐aside functions as a savings
account, allowing the City to address both planned and unplanned maintenance and repairs.
Capital Maintenance Projects (CM) identified and funded for Fiscal Year 23 equaled $3.02 million with
$2.38million in planned expenditures. At the end of Fiscal Year 2023 the Fund expended $256,727 of the
planned expenses. Below is the end of year status for capital maintenance in Fiscal Year 2023:
Incomplete projects can increase the demand on staff time and capacity, limiting the ability of the City to
complete scheduled and planned operation, maintenance, and replacement projects in their proper
timing. Incomplete projects should be evaluated to ensure that there is no impact to planned and
necessary improvements and to that there is no systemic or chronic issues in the ability to complete the
project.
Project No.Description FY 23 Budget Spent* % Complete Comments
PW CM‐1 Heritage Park 613,000.00$ 28,320.00$ 4.62% Preliminary eng. & savings for future
PW CM‐15 OK Park 130,000.00$ ‐$ 0.00%Defered by the Council to FY 24, Carry
Forward
IT CM‐7 Servers 8,500.00$ ‐$ 0.00% Defered to FY 24, Carry Forward
PW CM‐17 Jackson House 90,000.00$ 8,908.25$ 9.90%Occupancy Challenges, work bgan
9/2023, carry forward
TRL CP‐4 N. Channel Bank Repairs 550,000.00$ 133,273.40$ 24.23%Completed, savings should go to Capital
Reserves.
PW CM‐16 Equipment Replacement 2,500.00$ 3,699.00$ 147.96% Completed
TRL CM‐11 FEMA Trail Repair #4 215,000.00$ ‐$ 0.00%
Project defered, $ shifted to cover
increased cost in Library AC, carry
forward
TRL CM‐2 FEMA Trail Repairs 676,491.00$ ‐$ 0.00% Project complete in FY 22
PW CM‐18 Library Air Unit Upgrade (from ARPA) 70,400.00$ 100,330.00$ 142.51% Completed
PW CM‐19 Trolley 15,000.00$ 14,720.25$ 98.14% Repairs are on‐going
T&P CM‐1 Floodway/City Property Protection 10,000.00$ 957.00$ 9.57%
2,380,891.00$ 290,207.90$ 12.19%
FY23 Budget FY 23 Actual* % of Budget
Savings for future 1,695,762.75$ 71.22%
FY 2023 ‐ Capital Maintenance Year End Status
Page | 12
CAPITAL PROJECTS STATUS
Capital projects are new investments, construction, or purchases with a value of $20,000 or more. These
projects are ranked by department, evaluated through a public process, and then prioritized by the City
Council For Fiscal Year 2023 there were very few “new” projects added the capital projects list and as such
there was no new public participation in the prioritization process, the community scores from FY22 were
carried forward. The Fiscal Year 2023 funded priorities mirrored in the City’s Fiscal Year 2022‐2023
appropriation ordinance and budget. Capital Plan funding came from three specific funds: Capital (19
account), Pathway Impact Fees (25 account), and Park Impact Fees (08 account).
Capital Projects, including savings from previous fiscal years, for Fiscal Year 2023 equaled $7.72M million
with $3.5 million being new appropriations from the general fund. Additionally, the plan includes $4.5
million in American Recovery Act funding. Below is the status for the capital projects in FY 2023:
As seen above it should be anticipated that each year a portion of the Capital Projects fund will carry
forward monies that are earmarked for future year projects. This ability to plan and save for future needs
is a benefit of the Capital Plan, it reduces single year demands on the City’s general fund. Additionally,
incomplete projects may be a result of partner agency deferring/ un‐funding a project, project capacity
(too many projects in a year for staff to completed) or other bidding/construction supply challenges.
Project No.Description FY 23 Budget Spent* % Complete Comments
T&P CP‐1 State & Eagle Intersection 851,400.00$ ‐$ 0% Saving for FY 24/FY25 Construction
T&P CP‐3 Eagle Road Ped Bike Bridge 3,300,000.00$ 2,953,220.06$ 89% Substaintially Complete ‐ Painting and
plantings in floodway to be completed
PW CP‐2 City Owned Shop 350,000.00$ ‐$ 0% Saving for Future Construction
T&P CP‐6 Olde Park 600,000.00$ 22,051.25$ 4% Preliminary eng. & savings for future
P&R CP‐2 Regional Sports Park 2,589,000.00$ 2,232,560.74$ 86% On‐going construction
P&R CP‐8 Foothills Shooting Range 500,000.00$ 193,642.15$ 39% Under Contract for full amount
T&P CP‐2 Aikens Street Extension 680,000.00$ ‐$ 0% Saving for Future Construction
P&R CP‐9 Parks, Trails & Open Space Master Plan 100,000.00$ ‐$ 0% Staff capacity issue
No Number Parks Impact Fee Update 3,700.00$ 3,595.00$ 100% Completed, Unplanned Projet
PW CP‐9 Mace Park 136,800.00$ 12,343.75$ 9% Preliminary eng. & savings for future
PW CP‐11 Pamela Baker 276,200.00$ 86,628.00$ 0%
Will complete irrigation pump by end of
year
T&P CP‐12 Linder Road (SH 44 to FF) 40,000.00$ 3,950.00$ 0%
Waiting on contractor billing & saving
for future construction
T&P CP‐10 Three Cities River Crossing 25,000.00$ ‐$ 0% Carry forward to FY 24
TRL CM‐2 FEMA Trail Repairs 676,491.00$ ‐$ 0% Completed in FY 23
GEN CP‐1 Unanticipated Projects/Opportunities 75,000.00$ ‐$ 0% Added to 3CRX carry forward to FY 24
10,203,591.00$ 5,507,990.95$ 53.98%
FY23 Budget FY 23 Actual* % of Budget
Savings for future 3,060,005.00$ 29.99%
FY 2023 ‐ Capital Projets Year End Status
Page | 13
FY 23 INCREASED CAPITAL LIABILITY
While one of the functions of the Capital Plan is to identify projects and funding, the plan also helps the
City understand the increasing capital liability for the City. Capital Liability is the City’s cost/responsibility
to maintain, improved, or replace a piece of Capital Infrastructure once constructed or dedicated to the
City. In 2020, it was estimated that annual set aside to properly maintain the Capital Liability of the City’s
existing infrastructure was $1.25 million. That number has increased annually as the City has complete
capital projects and maintenance.
As part of the annual capital planning process, it was determined these costs need to be accounted for
and considered when the City is planning and budgeting for new capital infrastructure.
Through the Capital Maintenance planning process, the City estimated the annual cost needed to properly
save for the current and future upkeep of the City’s capital investment. This annual cost is used to guide
the Maintenance Set‐aside, a savings program of Capital Maintenance, within the budget. The City uses
a rate of $0.03 per dollar annually for each dollar of capital investment/liability the city currently holds.
Using this metric, the City’s increases capital liability for Fiscal Year 2023 is $168,725.32
Plans and projects under the control of another jurisdiction do not impact the City’s capital liability.
Additionally, the City does not include land costs in the capital maintenance set aside, only improvements
to the site. For example, the total cost for the Linder Road Sportsman’s Access was $500,352, the City
only accounts for the structure and site improvements as $286,910.
Capital Liability is an important consideration in the capital planning process. While Capital Projects (new
construction) is often off‐set by impact fees, grants, and public‐private partnerships the City’s Capital
Liability is reliant on the City’s General Fund (tax dollars and one‐time fees).
In Fiscal year 2023, the City’s capital liability increased by 9.9% to $1.53 million. This is the first time the
capital liability is higher than the $1.5 million annual funding guideline, see page 9. This increased cost
will be reflected in the FY25 planning process and may impact the FY25 Capital Planning prioritization
process. It is important to note that as the City grows and completes projects the City’s capital liability
and capital maintenance set aside will grow and eventually outpace the capital projects budget, $2 million
annually.
Page | 14
Page | 15
FY 2024‐28 CAPITAL PLAN
FY 2024‐28 CAPITAL MAINTENANCE
As discussed previously, the Fiscal Year 2022 to Fiscal Year 2026 Capital Plan was the first time the City
had established a 5‐year prioritized and fiscally constrained plan. The Fiscal Year 2024 will build on the
work of the previous plans refining the prioritization process and helping the Council evaluate project
capacity and its impact on implementation.
The plan considered the priorities of staff, the public, and the City Council within a fiscally constrained
framework, limiting the City Capital Project investment to only $2 million annually and placing Capital
Maintenance Projects (operation, maintenance, and repairs of existing investments) as a funding priority
ahead of new infrastructure investment.
Below are the projects identified and prioritized by the City of Eagle for Fiscal Year 2024 to Fiscal Year
2028. It is important to note that consistent with Idaho Statutes, funding of the Capital Plan is set of
annually through the City’s appropriation Ordinance, funding of projects from Fiscal Year 2025 to Fiscal
Year 2028 will be subject of the City’s annual prioritization process and the appropriation process and as
such are shown as “unfunded”.
As part of the FY24‐28 plan the Council established a new policy to limit the amount of money held in the
Capital Reserves within the Capital Fund to approximately $3.5M annually. The intent is to save for future
project but not create an excessive amount of unallocated reserves. The reserves amount is based on a
1‐year capital budget, for FY 24 the Capital Reserves was set at $3.18M.
While most capital plans focus on the funding of construction and investment into new infrastructure
often utilizing impact fees, grants, and other one‐time funds, they do not address the on‐going and annual
cost to the City for operation and maintenance. The City’s responsibility to operate, maintain, and replace
existing capital infrastructure falls to the City’s operating budget, and is mostly reliant on the general fund.
The City of Eagle maintains a significant portfolio of existing capital infrastructure, including municipal
buildings, parks, streetlights, a City‐owned water system, library, and existing public works equipment. As
part of the capital planning process the City Council reviewed the costs associated with the maintenance,
upgrade or replacement of existing capital projects, facilities, or investments.
Capital Maintenance, if not properly planned for, can quickly and significantly impact the City’s budget.
During the recession, many of the City’s capital facilities were placed on deferred maintenance due to
limited budgets and reserves, the City was not prepared to fund the existing investments without building
permit revenue to bolster the budget. For example, in Fiscal Year 2019 & Fiscal Year 2020 the City
expended over $3 million to replace the play equipment and splash pads in just two of the City’s parks
that had been impacted by deferred maintenance during the recession. Over the past 5 years, the City
has been able to bring most of the existing capital facilities into good repair and has begun the process of
Page | 16
inventorying facilities to plan for replacement, renovation, and upgrade. This work, combined with a fiscal
strategy to establish a capital maintenance set‐aside fund, money specific to maintenance, will help
safeguard the city during future economic downturns.
Each year the existing City Capital Portfolio will be evaluated for planned, the projects below, and
unplanned maintenance. Emergency or critical needs may result in the re‐ordering of projects in any given
year. A summary of the Capital Maintenance Project in priority order and by fiscal year is listed below.
This list provides limited details of the projects‐ total estimated project cost, impact fee eligibility, type of
project and total combined funding currently anticipated for the project. A detailed list including
estimated Capital Maintenance Set‐Aside and carry forward is available at the end of the document. The
FY 24 Capital Maintenance set‐aside is budgeted at $2.14M. The planned Capital Maintenance in FY 25‐
28 is estimated at $6.49M or approximately $1.62M annually.
Please note, Fiscal Year 2024 in the only funded year within the plan. Fiscal years 2025 to 2028 while
prioritized with require City Council appropriations in those specific years.
Page | 17
Fiscal Year 2024‐2028 Capital Maintenance Priorities
FY24 Rank CM #Project Name Details Request Total
Incomplete TRL CP‐4N. Channel Bank Repairs $ 100,000
1IT CM‐7 2024 City Hall Servers
Department: IT
Staff: Devonte Goodman
City Hall Servers
Year Requested: 2024
Priority: High
Amount Requested: $95K
FY 23‐27 PLAN YEAR: 2024
103,500$
4PW CM‐17 Jackson House
Department: Public Works
Staff: Eric Ziegenfuss
Jackson House
Year Requested: 2023
Priority: Planned FY 2023
Amount Requested: $100K
FY 23‐27 PLAN YEAR: 2023
100,000$
5IT CM‐3 2024 Backbone Infrastructure‐
City Hall & Library
Department: IT
Staff: Devonte Goodman
2024 Backbone Infrastructure
Year Requested: 2024
Priority: High
Amount Requested: $128K
FY 23‐27 PLAN YEAR: 2024
128,000$
6PW CM‐16 2024 Equipment Replacement
Department: Public Works
Staff: Eric Ziegenfuss
2024 Equipment Replacement
Year Requested: Annual
Priority: Planned Replacement
Amount Requested: $1.2K
FY 23‐27 PLAN YEAR: 2024
1,200$
8PW CM‐13 2024 Vehicle Replacement
Department: Public Works
2024 Vehicle Replacements
Year Requested: 2024
Priority: Annual Replacement
Amount Requested: $50K
FY 23‐27 PLAN YEAR: 2024
50,000$
9P&R CM‐1Heritage Park
Department: LRP&P & Public Works
Staff: Nichoel Baird Spencer
Heritage Park Renovation Design &
Engineering
Year Requested: 2023
Priority: Planned Replacement
Amount Requested: $450K
FY 23‐27 PLAN YEAR: 2023
1,050,000$
10 PW CM‐8 Library Roof
Department: Public Works
Staff: Eric Ziegenfuss
Library Roof Replacement
Year Requested: 2023
Priority: Planned Replacement
Amount Requested: $150K
FY 23‐27 PLAN YEAR: 2024
250,000$
13 PW CM‐15 OK Park Playground
Department: Public Works
Staff: Eric Ziegenfuss
Orville Krasen Park Playground
Year Requested: 2022
Priority: Planned FY 2022
Amount Requested: $130K
FY 23‐27 PLAN YEAR: 2023
130,000$
15 TP CM‐1 Floodway/City Property
Protection
Department: LRP&P
Staff: Nichoel Baird Spencer
2023 Floodway/Property Protection
Year Requested: Annual
Priority: Partnership
Amount Requested: $10K
FY 23‐27 PLAN YEAR: 2024
10,000$
FY 24 ‐ Funded
Page | 18
15 IT CM‐8Chamber Recording
Department: IT
Chambers Audio/Recording
Year Requested: 2023
Priority: High
Amount Requested: $80K
FY 23‐27 PLAN YEAR: 2024
80,000$
29 PW CM‐15 2023 & 2024 Trail Maintenance
Department: Public Works
Staff: Eric Ziegenfuss
2023 Trail Maintenance
Year Requested: 2024
Priority: Annual Planned Replacement
Amount Requested: $40K
FY 23‐27 PLAN YEAR: 2025
40,000$
21 TRL CM‐11 FEMA Repair 4A
Department: Planning & Zoning
Staff: Bill Vaughan
FEMA Trail Repair #4A
Year Requested: 2023,
Incomplete in FY 21, 22, & 23
Priority: FEMA Repair
Amount Requested: $272.3K
FY 23‐27 PLAN YEAR: 2023
104,000$
26 TRL CM‐4Greenbelt Merrill
Department: Public Works
Staff: Eric Ziegenfuss
Greenbelt Merrill Park
Year Requested: 2023
Priority: Planned Replacement
Amount Requested: $180K
FY 23‐27 PLAN YEAR: 2025
104,000$
2,146,700$
Request Total
2024 TOTAL:
Page | 19
FY 25 ‐ Unfunded
FY24 Rank CM #Project Name Details Request Total
7
IT CM‐32025 Backbone Infrastructure‐
City Hall & Library
Department: IT
2025 Backbone Infrastructure
Year Requested: 2025
Priority: High
Amount Requested: $15K
FY 23‐27 PLAN YEAR: 2025
15,000$
9
PW CM‐1Heritage Park
Department: LRP&P & PW
Staff: Eric Ziegenfuss
Heritage Park Renovation Construction
Year Requested: 2024
Priority: Planned Replacement
Amount Requested: $3M
FY 23‐27 PLAN YEAR: 2025
3,000,000$
No Rank
IT CM‐9Library Self‐check
Department: IT /Library
Staff: Devonte Goodman/Steve
Baumgartner
Self Check System
Year Requested: 2025
Priority: High
Amount Requested: $11.55K
FY 23‐27 PLAN YEAR: New
11,550$
17
PW CM‐132025 Vehicle Replacement
Department: Public Works
Staff: Eric Ziegenfuss
2025 Vehicle Replacements
Year Requested: 2025
Priority: Annual Replacement
Amount Requested: $60K
FY 23‐27 PLAN YEAR: 2025
110,000$
3,136,550$
Request Total 2025 TOTAL:
FY 26 ‐ Unfunded
FY24 Rank CM #Project Name Details
Request Total
12
IT CM‐32026 Backbone Infrastructure
Department: IT
Staff: Devonte Goodman
2026 Backbone Infrastructure
Year Requested: 2026
Priority: High
Amount Requested: $16K
FY 23‐27 PLAN YEAR: 2026
16,000$
13
IT CM‐6Plotter Replacement
Department: IT
Staff: Devonte Goodman
Plotter Replacement
Year Requested: 2026
Priority: Planned Replacement
Amount Requested: $12K
FY 23‐27 PLAN YEAR: 2026
12,000$
13
PW CM‐132026 Vehicle Replacement
Department: Public Works
Staff: Eric Ziegenfuss
2025 Vehicle Replacements
Year Requested: 2026
Priority: Annual Replacement
Amount Requested: $60K
FY 23‐27 PLAN YEAR: 2026
170,000$
Page | 20
19
PW CM‐19Trolley
Department: Public Works
Staff: Eric Ziegenfuss
Trolley Maintenance
Year Requested: FY24
Priority: Required Repair
Amount Requested: $60K
FY 23‐27 PLAN YEAR: Not
Programmed
60,000$
22
TP CM‐1Floodway/City Property
Protection
Department: LRP&P
Staff: Nichoel Baird Spencer
2023 Floodway/Property Protection
Year Requested: Annual
Priority: Partnership
Amount Requested: $10K
FY 23‐27 PLAN YEAR: 2025
10,000$ 23,24,27,31,37PW CM‐20 City Facilities Paving
Department: Public Works
Staff: Eric Ziegenfuss
Parking Lot Paving
Year Requested: 2024
Priority: Planned Replacement
Amount Requested: $390K
FY 23‐27 PLAN YEAR: 2025
390,000$
30
TRL CM‐344 Trail Repair
Department: Public Works
Staff: Eric Ziegenfuss
44 Trail Repair
Year Requested: 2026
Priority: Repair
Amount Requested: $227K
FY 23‐27 PLAN YEAR: 2026
227,000$
33
PW CM‐4Friendship Roof
Department: Public Works
Staff: Eric Ziegenfuss
Friendship Park Shelter Roof
Year Requested: 2023
Priority: Planned Replacement
Amount Requested: $7.5K
FY 23‐27 PLAN YEAR: 2025
7,500$
34
TRL CM‐10Mace Trail
Department: Planning & Zoning
Staff: Bill Vaughan
Mace Trail Modifications
Year Requested: 2026
Priority: Planned Repair
Amount Requested: $83K
FY 23‐27 PLAN YEAR: 2026
83,000$
35
PW CM‐152025 & 2026 Trail Maintenance
Department: Public Works
Staff: Eric Ziegenfuss
2025 Trail Maintenance
Year Requested: Annual
Priority: Planned Replacement
Amount Requested: $42K
FY 23‐27 PLAN YEAR: 2025
42,000$
1,017,500$
Request Total 2026 TOTAL:
Page | 21
FY 27 ‐ Unfunded
FY24 Rank CM #Project Name Details Request Total
2
IT CM‐72027 City Hall Servers
Department: IT
Staff: Devonte Goodman
2027 City Hall Servers
Year Requested: 2027
Priority: High
Amount Requested: $95K
FY 23‐27 PLAN YEAR: 2027
95,000$
32
PW CM‐14Picnic Tables & Benches
Department: Public Works
Staff: Eric Ziegenfuss
Picnic Table & Bench Replacement
Year Requested: 2027
Priority: Planned Replacement
Amount Requested: $11K
FY 23‐27 PLAN YEAR: 2027
11,000$
36
TRL CM‐6Lakemoor Trail
Department: Planning & Zoning
Staff: Bill Vaughan
Lakemoor Trail
Year Requested: 2024
Priority: Planned Replacement
Amount Requested: $321K
FY 23‐27 PLAN YEAR: 2025
321,000$
38
TRL CM‐5Greenbelt Lonesome Dove
Department: Planning & Zoning
Staff: Bill Vaughan
Greenbelt Lonesome Dove to
Edgewood
Year Requested: 2023
Priority: Planned Replacement
Amount Requested: $135K
FY 23‐27 PLAN YEAR: 2025
135,000$
39
TRL CM‐7Lonesome Dove Bridge
Department: Planning & Zoning
Staff: Bill Vaughan
Lonesome Dove Bridge Removal
Year Requested: 2024
Priority: Planned Replacement
Amount Requested: $30K
FY 23‐27 PLAN YEAR: 2025
30,000$
40
PW CM‐4Friendship Tennis
Department: Public Works
Staff: Eric Ziegenfuss
Friendship Park Tennis Courts
Year Requested: 2024
Priority: Planned Replacement
Amount Requested: $70K
FY 23‐27 PLAN YEAR: 2025
70,000$
42
TP CM‐1Floodway/City Property
Protection
Department: LRP&P
Staff: Nichoel Baird Spencer
2027 Floodway/Property Protection
Year Requested: Annual
Priority: Partnership
Amount Requested: $10K
FY 23‐27 PLAN YEAR: 2025
10,000$
44
PW CM‐4Friendship Playground
Department: Public Works
Friendship Park Playground
Replacement
Year Requested: 2024
Priority: Planned Replacement
Amount Requested: $150K
FY 23‐27 PLAN YEAR: 2025
150,000$
Page | 22
45
T&P CM‐11Eagle Road Arch Expansion
Department: Public Works
Staff: Eric Ziegenfuss
Eagle Road Arch
Year Requested: 2026
Priority: Planned Replacement
Amount Requested: $250K
FY 23‐27 PLAN YEAR: 2025
250,000$
45, 46, 47, PW CM‐2Sr Center Remodel ‐ Interior &
Extirior Paint & Flooring
Department: Public Works
Staff: Eric Ziegenfuss
Interior Sr. Center Paint
Year Requested: 2023
Priority: Planned Replacement
Amount Requested: $75K
FY 23‐27 PLAN YEAR: 2025
75,000$
49
PW CM‐152027 Trail Maintenance
Department: Public Works
Staff: Eric Ziegenfuss
2027 Trail Maintenance
Year Requested: Annual
Priority: Planned Replacement
Amount Requested: $8K
FY 23‐27 PLAN YEAR: 2027
8,000$
No Rank
IT CM‐102027 Backbone Infrastructure‐
Library
Department: IT /Library
Staff: Devonte Goodman/Steve
Baumgartner
2027 Backbone Infrastructure
Year Requested: 2025
Priority: High
Amount Requested: $10K
FY 23‐27 PLAN YEAR: New
10,000$
No Rank
IT CM‐11Library Security Replacement
Department: IT /Library
Staff: Devonte Goodman/Steve
Baumgartner
Library Security Replacement
Year Requested: 2025
Priority: High
Amount Requested: $42K
FY 23‐27 PLAN YEAR: New
42,000$
1,207,000$
Request Total 2027 TOTAL:
Page | 23
FY 28‐ Unfunded
FY24 Rank CM #Project Name Details Request Total
43
TP CM‐1Floodway/City Property
Protection
Department: LRP&P
Staff: Nichoel Baird Spencer
2028 Floodway/Property Protection
Year Requested: Annual
Priority: Partnership
Amount Requested: $10K
FY 23‐27 PLAN YEAR: Not
Programmed
10,000$
46
TRL CM‐8Clear Creek Trail
Department: Planning & Zoning
Staff: Bill Vaughan
Clear Creek Crossing
Year Requested: 2026
Priority: Planned Repair
Amount Requested: $617K
FY 23‐27 PLAN YEAR: 2025
617,000$
48
PW CM‐9Skate Bowl Replacement
Department: Public Works
Staff: Eric Ziegenfuss
Skate Bowl Replacement
Year Requested: 2025
Priority: Planned Replacement
Amount Requested: $500K
FY 23‐27 PLAN YEAR: 2026
500,000$
51
PW CM‐152028 Trail Maintenance
Department: Public Works
Staff: Eric Ziegenfuss
2028 Trail Maintenance
Year Requested: Annual
Priority: Planned Replacement
Amount Requested: $10K
FY 23‐27 PLAN YEAR: Not
Programmed
10,000$
1,137,000$
Request Total 2028 TOTAL:
A detailed scalable version of these tables can be found on Page 30 of this
document. A Capital Maintenance project maps can be found on
Page 38 of this document.
Page | 24
FY 2024‐28 CAPITAL PROJECTS
A full‐scale version of this table is available
on Page 50. A map & detailed descriptions
of the projects can be found on Page 43 of
this document.
Capital Projects are new projects,
facilities, and investments that cost
$20,000 or more and have a lifespan of 5‐
years or more. These projects generally
include new parks, trails or projects
associated with maintaining or increasing
the adopted level of service. These
projects often leverage impact fees,
grants, and public/private partnerships.
This classification includes plans and
studies for projects that are would upon
construction fall into this category.
A summary of the Capital Project in
priority order and by fiscal year is listed to
the right. This list provides limited details
of the projects ‐ total estimated project
cost, type of project and the timeline for
funding for the project. Most Capital
Projects leverage multiple funding
sources including impact fees, grants, and
public private partnerships. These details
are available in the detailed list at the end
of the document. A map of projects by
year is available at the end of the
document.
Planning/Study Savings Construction/Purchase
Page | 25
FUTURE & UNFUNDED PROJECTS
As the City’s Capital Plan is a 5‐year fiscally constrained document based on assumed funding levels and
limitations, each year there will be projects that are 1) incomplete (not completed within the planning
horizon), 2) not ready to be funded (need additional details or a partner agency), or 3) ranked low enough
overall that the City is unable to fund. Generally, projects ranked in the top 28 received funding and were
prioritized in the Fiscal Year 2024‐2028 Plan. Below is a list of Future/Unfunded projects:
FY 24 Rank Project
No.Project Name Project Cost Details Comments/Rational
31
TRL CP‐17Dry Creek & Dry Creek Canal $30K
(design only)
Department: Planning
Staff: Steve Noyes
$30K (Design Only) Requested
No Match
Med‐Low Public Score
Med‐Low Staff Score
Unfunded
Construct a trail and connection along Dry Creek and
the Dry Creek Canal south of the greenbelt. Based on
comments from the Council, new trail projects are
delayed until the Parks, Trails and Open Space Plan is
completed, the majority of trail projects are listed as
"unfunded" through FY28.
31
ED CP‐1Downtown Parking $750K
Department: Economic Development
Staff: TBD
$750K Requested
No Match
Med‐Low Public Score
Unfunded
Find land to partner in the construction a parking lot in
Downtown Eagle. Limited funding available
36
TRL CP‐16N. Channel Dry Creek Bridge $100K
(design only)
Department: Planning
Staff: Steve Noyes
$100K (Design Only)Requested
Impact fee eligible up to $1.02M
Med‐Low Public Score
Med‐Low Staff Score
Unfunded
Construct a bridge across Dry Creek north of Floating
Feather Road. Based on comments from the Council,
new trail projects are delayed until the Parks, Trails and
Open Space Plan is completed, the majority of trail
projects are listed as "unfunded" through FY28.
39
TRL CP‐8Trails Wayfinding & Branding $20K
Department: Planning
Staff: Steve Noyes
$20K Requested
No Match
Med‐Low Public Score
High Staff Score
Unfunded
Based on comments from the Council, new trail
projects are delayed until the Parks, Trails and Open
Space Plan is completed, the majority of trail projects
are listed as "unfunded" through FY28.
41
LIB CP‐2Bookmobile $250K
Department: Library
Staff: Steve Bumgarner
$250K
No Match
Low Public Score
Med‐Low Staff Score
Unfunded
Limited funding available
43
TRL CP‐12Water Trail Study $30K
(design only)
Department: Public Works, Planning, &
Recreation
Staff: Eric Ziegenfuss, Steve Noyes, &
Brian Allen
$30K (Study Only) Requested
No Match
Med‐Low Public Score
Med‐High Staff Score
Unfunded
Based on comments from the Council, new trail
projects are delayed until the Parks, Trails and Open
Space Plan is completed, the majority of trail projects
are listed as "unfunded" through FY28.
45
TRL CP‐21Laguna Point Bridge $30K
Department: Planning
Staff: Steve Noyes
$30K Requested
New Project
Unfunded
Based on comments from the Council, new trail
projects are delayed until the Parks, Trails and Open
Space Plan is completed, the majority of trail projects
are listed as "unfunded" through FY28.
46
TRL CP‐20Williamson River Ranch Bridge $100
(study only)
Department: Planning
Staff: Steve Noyes
$100K (Study Only) Requested
No Match
Low Public Score
Med‐Low Staff Score
Unfunded
Based on comments from the Council, new trail
projects are delayed until the Parks, Trails and Open
Space Plan is completed, the majority of trail projects
are listed as "unfunded" through FY28.
47
TRL CP‐9Trailhead Amenities ‐ Ada
Sports Complex $150K
Department: Planning & Public Works
Staff: Steve Noyes & Eric Ziegenfuss
$150K Requested
No Match
Med‐Low Public Score
Med‐High Staff Score
Unfunded
Based on comments from the Council, new trail
projects are delayed until the Parks, Trails and Open
Space Plan is completed, the majority of trail projects
are listed as "unfunded" through FY28.
FUTURE Capital Projects Beyond FY 28
Page | 26
REMOVED PROJECTS
For Fiscal Year 2024 to 2028 the City Council removed 9 projects from consideration in the Capital Plan.
Unlike the Unfunded Projects identified above, these projects will no longer be ranked or considered by
the City in future capital planning processes. For a removed project to return to the ranking process it
must be endorsed by a member of the City Council and rescoped by staff. A description and rational for
removal are include below:
FY 24
Rank Project No. Project Name FY 24 Rank Project No. Project Name
26
PW CP‐12Senior Center
Remodel 40
TRL CP‐11The Shores
Sportsman's
Access
34
LIB CP‐3Library Book
Pick‐up 42
TRL CP‐6All Weather
Trail Ada
Sports Park
34
P&R CP‐1Community/
Performing Arts
Study
43
TRL CP‐7Bike Skills
Park ‐ Ada
Sports
Complex
37
T&P CP‐11Eagle Road
Arch Expansion 48
P&R CP‐6Motocross
Study
38
T&P CP‐NEWEagle Memorial
Garden/Cemet
ery in Foothills
The City Completed the Community
Hall project in FY 22.
Moved to CM, funded in FY27
(T&P CP‐11) to provide for road
project completion
Removed by the Council. Work with
land owners to develop a facility but
not city owned.
This project is redundant to
the Mace Park Project (PW CP‐
9) scheduled for construction
in FY 24 and is located on the
same corridor.
This project is being
completed with existing
resources and the use of
recycled materials.
This project is being
completed through
donation and recycled
materials.
Locally undesirable project.
Removed by the City Council.
Comments/Rational Comments/Rational
Funded in Capital Maintenance
Program in FY 27 (PW CM‐2) ‐
Flooring, interior & Exterior painting,
further work should be scoped
before seeking funding
Removed per Library Director.
Lockers installed in 2023.
Removed Capital Projects FY 24‐FY 28
Page | 27
PLAN AMENDMENTS
One of the goals in adopting a capital plan was to provide the City Council a list of funding priorities for
both new capital projects and the ability to address and fund maintenance needs, both planned and
unplanned, within the City. Grants are a great funding tool to offset the fiscal burden of the City with
public and private dollars, but many grant applications require the City to commit or recognize the
required City match at the time of application. Under Idaho Code an existing Council cannot bind a future
Council, so all decisions about future‐year funding needs to be formally recognized and reversable if not
in the current fiscal year.
The intent of the process is to establish who, how, and when grants and alternative funding are applied
for, and to ensure that the Mayor and Council are aware of the financial commitments being made or
potentially required for the City. Additionally, this process allows the City to evaluate:
1) The importance of a project, considering other capital projects/needs within the City;
2) Understand the staffing and/or financial resources that the application places on the
City; and
3) The totality of the commitment that the City is committing.
To evaluate alternative funding and grants within the capital planning process, the following process
should be used for the evaluation of a potential grant application when presented outside of the annual
capital planning process.
1) Funding Identification: Each department should continually work to identify potential, existing,
and future outside funding sources to help develop capital projects and maintain the City’s
existing investment and operations, thus removing or decreasing the taxpayer’s burden.
2) Funding Evaluation: When a funding source is identified, staff should evaluate and prepare a
memo addressing the following:
a. Is this project/improvement identified within a City’s adopted plan? Which plan?
b. Is the project/improvement in the current Capital Plan?
c. Will this offset future City resources/expenditures as identified in the Capital Plan? What
fiscal year is the benefit realized?
d. Does the grant require up‐front funding by the City? If yes, what is the timeline for
reimbursements? What is the rate of reimbursement?
e. If the City moves forward with this application, does it need to be included in the current
budget or can it be included in a future year budget?
f. What is the cost to prepare the application (staff and monetary)?
3) Direction to Apply: There are three (3) processes to receive direction to undertake an application:
Page | 28
a. If the application requires less than a $5,000 City match and/or offsets a budgeted
expense within the current fiscal year, staff should brief the Mayor and seek his direction
to move forward into a formal application process.
b. If the application requires over $5,000 City match but is in a future fiscal year, staff
should:
i. Brief the Mayor about the application;
ii. Work with the Treasurer to identify City funding needs (both for completion of
the application and for construction);
iii. Integrate the project into the department budget request or work with staff to
integrate into the capital projects fund for consideration during the regular
budgeting workshop and hearings.
c. If the application has over $5,000 City match and is in the current fiscal year, staff
should:
i. Brief the Mayor;
ii. Work with the Treasurer and capital projects manager to identify City funding
needs, sources, and project timelines (both for completion of the application and
for construction);
iii. Agendize item for City Council approval. The Council should be provided the
following to guide their decision:
1. Grant evaluation information (from Section 2 above);
2. Identified funding needs, funding sources, where the City required match
will be budgeted from and a summary of how that request impacts other
funding sources within the City (from Treasurer/capital projects
manager);
3. Timeline for the application & project construction;
4. Identified fund for project reimbursement (if applicable).
d. Upon review, the Mayor and/or City Council can direct staff whether to move forward
with an application and/or amend the capital plan.
4) Funding Acceptance: Upon notice of an award, the formal award should be brought back to the
City Council for acceptance during a public meeting. The acceptance process should address the
final status of the following:
a. Total award amount – including the City’s required match;
b. Identified funding sources ‐ where the City‐required match will be budgeted from (a
budget amendment, if deemed necessary) and a summary of how that request impacts
other accounts/funds within the City (from Treasurer/Capital Projects manager);
c. Timeline for project construction;
d. Timeline for City reimbursement;
e. If directed by the Council, an amendment to the capital plan.
Page | 29
APPENDIX
Fiscal Year 2024‐2028 Capital Maintenance Priorities FY24 Rank CM #Project Name Details Request Total New FY 24 GF Request FY 23 Carry Forward FY 24 Reserve Transfer Outside Funding Comments Incomplete TRL CP‐4N.Channel Bank Repairs $ 100,000 $‐ $ 100,000 $‐ $‐ To be completed in FY23, contingency if highwater limits completion 1IT CM‐72024 City Hall ServersDepartment: ITStaff: Devonte GoodmanCity Hall ServersYear Requested: 2024Priority: HighAmount Requested: $95KFY 23‐27 PLAN YEAR: 2024 103,500$ 95,000$ 8,500$ ‐$ ‐$ Increased by $8.5K for FY23 Server replacement that was not completed. 4PW CM‐17 Jackson HouseDepartment: Public WorksStaff: Eric ZiegenfussJackson HouseYear Requested: 2023Priority: Planned FY 2023Amount Requested: $100KFY 23‐27 PLAN YEAR: 2023 100,000$ ‐$ 90,000$ ‐$ 10,000$ Incomplete in FY23 Carry forward $100K from FY235IT CM‐32024 Backbone Infrastructure‐ City Hall & LibraryDepartment: ITStaff: Devonte Goodman2024 Backbone InfrastructureYear Requested: 2024Priority: HighAmount Requested: $128KFY 23‐27 PLAN YEAR: 2024 128,000$ 128,000$ ‐$ ‐$ ‐$ Combined Library & City Hall into single project. Library changed funding from off the top to department‐ these are projects previously under the Library board6PW CM‐16 2024 Equipment Replacement Department: Public WorksStaff: Eric Ziegenfuss2024 Equipment ReplacementYear Requested: AnnualPriority: Planned ReplacementAmount Requested: $1.2KFY 23‐27 PLAN YEAR: 2024 1,200$ 1,200$ ‐$ ‐$ ‐$ Project could be removed from CM and placed in Public works annual budget request8PW CM‐13 2024 Vehicle ReplacementDepartment: Public Works2024 Vehicle ReplacementsYear Requested: 2024Priority: Annual ReplacementAmount Requested: $50KFY 23‐27 PLAN YEAR: 2024 50,000$ 50,000$ ‐$ ‐$ ‐$ Mayor has requested replacement be budgeted annually and accumulate/CF9 P&R CM‐1 Heritage Park Department: LRP&P & Public Works Staff: Nichoel Baird SpencerHeritage Park Renovation Design & EngineeringYear Requested: 2023Priority: Planned ReplacementAmount Requested: $450KFY 23‐27 PLAN YEAR: 2023 1,050,000$ 450,000$ 600,000$ ‐$ ‐$ Carry forward $600K from FY23 & add 450K in FY24 = 1.05M Total carry forward to construction on FY 25FY 24 ‐ FundedPAGE I 3 0
10 PW CM‐8 Library RoofDepartment: Public WorksStaff: Eric ZiegenfussLibrary Roof ReplacementYear Requested: 2023Priority: Planned ReplacementAmount Requested: $150KFY 23‐27 PLAN YEAR: 2024 250,000$ 250,000$ ‐$ ‐$ ‐$ Critical Project Delayed in FY 23 priorities to FY24 Staff took $100K fromTRL CM‐11: FEMA Trail Repairs to fund shortfall here. 13 PW CM‐15 OK Park PlaygroundDepartment: Public WorksStaff: Eric ZiegenfussOrville Krasen Park PlaygroundYear Requested: 2022Priority: Planned FY 2022Amount Requested: $130KFY 23‐27 PLAN YEAR: 2023 130,000$ ‐$ 130,000$ ‐$ ‐$ $ 130K in carry forward from FY 2315 TP CM‐1Floodway/City Property ProtectionDepartment: LRP&PStaff: Nichoel Baird Spencer2023 Floodway/Property Protection Year Requested: AnnualPriority: PartnershipAmount Requested: $10KFY 23‐27 PLAN YEAR: 2024 10,000$ 10,000$ ‐$ ‐$ ‐$ Preliminary discussions with FCD#10 to address issues at the Dry Creek Tunnel15 IT CM‐8 Chamber RecordingDepartment: ITChambers Audio/RecordingYear Requested: 2023Priority: HighAmount Requested: $80KFY 23‐27 PLAN YEAR: 2024 80,000$ 80,000$ ‐$ ‐$ ‐$ 29 PW CM‐15 2023 & 2024 Trail MaintenanceDepartment: Public WorksStaff: Eric Ziegenfuss2023 Trail MaintenanceYear Requested: 2024Priority: Annual Planned Replacement Amount Requested: $40KFY 23‐27 PLAN YEAR: 202540,000$ 20,000$ ‐$ 20,000$ ‐$ Laguna Natural Surface Trail & Patch/Sealing of root repairs throughout the system21 TRL CM‐11 FEMA Repair 4ADepartment: Planning & Zoning Staff: Bill VaughanFEMA Trail Repair #4AYear Requested: 2023,Incomplete in FY 21, 22, & 23Priority: FEMA RepairAmount Requested: $272.3KFY 23‐27 PLAN YEAR: 2023 104,000$ 104,000$ ‐$ ‐$ ‐$ 26 TRL CM‐4 Greenbelt MerrillDepartment: Public WorksStaff: Eric ZiegenfussGreenbelt Merrill ParkYear Requested: 2023Priority: Planned ReplacementAmount Requested: $180KFY 23‐27 PLAN YEAR: 2025 104,000$ 2,146,700$ 1,188,200$ 928,500$ 20,000$ 10,000$ Request Total New FY 24 GF Request FY 23 Carry Forward FY 24 Reserve Transfer Outside Funding2024 TOTAL: TRL CM‐11 incomplete in FY 21,22,& 23. Funding requested for FY26 forTRL CM‐11. Per CC wrksp 5/18 CF $maybe leveraged for the completion of TRL CM‐4, if partnership can be secured.Staff moved $100K to PW CM‐8: Library Roof to cover current estimate To be determined may be funded with $ from TRL CM‐11PAGE I 3 1
FY 25 ‐ UnfundedFY24 Rank CM #Project Name DetailsRequest Total New FY 25 GF Request FY 24 Carry Forward FY 25 Reserve Transfer Outside FundingComments 7IT CM‐32025 Backbone Infrastructure‐ City Hall & LibraryDepartment: IT2025 Backbone InfrastructureYear Requested: 2025Priority: HighAmount Requested: $15KFY 23‐27 PLAN YEAR: 2025 15,000$ 15,000$ ‐$ ‐$ Combined Library & City Hall into single project. Library changed funding from off the top to department‐ these are projects previously under the Library board9PW CM‐1Heritage Park Department: LRP&P & PWStaff: Eric ZiegenfussHeritage Park Renovation Construction Year Requested: 2024Priority: Planned ReplacementAmount Requested: $3MFY 23‐27 PLAN YEAR: 2025 3,000,000$ 1,175,000$ 1,050,000$ 775,000$ ‐$ Carry forward from FY 23 & FY24 = $1,050,000 offset to construction. Could use reserves to off set the $700K over the annual set‐aside No RankIT CM‐9Library Self‐checkDepartment: IT /LibraryStaff: Devonte Goodman/Steve BaumgartnerSelf Check SystemYear Requested: 2025Priority: HighAmount Requested: $11.55KFY 23‐27 PLAN YEAR: New 11,550$ 11,550$ ‐$ ‐$ Library changed funding from off the top to department‐ these are projects previously under the Library board 17PW CM‐132025 Vehicle ReplacementDepartment: Public WorksStaff: Eric Ziegenfuss2025 Vehicle ReplacementsYear Requested: 2025Priority: Annual ReplacementAmount Requested: $60KFY 23‐27 PLAN YEAR: 2025 110,000$ ‐$ 50,000$ 60,000$ ‐$ Mayor has requested replacement be budgeted annually and accumulate/CF. Funding in FY 25 as reserves 3,136,550$ 1,201,550$ 1,100,000$ 835,000$ ‐$ Request Total New FY 25 GF Request FY 24 Carry Forward FY 25 Reserve Transfer Outside Funding 2025 TOTAL:PAGE I 3 2
FY 26 ‐ UnfundedFY24 Rank CM #Project Name DetailsRequest Total New FY 26 GF Request FY 25 Carry Forward FY 26 Reserve Transfer Outside FundingComments 12IT CM‐32026 Backbone InfrastructureDepartment: ITStaff: Devonte Goodman2026 Backbone InfrastructureYear Requested: 2026Priority: HighAmount Requested: $16KFY 23‐27 PLAN YEAR: 2026 16,000$ 16,000$ ‐$ ‐$ ‐$ 13IT CM‐6Plotter ReplacementDepartment: ITStaff: Devonte GoodmanPlotter ReplacementYear Requested: 2026Priority: Planned ReplacementAmount Requested: $12KFY 23‐27 PLAN YEAR: 2026 12,000$ 12,000$ ‐$ ‐$ ‐$ 13PW CM‐132026 Vehicle ReplacementDepartment: Public WorksStaff: Eric Ziegenfuss2025 Vehicle ReplacementsYear Requested: 2026Priority: Annual ReplacementAmount Requested: $60KFY 23‐27 PLAN YEAR: 2026170,000$ 60,000$ 110,000$ ‐$ ‐$ Mayor has requested replacement be budgeted annually and accumulate/CF. Funding in FY 25 as reserves 19PW CM‐19TrolleyDepartment: Public WorksStaff: Eric ZiegenfussTrolley MaintenanceYear Requested: FY24Priority: Required RepairAmount Requested: $60KFY 23‐27 PLAN YEAR: Not Programmed60,000$ 60,000$ ‐$ ‐$ ‐$ Need to talk about the functionality of the trolley of this is delayed ‐ may need to use reserves to advance 22TP CM‐1Floodway/City Property ProtectionDepartment: LRP&PStaff: Nichoel Baird Spencer2023 Floodway/Property Protection Year Requested: AnnualPriority: PartnershipAmount Requested: $10KFY 23‐27 PLAN YEAR: 2025 10,000$ 10,000$ ‐$ ‐$ ‐$ Removed year, this will be inserted in the years where the program has capacity and they priority is high enough to be considered. 23,24,27,31,37PW CM‐20 City Facilities Paving Department: Public WorksStaff: Eric ZiegenfussParking Lot PavingYear Requested: 2024Priority: Planned ReplacementAmount Requested: $390KFY 23‐27 PLAN YEAR: 2025390,000$ 390,000$ ‐$ ‐$ ‐$ Grouped with other parking projects to be processed as single contract: CH, Lib, Guerber, Merrill, Sr Center, Ada/Eagle30TRL CM‐344 Trail RepairDepartment: Public WorksStaff: Eric Ziegenfuss44 Trail RepairYear Requested: 2026Priority: RepairAmount Requested: $227KFY 23‐27 PLAN YEAR: 2026 227,000$ 227,000$ ‐$ ‐$ ‐$ Based on CC comments: No construction until the completion of the PT&OS Master PlanPAGE I 3 3
33PW CM‐4Friendship RoofDepartment: Public WorksStaff: Eric ZiegenfussFriendship Park Shelter RoofYear Requested: 2023Priority: Planned ReplacementAmount Requested: $7.5KFY 23‐27 PLAN YEAR: 20257,500$ 7,500$ ‐$ ‐$ ‐$ 34TRL CM‐10Mace TrailDepartment: Planning & Zoning Staff: Bill VaughanMace Trail ModificationsYear Requested: 2026Priority: Planned RepairAmount Requested: $83KFY 23‐27 PLAN YEAR: 202683,000$ 83,000$ ‐$ ‐$ ‐$ Year Requested Council Direction was for it to be Subject to development‐ Could be removed35PW CM‐152025 & 2026 Trail Maintenance Department: Public WorksStaff: Eric Ziegenfuss2025 Trail MaintenanceYear Requested: AnnualPriority: Planned ReplacementAmount Requested: $42KFY 23‐27 PLAN YEAR: 2025 42,000$ 42,000$ ‐$ ‐$ ‐$ Combined FY 25 & 26 Projects into a single project 1,017,500$ 907,500$ 110,000$ ‐$ ‐$ Request Total New FY 26 GF Request FY 25 Carry Forward FY 26 Reserve Transfer Outside Funding2026 TOTAL:PAGE I 3 4
FY 27 ‐ Unfunded FY24 Rank CM #Project Name DetailsRequest Total New FY 27 GF Request FY 26 Carry Forward FY 27 Reserve Transfer Outside FundingComments 2IT CM‐72027 City Hall ServersDepartment: ITStaff: Devonte Goodman2027 City Hall ServersYear Requested: 2027Priority: HighAmount Requested: $95KFY 23‐27 PLAN YEAR: 2027 95,000$ 95,000$ ‐$ ‐$ ‐$ 32PW CM‐14Picnic Tables & BenchesDepartment: Public WorksStaff: Eric ZiegenfussPicnic Table & Bench Replacement Year Requested: 2027Priority: Planned ReplacementAmount Requested: $11KFY 23‐27 PLAN YEAR: 2027 11,000$ 11,000$ ‐$ ‐$ ‐$ 36TRL CM‐6Lakemoor TrailDepartment: Planning & Zoning Staff: Bill VaughanLakemoor TrailYear Requested: 2024Priority: Planned ReplacementAmount Requested: $321KFY 23‐27 PLAN YEAR: 2025 321,000$ 321,000$ ‐$ ‐$ ‐$ 38TRL CM‐5Greenbelt Lonesome DoveDepartment: Planning & Zoning Staff: Bill VaughanGreenbelt Lonesome Dove to Edgewood Year Requested: 2023Priority: Planned ReplacementAmount Requested: $135KFY 23‐27 PLAN YEAR: 2025135,000$ 135,000$ ‐$ ‐$ ‐$ 39TRL CM‐7Lonesome Dove BridgeDepartment: Planning & Zoning Staff: Bill VaughanLonesome Dove Bridge Removal Year Requested: 2024Priority: Planned ReplacementAmount Requested: $30KFY 23‐27 PLAN YEAR: 202530,000$ 30,000$ ‐$ ‐$ ‐$ 40PW CM‐4Friendship TennisDepartment: Public WorksStaff: Eric ZiegenfussFriendship Park Tennis CourtsYear Requested: 2024Priority: Planned ReplacementAmount Requested: $70KFY 23‐27 PLAN YEAR: 202570,000$ 70,000$ ‐$ ‐$ ‐$ Based on CC comments: No construction until the completion of the PT&OS Master PlanPAGE I 3 5
42TP CM‐1Floodway/City Property ProtectionDepartment: LRP&PStaff: Nichoel Baird Spencer2027 Floodway/Property Protection Year Requested: AnnualPriority: PartnershipAmount Requested: $10KFY 23‐27 PLAN YEAR: 202510,000$ 10,000$ ‐$ ‐$ ‐$ Removed year, this will be inserted in the years where the program has capacity and they priority is high enough to be considered. 44PW CM‐4Friendship PlaygroundDepartment: Public WorksFriendship Park Playground ReplacementYear Requested: 2024Priority: Planned ReplacementAmount Requested: $150KFY 23‐27 PLAN YEAR: 2025150,000$ 150,000$ ‐$ ‐$ ‐$ 45T&P CM‐11Eagle Road Arch Expansion Department: Public WorksStaff: Eric ZiegenfussEagle Road ArchYear Requested: 2026Priority: Planned ReplacementAmount Requested: $250KFY 23‐27 PLAN YEAR: 2025250,000$ 250,000$ ‐$ ‐$ ‐$ Moved from CP to CM. Placed in FY 26 by the CC to follow the completion of State and Eagle Intersection 45, 46, 47, PW CM‐2Sr Center Remodel ‐ Interior & Extirior Paint & Flooring Department: Public WorksStaff: Eric ZiegenfussInterior Sr. Center PaintYear Requested: 2023Priority: Planned ReplacementAmount Requested: $75KFY 23‐27 PLAN YEAR: 202575,000$ 75,000$ ‐$ ‐$ ‐$ Need a Scope for the Senior center this is a holding spot for the identified projects to date49PW CM‐152027 Trail MaintenanceDepartment: Public WorksStaff: Eric Ziegenfuss2027 Trail MaintenanceYear Requested: AnnualPriority: Planned ReplacementAmount Requested: $8KFY 23‐27 PLAN YEAR: 20278,000$ 1,000$ ‐$ 7,000$ ‐$ Advanced due to capacity and project sizeNo RankIT CM‐102027 Backbone Infrastructure‐Library Department: IT /LibraryStaff: Devonte Goodman/Steve Baumgartner2027 Backbone InfrastructureYear Requested: 2025Priority: HighAmount Requested: $10KFY 23‐27 PLAN YEAR: New 10,000$ 10,000$ ‐$ ‐$ ‐$ Library changed funding from off the top to department‐ these are projects previously under the Library board No RankIT CM‐11Library Security ReplacementDepartment: IT /LibraryStaff: Devonte Goodman/Steve BaumgartnerLibrary Security ReplacementYear Requested: 2025Priority: HighAmount Requested: $42KFY 23‐27 PLAN YEAR: New 42,000$ 42,000$ ‐$ ‐$ ‐$ Library changed funding from off the top to department‐ these are projects previously under the Library board 1,207,000$ 1,200,000$ ‐$ 7,000$ ‐$ Request Total New FY 27 GF Request FY 26 Carry Forward FY 27 Reserve Transfer Outside Funding2027 TOTAL:PAGE I 3 6
FY 28‐ Unfunded FY24 Rank CM #Project Name DetailsRequest Total New FY 28 GF Request FY 27 Carry Forward FY 28 Reserve Transfer Outside FundingComments 43TP CM‐1Floodway/City Property ProtectionDepartment: LRP&PStaff: Nichoel Baird Spencer2028 Floodway/Property Protection Year Requested: AnnualPriority: PartnershipAmount Requested: $10KFY 23‐27 PLAN YEAR: Not Programmed10,000$ 10,000$ ‐$ ‐$ ‐$ Removed year, this will be inserted in the years where the program has capacity and they priority is high enough to be considered. 46TRL CM‐8Clear Creek TrailDepartment: Planning & Zoning Staff: Bill VaughanClear Creek CrossingYear Requested: 2026Priority: Planned RepairAmount Requested: $617KFY 23‐27 PLAN YEAR: 2025617,000$ 617,000$ ‐$ ‐$ ‐$ Based on CC comments: No construction until the completion of the PT&OS Master Plan48PW CM‐9Skate Bowl ReplacementDepartment: Public WorksStaff: Eric ZiegenfussSkate Bowl ReplacementYear Requested: 2025Priority: Planned ReplacementAmount Requested: $500KFY 23‐27 PLAN YEAR: 2026500,000$ 500,000$ ‐$ ‐$ ‐$ 51PW CM‐152028 Trail MaintenanceDepartment: Public WorksStaff: Eric Ziegenfuss2028 Trail MaintenanceYear Requested: AnnualPriority: Planned ReplacementAmount Requested: $10KFY 23‐27 PLAN YEAR: Not Programmed10,000$ 10,000$ ‐$ ‐$ ‐$ 1,137,000$ 1,137,000$ ‐$ ‐$ ‐$ Request Total New FY 28 GF Request FY 27 Carry Forward FY 28 Reserve Transfer Outside Funding52TRL CM‐9South Bank Trail Merrill Park to Eagle Road Department: Planning & Zoning Staff: Bill VaughanSouth Bank Trail Merrill Park to Eagle RoadYear Requested: 2028Priority: UpgradeAmount Requested: $1.15MFY 23‐27 PLAN YEAR: Not ProgrammedUnprogramed & Unfunded Projects 2028 TOTAL:PAGE I 3 7
FISCAL YEAR 2024 –FUNDED CAPITAL MAINTENANCE UNMAPPED: IT CM‐7: Servers City Hall IT CM‐3: City Hall & Library Backbone Infrastructure PW CM‐16: Equipment Replacement PW CM‐13: Vehicle Replacement LIB CM‐7: Library Backbone Infrastructure T&P CM‐1: Floodway/City Property Protection PW CM‐15: Trail Maintenance PW CM‐8: Library Roof PW CM‐17: Jackson House PW CM‐1: Heritage Park Planning PW CM‐15: OK Park Playground TRL CP‐4: N.Channel Bank RepairsTRL CM‐3: SH‐44 Trail IT CM‐8: Chambers Recording Tentative Projects: TRL CM‐11: FEMA Trail Repair 4A TRL CM‐4: Greenbelt Merrill Page | 38
CAPITAL MAINTENANCE FISCAL YEAR 2025 – UNFUNDED UNMAPPED: PW CM‐13: Vehicle Replacement IT CM‐3: City Hall & Library Backbone Infrastructure PW CM‐1: Heritage Park Renovation IT CM‐9:Library Self Check Page | 39
CAPITAL MAINTENANCE FISCAL YEAR 2026 ‐ UNFUNDED UNMAPPED: P&Z CM‐1 Floodway/City Property Protection IT CM‐6: Plotter Replacement PW CM‐13: Vehicle Replacement PW CM‐19: Trolley IT CM‐3: City Hall Backbone Infrastructure PW CM‐15: Trail Maintenance PW CM‐20: City Facilities Paving PW CM‐1: Heritage Park Renovation TRL CM‐3: 44 Trail Repair PW CM‐4: Friendship Park Roof PW CM‐10: Mace Trail Page | 40
CAPITAL MAINTENANCE FISCAL YEAR 2027‐ UNFUNDED UNMAPPED: P&Z CM‐1 Floodway/City Property Protection PW CM‐13: Vehicle Replacement PW CM‐14: Picnic Table & Benches PW CM‐15: Trail Maintenance IT CM‐7: City Hall Servers LIB CM‐7: Library Backbone Infrastructure IT CM‐11: Library Security Replacement TRL CM‐6: Lakemoor Trail TRL CM‐8: Clear Creek Crossing TRL CM‐5/TRL CM‐7: Greenbelt Lonesome Dove/Lonesome Dove Bridge PW CM‐4: Friendship Park Tennis Court & Playground T&P CM‐11: Eagle Road Arch PW CM‐2: Senior Center Remodel Page | 41
4
FISCAL YEAR 2028 ‐ FUNDED CAPITAL MAINTENANCE UNMAPPED: P&Z CM‐1: Floodway/City Property Protection PW CM‐15: Trail Maintenance TRL CM‐8: Clear Creek Trail PW CP‐9: Skate Bowl Replacement Page | 42
FY 24 Rank Project No. Project Name Project Cost FY 24 FY 25 FY 26 FY 27 FY 28
Incomplete
FY 23
GEN‐CP‐1
T&P CP‐10 Three Cities River Crossing (3CRX)100,000$
Incomplete
FY 23 T&P CP‐3Eagle Road Ped‐Bike Bridge 30,000$
1T&P CP‐1 State & Eagle Intersection $ 2,026,000
2PW CP‐2City Owned Shop $ 5,200,000
3T&P CP‐1Olde Park Extension $ 600,000
4P&R CP‐2Regional Sports Park ‐ Phase 1 $ 12,000,000
5P&R CP‐8 Foothills Shooting Sport Park $ 4,500,000
6T&P CP‐2Aikens Street Extension $ 855,000
7TRL CP‐19 Linder Road Underpass @ N. Channel $ 15,000
9PW CP‐13 City Hall Facility Projects $ 425,000
10 T&P CP‐12 Linder Road (SH‐44 to FF) $ 1,200,000
11 P&R CP‐9Parks, Trails & Open Space Master Plan $ 287,000
12 POL CP‐1 Police Substation 615,000$
14 P&R CP‐7 Charlie Wood Park $ 500,000
16 ED CP‐6Excess ROW‐ State Street $ 30,000
17 P&R CP‐10 Pamela Baker Park $ 2,200,000
18 ED CP‐5 Idaho Street Streetscape Improvements $ 600,000
20 ED CP‐31st Street Festival Street $ 1,147,000
22 P&R CP‐11 Mace Park $ 500,000
23/39 T&P CP‐8
T&P CP‐9 Ped/Bike Studies ‐ FF & BL Rds. $ 200,000
No Rank PW CP‐17 Fleet Expansion $ 50,000
24 P&R CP‐12 Merrill Park Storage Building $ 30,000
27 ED CP‐7 Downtown Façade Improvement $ 50,000
28 PW CP‐7City Entry Sign Plan $ 10,000
26 & 35 TRL CP‐15 S. Channel @ Eagle Road Ped/Bike Crossing
(Bridge & Underpass) $ 100,000
No Rank LIB CP‐1Library Facilities Master Plan $ 150,000
Funded Capital Projects FY 24‐FY 28
Planning/Study Savings Construction/Purchase
Page | 43
FY 24 RankProject No.Project Name Project Cost DetailsComments/Rational FY 24‐28 Requested Amount FY23 Carry Forward/SavingsPlan Years GF by Year Impact feesReserve Transfer by Year Outside funding Total Project Balance % Funded in FY 24‐28 Plan % Funded per Total project costIncomplete GEN‐CP‐1/ T&P CP‐10Three Cities River Crossing (3CRX)100,000$ Delayed due to regional coordination efforts Study Completion FY24This is a regional project in the COMPASS Long‐range Transportation Plan. It requires interagency review of the feasibility Study. The agency partners have asked for additional review as a resiliency project (floodway protection and protection of the Boise wastewater treatment plant) in addition to just transportation connectivity & congestion. $ 100,000.00 $ 100,000.00 FY24 $‐ $‐ $‐ $ 100,000.00 100% 100%Incomplete T&P CP‐3Eagle Road Ped‐Bike Bridge 30,000$ Delayed due to highwaterCompletion FY24Carried forward to complete final Landscape and graffiti coating after water level drops $ 30,000.00 $ 30,000.00 FY24 $‐ $‐ $ 28,000.00 $ 30,000.00 100% 100%FY 24 162,000.00$ ‐$ ‐$ ‐$ FY 25‐$ ‐$ ‐$ 1,013,000.00$ FY 26‐$ ‐$ ‐$ ‐$ FY 27‐$ ‐$ ‐$ ‐$ FY 28‐$ ‐$ ‐$ ‐$ FY 24‐$ 100,000.00$ 275,000.00$ FY 25 250,000.00$ ‐$ ‐$ 25,000.00$ FY 26 250,000.00$ ‐$ ‐$ 25,000.00$ FY 27 250,000.00$ ‐$ ‐$ 25,000.00$ FY 28 250,000.00$ ‐$ ‐$ 25,000.00$ FY 24 16,000.00$ ‐$ ‐$ ‐$ FY 25‐$ ‐$ ‐$ ‐$ FY 26‐$ ‐$ ‐$ ‐$ FY 27‐$ ‐$ ‐$ ‐$ FY 28‐$ ‐$ ‐$ ‐$ FY 24‐$ 250,000.00$ ‐$ FY 25 250,000.00$ ‐$ ‐$ ‐$ FY 26 250,000.00$ ‐$ ‐$ ‐$ FY 27 250,000.00$ ‐$ ‐$ ‐$ FY 28 250,000.00$ ‐$ ‐$ ‐$ Funded Capital Projects FY 24‐FY 28100%35%100%10%600,000.00$ 100%4Regional Sports Park ‐ Phase 11State & Eagle IntersectionDepartment: LRP&PStaff: Nichoel Baird Spencer$1.013M Requested$1.013 Match from Eagle URAACHD Cost Share Med‐High Public ScoreHigh Staff Score Construction FY24 & FY25T&P CP‐1 $ 5,200,000 $ 2,026,000 P&R CP‐2Department: LRP&PStaff: Nichoel Baird SPencer & Eric Ziegenfuss$12M Design & ConstructionImpact Fee Eligible up to $4.9MMed‐Low Public ScoreMed‐High Staff ScoreConstruction FY24‐FY283 $ 1,013,000.00 $ 851,000.00 2,026,000.00$ 200%2Department: Public Works & Water Dept. Staff: Eric Ziegenfuss$5.2 M Requested$600K from Capital Plan$1M from Water Dept.Impact Fee Eligible Med‐Low Public ScoreHigh Staff ScoreStudy FY 24, Construction TBDCity Owned ShopConstruct and permanent site for the City Public Works and Water Department Shops. City has acquired property at SH‐16 in the sports park that is currently being used for shop space. The area in question is in Phase 3 of the park and is unlikely to be ready to transition to park space in the next 8‐10 years. FY 24 Funding is for $100K for a plan that addresses the improvements needed at the current site and parameters for the future site based on city growth and needs. Project is impact fee eligible up to $572K.The park impact fee fund was diminished in 2022 and will need time to recover before it will be able to support this project. Future years savings should be contingent on Water Fund MatchPW CP‐2Augmentations to the ACHD project providing for 10‐ft paver sidewalks, street trees, and historic streetlights. This project has over 90% of the funding to match ACHD's investment DT. Future FY will not require allocation of additional general fund $ unless project comes in over budget. EURA is funding 50% of the cost share costs. Fully funded in FY 24 ‐ carry forward for project into FY 25 & FY26 as needed. $ 1,100,000.00 $ 350,000.00 1,825,000.00$ 166% $ 600,000.00 $ 584,000.00 Department: LRP&PStaff: Nichoel Baird Spencer$600K RequestedNo MatchMed‐Low Public ScoreHigh Staff ScoreConstruction FY24Olde Park ExtensionT&P CP‐1 $ 600,000 The City is to construction an extension of Olde Park Place from the current terminus at Aikens Street to the signal at Plaza Drive. Project has an estimated $585K carry forward from FY23 with an estimated preliminary construction cost of $600K (assuming limited ROW costs). This project is planned to be constructed with the 2nd phase of the State and Eagle Project. Fund fully in FY 24 and to make adjustments in future years as needed for ROW. Contingent on ACHD partnership.100% $ 12,000,000 Construct a +/‐ 90 ‐acre sports park on SH‐16 north of Beacon Light Road. To date the City has spent or contracted $4.5M toward this park. The $12M is for phase 1 construction only (infrastructure and 4 fields). Bringing to the total to complete phase 1 to $16.5M. The City has already committed 27% of the total project cost without consideration of the impact fee credits to GWC for land purchase. This project alone could consume the entire FY24‐28 capital plan and still not be fully funded. This project is to have an annual set aside of $250K,Council has directed a funding committee be established to pursue match dollars from public/private entities. Once partners/funds are found the project can move toward construction. Project is impact fee eligible up to $18.9M. The park impact fee fund was diminished in 2022 and will need time to recover before it will be able to support this project. City has expended/committed $4.5M to date on land acquisition and engineering. Contingent on outside partnerships. $ 1,250,000.00 $‐ 1,250,000.00$ PAGE I 4 4
FY 24 250,000.00$ ‐$ 250,000.00$ ‐$ FY 25 500,000.00$ ‐$ ‐$ ‐$ FY 26 500,000.00$ ‐$ ‐$ ‐$ FY 27 500,000.00$ ‐$ ‐$ ‐$ FY 28 500,000.00$ ‐$ ‐$ ‐$ FY 24‐$ ‐$ ‐$ ‐$ FY 25 65,000.00$ ‐$ ‐$ 113,000.00$ FY 26‐$ ‐$ ‐$ ‐$ FY 27‐$ ‐$ ‐$ ‐$ FY 28‐$ ‐$ ‐$ ‐$ FY 24‐$ ‐$ ‐$ ‐$ FY 25 15,000.00$ ‐$ ‐$ ‐$ FY 26‐$ ‐$ ‐$ ‐$ FY 27‐$ ‐$ ‐$ ‐$ FY 28‐$ ‐$ ‐$ ‐$ FY 24 425,000.00$ ‐$ ‐$ ‐$ FY 25‐$ ‐$ ‐$ ‐$ FY 26‐$ ‐$ ‐$ ‐$ FY 27‐$ ‐$ ‐$ ‐$ FY 28‐$ ‐$ ‐$ ‐$ FY 24 400,000.00$ ‐$ ‐$ ‐$ FY 25 400,000.00$ ‐$ ‐$ ‐$ FY 26 400,000.00$ ‐$ ‐$ ‐$ FY 27‐$ ‐$ ‐$ ‐$ FY 28‐$ ‐$ ‐$ ‐$ 62%100%100%100%100%9PW CP‐13City Hall Facility Projects $ 425,000 6T&P CP‐2Aikens Street Extension $ 855,000 Department: LRP&PStaff: Nichoel Baird Spencer$858K Requested$113K Match from Eagle URAACHD Cost Share Med‐Low Public ScoreHigh Staff ScoreConstruction FY25Department: Clerk/Treasure & Public WorksStaff: Tracy Osborn, Kellie Rekow, & Eric Ziegenfuss$425K Med‐High Staff ScoreConstruction FY247T&P CP‐125P&R CP‐8Foothills Shooting Sport Park $ 4,500,000 Department: LRP&P & Public Works Staff: Nichoel Baird Spencer & Eric Ziegenfuss$70,000 Preliminary DesignConstruction:$4.5MOutside Foundation Match: $1.2 M No Public ScoreMed‐Low Staff Score Construction FY24‐FY28Complete a design‐build of a +/‐ 85‐acres shooting sports park (archery, pistol, rifle & shotgun). City in under contract for the design and phased construction of the Phase 1&2 of the park (archery). The City has committed $500K to date (11%) for design and the archery range in FY23. It is anticipated to carry forward $300K from FY 23. The timeline for construction if full funding is achieved is 9 months. Due to the limited timeline for construction this project is a good ‐quicker, faster, smarter project that helps bolster the City's Parks LOS while larger projects are developed. This project is to have an annual set aside of $500K, Council has directed a funding committee be established to pursue match dollars from public/private entities. Once partners/funds are found the project can move toward construction. Project is impact fee eligible up to $20M. The park impact fee fund was diminished in 2022 and will need time to recover before it will be able to support this project. City has committed $500,000 to date on studies and design. Contingent on outside partnerships. $ 800,000.00 $ 300,000.00 2,800,000.00$ 350%Department: LRP&P & PlanningStaff: Nichoel Baird Spencer & Bill Vaughan$15K Design OnlyACHD Cost Share Med‐High Public ScoreMed‐High Staff ScoreStudy FY 25This is a study only that would augment the ACHD design for Linder Road at the N. Channel. The cost is minimal and is needed to establish a planned construction cost for future cost share with ACHD. This is the highest ranked trail project in the plan and is eligible for up to $132K in pathway impact fees. A construction savings project should be programed in FY 26 to begin set aside for construction and utilization of impact fees for construction. 10 $ 425,000.00 $‐ Augmentations to the ACHD project providing for enhanced sidewalks, street trees, and medians to Linder Road north of SH‐44 to Floating Feather Roads .This project will move forward for construction by ACHD in FY 26. Either the City participates and funds the design elements they have requested (paver medians, planters and augmented landscape) or ACHD defaults to their standard section with the potential of a delay. $ 1,200,000.00 $‐ Merger of three City Hall facility projects into a single FY 24 expenditure‐City Hall safety improvements, Clerks Office Reconfiguration & Glass in Rec Center Linder Road(SH‐44 to FF) $ 1,200,000 Department: LRP&PStaff: Nichoel Baird Spencer$1.2M RequestedACHD Cost Share Med‐Low Public ScoreHigh Staff ScoreRequested Year: 2022Construction FY26425,000.00$ 100%TRL CP‐19Linder Road Underpass @ N. Channel $ 15,000 858,000.00$ 115%Augmentations to the ACHD project providing for 10‐ft paver sidewalks, street trees, and historic streetlights to the extension of Aikens Street from 1st street to 2nd street. The City has set‐aside $745K to date and with the EURA match ($113K) this project is fully funded but has been on hold for nearly a decade due to ROW issues. While still a priority should the City continue to hold funds for the project or leverage the money to complete higher priority projects and replace these funds over time? The project does not impact the General fund request for FY 24. City is holding funds for 1 more year to see if ROW or partnership can be achieved. If a path forward is available the city will fund the remaining $65K. Contingent on ACHD partnership. $ 745,000.00 $ 680,000.00 1,200,000.00$ 100% $ 15,000.00 $‐ 15,000.00$ 100%PAGE I 4 5
FY 24 100,000.00$ ‐$ ‐$ 100,000.00$ FY 25‐$ ‐$ ‐$ FY 26‐$ ‐$ ‐$ FY 27‐$ ‐$ ‐$ ‐$ FY 28‐$ ‐$ ‐$ ‐$ FY 24FY 25FY 26FY 27FY 28FY 24‐$ ‐$ 20,000.00$ ‐$ FY 25 190,000.00$ ‐$ ‐$ ‐$ FY 26‐$ ‐$ ‐$ ‐$ FY 27‐$ ‐$ ‐$ ‐$ FY 28‐$ ‐$ ‐$ ‐$ FY 24‐$ ‐$ ‐$ ‐$ FY 25 30,000.00$ ‐$ ‐$ ‐$ FY 26‐$ ‐$ ‐$ ‐$ FY 27‐$ ‐$ ‐$ ‐$ FY 28‐$ ‐$ ‐$ ‐$ FY 24‐$ ‐$ ‐$ ‐$ FY 25300,000.00$ ‐$ ‐$ 300,000.00$ FY 26 287,000.00$ ‐$ ‐$ 287,000.00$ FY 27 200,000.00$ 413,000.00$ ‐$ 413,000.00$ FY 28‐$ ‐$ ‐$ FY 24‐$ ‐$ ‐$ ‐$ FY 25‐$ ‐$ ‐$ ‐$ FY 26 100,000.00$ ‐$ ‐$ ‐$ FY 27‐$ ‐$ ‐$ FY 28 500,000.00$ ‐$ ‐$ ‐$ 15%100%100%100%42%100% $‐ 30,000.00$ 100% $ 500,000 Department: LRP&P & Public Works Staff: Nichoel Baird Spencer & Eric Ziegenfuss$500K RequestedPrivate Partnership up to 50%Impact Fee Eligible up to $1.4MMed‐Low Public ScoreMed‐High Staff ScorePreliminary Design Completed in FY21 Wetlands Study FY25Develop a park on the north side of the north channel of the Boise River just south of the prospectus of Edgewood Lane. The City completed preliminary design for the park in FY 21, the current plan is to develop a natural area an wetlands bank as contained within the park master plan. The City needs to develop a prospectus for the wetland bank and then could talk about leveraging the sale of wetlands credits to develop the park site. Project is impact fee eligible up to $2.1M. The park impact fee fund was diminished in 2022 and will need time to recover before it will be able to support this project. $ 2,100,000.00 $‐ $ 600,000.00 15%12POL CP‐1Police Substation Department: PoliceStaff: Chief Wilkie$615,000 Requested $350,000 from Impact Fees Partnership with Eagle FireMed‐High Public ScoreConstruction TBD615,000$ As identified in the Police Impact Fee Capital Plan, begin the process of identifying and constructing a police substation. The project is funded solely through impact fees. City needs to determine feasibility of the station prior to FY 27 and allocate collected funds or fund alternative projects allowed in the Police Impact Fee CIP. If the Council adds officers in FY 24 the carry forward of $90K can be used for equipment purchases for new officers ($2,300/officer). $ 615,000.00 90,267.00$ 210,000.00$ 2,200,000.00$ 183%Phased construction of Pamela Baker Park located in the Lakemoor Development. The preliminary design for the park was completed and approved by the Eagle Design Review Board in 2023. The City constructed the 1st phase in FY 2020 (bathroom, parking and pathway). The funding for construction is primarily from park impact fees. The fund was diminished in 2022 and will need time to recover. The City completed the irrigation pump in FY 23 at $100K. Earlier phases of the project utilized all but $413K of the eligible park impact fees. The City will need to find an additional $1.7M to finish the project. Project is impact fee eligible up to $413K. $ 1,200,000.00 $‐ $ 90,267.00 Parks, Trails & Open Space Master Plan $ 287,000 287,000.00$ 17P&R CP‐10Pamela Baker Park $ 2,200,000 Department: Public Works & LRP&P Staff: Eric Ziegenfuss & Nichoel Baird Spencer$2.2M RequestedPrivate Partnership up to 50%Impact Fee Eligible up to $390KMed‐Low Public ScoreMed‐High Staff ScoreConstruction FY25‐FY27Install curb, gutter, and enhanced sidewalks with lighting and street trees on Idaho Street between 2nd Street and Eagle Road. $100K in FY 26 for engineering/Design, $500K for construction. Project requires cost share with ACHD and/or EURA. Contingent on EURA as a funding partner. 18ED CP‐5Idaho Street Streetscape Improvements $ 600,000 Department: Economic Development Staff: TBD$600K RequestedNo Match Med‐Low Public ScoreMed‐High Staff ScoreRequested Year: 2027Study FY26Construction FY2811P&R CP‐9100%10%16ED CP‐6Department: LRP&PStaff: Nichoel Baird Spencer$287K RequestedNo Match Med‐High Public ScoreMed‐High Staff ScoreStudy FY24Complete a city‐wide plan for the provision of parks, trail and open space within the community as well as establishing minimum standards and long‐term operation and maintenance responsibilities. This plan is funded in FY 23 and can be completed in FY 24 with carry forward dollars and no new allocation of general fund dollars. Based on comments from the Council about delaying new trail projects until the plan is completed, the majority of trail projects are listed as "unfunded" through FY28. This project requires $100K in outside funding is from landowners in the foothills seeking options for impact fee credits/reimbursements. The goal is to have this project to include updates to the park & pathways impact fee studies. $ 287,000.00 $ 87,000.00 14P&R CP‐7Charlie Wood Park Excess ROW‐ State Street $ 30,000 $‐ 600,000.00$ 100%Department: Economic Development Staff: TBD$30K Study OnlyNo Match ‐Make a request to ACHD Med‐Low Public ScoreHigh Staff ScoreStudy FY25Work Cooperatively with ACHD to look at options for the excess highway ROW in DT Eagle, West of Olde Park Place and east of the Eagle Senior Center. Options should include parking, medians and other traffic calming items that benefit the vitality of DT Eagle. $ 30,000.00 PAGE I 4 6
FY 24‐$ ‐$ ‐$ ‐$ FY 25‐$ ‐$ ‐$ ‐$ FY 26 100,000.00$ ‐$ ‐$ ‐$ FY 27 413,000.00$ ‐$ 87,000.00$ ‐$ FY 28‐$ ‐$ ‐$ ‐$ FY 24 500,000.00$ ‐$ ‐$ ‐$ FY 25‐$ ‐$ ‐$ ‐$ FY 26‐$ ‐$ ‐$ ‐$ FY 27‐$ ‐$ ‐$ ‐$ FY 28‐$ ‐$ ‐$ ‐$ FY 24‐$ ‐$ 200,000.00$ ‐$ FY 25‐$ ‐$ ‐$ ‐$ FY 26‐$ ‐$ ‐$ ‐$ FY 27‐$ ‐$ ‐$ ‐$ FY 28‐$ ‐$ ‐$ ‐$ FY 24‐$ 50,000.00$ ‐$ FY 25‐$ 50,000.00$ ‐$ FY 2650,000.00$ ‐$ ‐$ ‐$ FY 27 50,000.00$ ‐$ ‐$ ‐$ FY 28 50,000.00$ ‐$ ‐$ ‐$ FY 24‐$ ‐$ ‐$ ‐$ FY 25‐$ ‐$ ‐$ ‐$ FY 26 30,000.00$ ‐$ ‐$ ‐$ FY 27‐$ ‐$ ‐$ ‐$ FY 28‐$ ‐$ ‐$ ‐$ FY 24‐$ ‐$ ‐$ ‐$ FY 25‐$ ‐$ ‐$ ‐$ FY 26‐$ 25,000.00$ ‐$ FY 27 25,000.00$ ‐$ ‐$ ‐$ FY 28 25,000.00$ ‐$ ‐$ ‐$ FY 24‐$ ‐$ ‐$ ‐$ FY 25‐$ ‐$ ‐$ ‐$ FY 26‐$ 10,000.00$ ‐$ FY 27‐$ ‐$ ‐$ ‐$ FY 28‐$ ‐$ ‐$ ‐$ $‐ 75,000.00$ 50% $ 150,000.00 27ED CP‐7Downtown Façade Improvement Department: Economic Development Staff: RTBD$50K Requested AnnuallyMed‐Low Public ScoreHigh Staff ScoreFY 23‐27 PLAN YEAR: $50K/year starting in FY 26Provide incentives to Downtown business to bring facades, signage, and sidewalk improvements into new standards. The City should work with the EURA to cost share on the project City will fund at $25K/year starting in FY 26 and asking EUR to match at $25K annually to full fund. Contingent on EURA as a funding partner. Department: Public WorksStaff: Eric Ziegenfuss$10K (Study Only) Requested$390k ConstructionNo MatchMed‐Low Public ScoreMed‐Low Staff ScoreStudy FY26100%50%100%52%100% $ 50,000 500,000.00$ 100%100%100%10,000.00$ 100%Re‐evaluate the location of the City of Eagle Entry Arches to determine if they are still in the appropriate locations or if they need relocated. Consider any additional entry monumentation locations for the City. This is a study only, the out come would be a plan for new or relocated signs that will need funding in future years. $ 10,000.00 $‐ 28PW CP‐7City Entry Sign Plan $ 10,000 $ 1,147,000.00 $‐ 600,000.00$ 52%20ED CP‐31st Street Festival Street $ 1,147,000 Department: Economic Development Staff: TBD$1.147M RequestedNo Match Med‐Low Public ScoreHigh Staff ScoreRequested Year: FY 2024Study FY26Construction FY27No RankPW CP‐17Fleet Expansion (changed from PW vehicles) $ 50,000 Department: Public Works & Water Dept. Staff: Eric Ziegenfuss$50K Requested AnnuallyREQUESTED CONSTRUCTION: As needed Funds will be used for fleet expansion on an as needed basis. Funds will be carry forward each year until needed. Project was brought back into the Capital Plan at the Mayor's request. $ 250,000.00 $‐ $ 500,000.00 $‐ Construct a storage facility in Merrill Park for park equipment and maintenance needs. $ 30,000.00 $‐ 100%24P&R CP‐12Merrill Park Storage Building $ 30,000 Department: Public WorksStaff: Eric Ziegenfuss$30K No MatchConstruction FY2630,000.00$ 23/39T&P CP‐8T&P CP‐9Ped/Bike Studies ‐ FF & BL Rds. $ 200,000 Department: LRP&PStaff: Nichoel Baird Spencer$200K (Study Only) RequestedNo Match ‐ Seek ACHD Partnership Med‐Low Public ScoreMed‐Low Staff ScoreStudy FY 24 City is seeking ACHD support and partnership on completing Ped/Bike Plans for Floating Feather Road and Beacon Light Road. This will include plans for pedestrian safety, bike lanes/crossings, on street parking (as needed) and establishing mutually adopted cross sections for the two roadways between SH‐16 & SH‐55. Combined two projects into a single study. Contingent on ACHD partnership. $ 200,000.00 $‐ 22P&R CP‐11Mace Park $ 500,000 Department: LRP&P & Public Works Staff: Nichoel Baird Spencer & Eric Ziegenfuss$477K RequestedImpact Fee Eligible up to $23.5K Med‐Low Public ScoreMed‐High Staff ScoreEngineering Design FY23Construction FY24Construct a greenbelt access, parking area, and native area on the southside of the north channel of the Boise River, west of Eagle Road and the terminus of the Eagle Road Ped/Bike Bridge. Project is 90% designed and ITD has agreed to issue the permit and construct the improvements within the center turn area of SH‐55. Project is a good augmentation to the ped bike bridge completed in FY 23. project is categorized as a park thus benefiting the City's LOS. Project is impact fee eligible up to $577K.The park impact fee fund was diminished in 2022 and will need time to recover and will not be able to support this project.Create a festival street similar to the Basque Block in Boise that can be used for events and overflow from Heritage Park. Install rolled curb, gutter, and enhanced sidewalks with lighting and planters on 1st Street from Aikens to Idaho Street. $100K in FY 26 for engineering/Design, $500K for construction. Project requires cost share with ACHD and/or EURA. Contingent on EURA as a funding partner. 200,000.00$ 100%250,000.00$ 100%PAGE I 4 7
FY 24‐$ ‐$ ‐$ ‐$ FY 25‐$ ‐$ ‐$ ‐$ FY 26‐$ ‐$ ‐$ ‐$ FY 27‐$ ‐$ ‐$ ‐$ FY 28 50,000.00$ ‐$ ‐$ 50,000.00$ FY 24‐$ ‐$ ‐$ ‐$ FY 25‐$ ‐$ ‐$ ‐$ FY 26‐$ ‐$ ‐$ ‐$ FY 27‐$ ‐$ ‐$ ‐$ FY 28‐$ ‐$ ‐$ ‐$ #NAME? $ 3,122,267.00 Plan Years GF by Year Impact feesReserve Transfer by Year Outside funding FY 241,853,000.00$ ‐$ 870,000.00$ 375,000.00$ FY 252,000,000.00$ ‐$ 50,000.00$ 1,451,000.00$ FY 261,967,000.00$ ‐$ 35,000.00$ 312,000.00$ FY 271,688,000.00$ 413,000.00$ 87,000.00$ 438,000.00$ FY 281,625,000.00$ ‐$ ‐$ 75,000.00$ TOTAL 9,133,000.00$ 413,000.00$ 1,042,000.00$ 2,651,000.00$ $‐ $ 50,000.00 FY 24‐28 Total Requested 33%FY 23 Carry Forward FY 24‐28 Total Capital Plan AllocationsNo RankLIB CP‐1Library Facilities Master Plan $ 150,000 Department: LibraryStaff: Steve Baumgartner$150K Study OnlyNo Public ScoreHigh Staff ScoreTBDBegin saving for a Library Master Plan that will help direct investment, expansion and the provision of services. This savings was set aside by the Library Board before the Library became a City Dept. The project will need to be ranked in future years for funding. 50,000.00$ 100%26 & 35TRL CP‐15S. Channel @ EagleRoad Ped/BikeCrossing(Bridge &Underpass) $ 100,000 Department: PlanningStaff: Bill Vaughan$100K Preliminary Design OnlyImpact Fee Eligible Med‐Low Public ScoreHigh Staff ScoreStudy FY28Begin the process, similar to the N. Channel, to conduct a feasibility study of a ped/bike bridge across the n. channel and a tunnel commenting e/w across Eagle Road. Project should be submitted to COMPASS as a Preliminary Development Plan and potential outside funding of $50K for the study. The City should provide a $50K to bring the project to full funding. COMPASS application needs to be made in November of 2023 to fund in FY 28. Once complete City can determine timing of construction. Contingent on COMPASS Project Development Funding. $ 50,000.00 $‐ 100,000.00$ 200%33%PAGE I 4 8
FY 24 RankProject No.Project Name Project Cost DetailsComments/Rational FY 24 RankProject No. Project NameComments/Rational 31TRL CP‐17Dry Creek & Dry Creek Canal $30K (design only) Department: PlanningStaff: Steve Noyes $30K (Design Only) RequestedNo MatchMed‐Low Public ScoreMed‐Low Staff ScoreUnfunded Construct a trail and connection along Dry Creek and the Dry Creek Canal south of the greenbelt. Based on comments from the Council, new trail projects are delayed until the Parks, Trails and Open Space Plan is completed, the majority of trail projects are listed as "unfunded" through FY28. 26PW CP‐12Senior Center Remodel31ED CP‐1Downtown Parking $750K Department: Economic Development Staff: TBD$750K RequestedNo MatchMed‐Low Public ScoreUnfundedFind land to partner in the construction a parking lot in Downtown Eagle. Limited funding available 34LIB CP‐3Library Book Pick‐up 36TRL CP‐16N. Channel DryCreek Bridge $100K (design only) Department: PlanningStaff: Steve Noyes$100K (Design Only)Requested Impact fee eligible up to $1.02M Med‐Low Public ScoreMed‐Low Staff ScoreUnfundedConstruct a bridge across Dry Creek north of Floating Feather Road. Based on comments from the Council, new trail projects are delayed until the Parks, Trails and Open Space Plan is completed, the majority of trail projects are listed as "unfunded" through FY28. 34P&R CP‐1Community/ Performing Arts Study39TRL CP‐8Trails Wayfinding & Branding $20K Department: PlanningStaff: Steve Noyes$20K RequestedNo MatchMed‐Low Public ScoreHigh Staff ScoreUnfunded Based on comments from the Council, new trail projects are delayed until the Parks, Trails and Open Space Plan is completed, the majority of trail projects are listed as "unfunded" through FY28. 37T&P CP‐11Eagle Road Arch Expansion 41LIB CP‐2Bookmobile $250K Department: LibraryStaff: Steve Bumgarner$250KNo MatchLow Public ScoreMed‐Low Staff ScoreUnfunded Limited funding available 38T&P CP‐NEWEagle Memorial Garden/Cemetery in Foothills43TRL CP‐12Water Trail Study $30K (design only) Department: Public Works, Planning, & RecreationStaff: Eric Ziegenfuss, Steve Noyes, & Brian Allen$30K (Study Only) Requested No MatchMed‐Low Public ScoreMed‐High Staff ScoreUnfunded Based on comments from the Council, new trail projects are delayed until the Parks, Trails and Open Space Plan is completed, the majority of trail projects are listed as "unfunded" through FY28. 40TRL CP‐11The Shores Sportsman's Access45TRL CP‐21Laguna Point Bridge $30K Department: PlanningStaff: Steve Noyes$30K RequestedNew ProjectUnfundedBased on comments from the Council, new trail projects are delayed until the Parks, Trails and Open Space Plan is completed, the majority of trail projects are listed as "unfunded" through FY28. 42TRL CP‐6All Weather Trail Ada Sports Park46TRL CP‐20Williamson River Ranch Bridge $100 (study only) Department: PlanningStaff: Steve Noyes$100K (Study Only) Requested No MatchLow Public ScoreMed‐Low Staff ScoreUnfunded Based on comments from the Council, new trail projects are delayed until the Parks, Trails and Open Space Plan is completed, the majority of trail projects are listed as "unfunded" through FY28. 43TRL CP‐7Bike Skills Park ‐ Ada Sports Complex 47TRL CP‐9Trailhead Amenities ‐Ada Sports Complex $150K Department: Planning & Public WorksStaff: Steve Noyes & Eric Ziegenfuss $150K RequestedNo MatchMed‐Low Public ScoreMed‐High Staff ScoreUnfunded Based on comments from the Council, new trail projects are delayed until the Parks, Trails and Open Space Plan is completed, the majority of trail projects are listed as "unfunded" through FY28. 48P&R CP‐6Motocross Study The City Completed the Community Hall project in FY 22. Moved to CM, funded in FY27 (T&P CP‐11) to provide for road project completionRemoved by the Council. Work with land owners to develop a facility but not city owned. This project is redundant to the Mace Park Project (PW CP‐9) scheduled for construction in FY 24 and is located on the same corridor. This project is being completed with existing resources and the use of recycled materials. This project is being completed through donation and recycled materials. Locally undesirable project. Removed by the City Council. Removed Capital Projects FY 24‐FY 28Funded in Capital Maintenance Program in FY 27 (PW CM‐2) ‐ Flooring, interior & Exterior painting, further work should be scoped before seeking fundingRemoved per Library Director. Lockers installed in 2023.FUTURE Capital Projects Beyond FY 28PAGE I 4 9
FISCAL YEAR 2024 –2028 CAPITAL PROJECTS MAP UNMAPPED: PW CM‐2: City Owned Shop P&R CP‐9: Parks, Trails & Open Space Plan POL CP‐1: Police Substation PW CP‐17: Fleet Expansion T&P CP‐8 & 9: Ped/Bike Studies Floating Feather & Beacon Light Road PW CP‐7: City Entry Sign Plan LIB CP‐1: Library Facilities Master Plan PW CM‐8: Library Roof TRL CP‐19: Linder Road P&R CM‐2: Regional Sports Park T&P CP‐3: Eagle Road Ped/Bike P&R CP‐8: Shooting Sport Park GEN CP‐1/T&P CP‐10: Three Cities River Crossing Page | 5 0 T&P CP‐12: Linder Road (SH‐44 to FF) P&R CM‐7: Charlie Wood Park ED CP‐6: Excess ROW Study ED CP‐5: Idaho Street ED CP‐3: First Street Festival Street ED CP‐7: Façade Improvements T&P CP‐1: State & Eagle Intersection Olde Park Place Extension PW CP‐13: City Hall Facilities T&P CP‐2: Aikens Street Extension P&R CM‐10: Pamela Baker Park P&R CM‐11: Mace Park P&R CM‐12: Merrill Park Storage TRL CP‐15: S.Channel Ped/Bike Crossing
FY 2024-2028 CAPITAL PLAN
GEN-CP-1
T&P CP-10
THREE CITIES RIVER
CROSSING (3CRX)
Department: LRP&P
Staff: Nichoel Baird Spencer
Delayed due to regional coordination
efforts
$100K
Study Completion FY24
This is a regional project in the COMPASS Long-range Transporta-
tion Plan. It requires interagency review of the feasibility study.
The agency partners have asked for additional review as a resiliency
project (floodway protection and protection of the Boise
wastewater treatment plant) in addition to just transportation con-
nectivity & congestion.
Plan Years General Impact Fees Outside Total:
FY 24 $ $ $ $
FY 25 $ $$ $
FY 26 $ $ $ $ 100,000.00
FY 27 $ $ $ $
FY 28 $ $ $ $
Reserves
$
$
$
$
$
Carry Forward FY 23
$ 100,000.00
P a g e I 51
FY 2024-2028 CAPITAL PLAN
T&P CP-3 EAGLE ROAD PED/BIKE
BRIDGE
Department: LRP&P
Staff: Nichoel Baird Spencer
Incomplete in FY 2023
Delayed due to highwater
$30K Remaining
Completion FY24
Carried forward to complete final landscape
and graffiti coating after water level drops.
Plan Years General Impact Fees Outside Total:
FY 24 $ $ $ 28,000.00 $
FY 25 $ $$ $
FY 26 $ $ $ $ 30,000.00
FY 27 $ $ $ $
FY 28 $ $ $ $
Reserves
$
$
$
$
$
Carry Forward
$ 30,000.00
For additional Information: hƩps://www.cityofeagle.org/2002/Eagle-Road-Pedestrian-and-Bicycle-Bridge
P a g e I 52
FY 2024-2028 CAPITAL PLAN
T&P CP-1 STATE & EAGLE
INTERSECTION
Department: LRP&P
Staff: Nichoel Baird Spencer
$1.013M Requested
$1.013M Match from Eagle URA
ACHD Cost Share
Construction FY24 & FY25
Augmentations to the ACHD project providing for 10-ft paver
sidewalks, street trees, and historic streetlights. This project has
over 90% of the funding to match ACHD's investment Down Town.
Future FY will not require allocation of additional general fund dol-
lars unless project comes in over budget. EURA is funding 50% of
the cost share costs. Fully funded in FY 24 - carry forward for pro-
ject into FY 25 & FY26 as needed.
Plan Years General Fund Impact Fees Outside Total:
FY 24 $ 162,000.00 $ $ $
FY 25 $ $$ 1,013,000.00 $
FY 26 $ $ $ $ 2,026,000.00
FY 27 $ $ $ $
FY 28 $ $ $ $
Reserves
$
$
$
$
$
Carry Forward
$ 851,000.00
For additional Information: hƩps://engage.achdidaho.org/downtown-eagle-mobility-improvements-eagle-road-and-state-street
P a g e I 53
FY 2024-2028 CAPITAL PLAN
PW CP-2 CITY OWNED
SHOP
Department: Public Works & Water
Staff: Eric Ziegenfuss
$5.2M Requested
$600K from Capital Plan
$1M from Water Dept.
Impact Fee Eligible
Study FY24, Construction TBD
Construct and permanent site for the City Public Works and Water Depart-
ment Shops. City has acquired property at SH-16 in the sports park that is
currently being used for shop space. The area in question is in Phase 3 of the
park and is unlikely to be ready to transition to park space in the next 8-10
years. FY 24 Funding is for $100K for a plan that addresses the improve-
ments needed at the current site and parameters for the future site based on
city growth and needs. Project is impact fee eligible up to $572K. The
park impact fee fund was diminished in 2022 and will need time to recover
before it will be able to support this project. Future years savings should be
contingent on Water Fund Match
Plan Years General Fund Impact Fees Outside Total:
FY 24 $ $ $ 275,000.00
FY 25 $ 250,000.00 $$ 25,000.00
FY 26 $ 250,000.00 $ $ 25,000.00 $ 1,825,000.00
FY 27 $ 250,000.00 $ $ 25,000.00
FY 28 $ 250,000.00 $ $ 25,000.00
Reserves
$ 100,000.00
$
$
$
$
Carry Forward FY23
$350,000.00
P a g e I 54
FY 2024-2028 CAPITAL PLAN
T&P CP-1 OLDE PARK
EXTENSION
Department: LRP&P
Staff: Nichoel Baird Spencer
$600K Requested
No Match
Construction FY24
The City is to construction an extension of Olde Park Place from the
current terminus at Aikens Street to the signal at Plaza Drive. Project
has an estimated $585K carry forward from FY23 with an estimated
preliminary construction cost of $600K (assuming limited right of way
costs). This project is planned to be constructed with the 2nd phase of
the State and Eagle Project. Fund fully in FY 24 and to make adjust-
ments in future years as needed for right of way.
Contingent on ACHD partnership.
Plan Years General Fund Impact Fees Outside Total:
FY 24 $ 16,000.00 $ $
FY 25 $ $$
FY 26 $ $ $ $ 600,000.00
FY 27 $ $ $
FY 28 $ $ $
Reserves
$
$
$
$
$
Carry Forward
$ 584,000.00
P a g e I 55
FY 2024-2028 CAPITAL PLAN
P&R CP-2 REGIONAL SPORTS
PARK – Phase 1
Department: LRP&P
Staff: Nichoel Baird-Spencer & Eric
Ziegenfuss
$12M Design & Construction
Impact Fee Eligible up to $4.9M
Construction FY24-FY28
Construct a +/- 90 -acre sports park on SH-16 north of Beacon Light Road. To
date the City has spent or contracted $4.5M toward this park. The $12M is for
phase 1 construction only (infrastructure and 4 fields). Bringing to the total to
complete phase 1 to $16.5M. The City has already committed 27% of the total
project cost without consideration of the impact fee credits to GWC for land
purchase. This project alone could consume the entire FY24-28 capital plan and
still not be fully funded. This project is to have an annual set aside of $250K,
Council has directed a funding committee be established to pursue match dollars
from public/private entities. Once partners/funds are found the project can
move toward construction. Project is impact fee eligible up to $18.9M. The park
impact fee fund was diminished in 2022 and will need time to recover before it
will be able to support this project. City has expended/committed $4.5M to
date on land acquisition and engineering. Contingent on outside partnerships.
Plan Years General Fund Impact Fees Outside Total:
FY 24 $ $ $
FY 25 $ 250,000.00 $$
FY 26 $ 250,000.00 $ $ $ 1,250,000.00
FY 27 $ 250,000.00 $ $
FY 28 $ 250,000.00 $ $
Reserves
$ 250,000.00
$
$
$
$
Carry Forward
$ -
For additional Information: hƩps://www.cityofeagle.org/1944/Eagle-Regional-Sports-Park
P a g e I 56
FY 2024-2028 CAPITAL PLAN
P&R CP-8 FOOTHILLS SHOOTING
RANGE
Department: LRP&P & Public
Works
Staff: Nichoel Baird Spencer &
Eric Ziegenfuss
$70K Preliminary Design
$4.5M Construction
$1.2M Outside Foundation Match
Construction FY24-FY28
Complete a design-build of a +/- 85-acres shooting sports park (archery, pistol,
rifle & shotgun). City in under contract for the design and phased construction
of the Phase 1&2 of the park (archery). The City has committed $500K to date
(11%) for design and the archery range in FY23. It is anticipated to carry forward
$300K from FY 23. The timeline for construction if full funding is achieved is
9 months. Due to the limited timeline for construction this project is a good -
quicker, faster, smarter project that helps bolster the City's Parks LOS while
larger projects are developed. This project is to have an annual set aside of
$500K, Council has directed a funding committee be established to pursue
match dollars from public/private entities. Once partners/funds are found the
project can move toward construction. Project is impact fee eligible up to
$20M. The park impact fee fund was diminished in 2022 and will need time to
recover before it will be able to support this project. City has committed
$500,000 to date on studies and design. Contingent on outside partnerships.
Plan Years General Fund Impact Fees Outside Total:
FY 24 $ 250,000.00 $ $
FY 25 $ 500,000.00 $$
FY 26 $ 500,000.00 $ $ $ 2,800.000.00
FY 27 $ 500,000.00 $ $
FY 28 $ 500,000.00 $ $
Reserves
$ 250,000.00
$
$
$
$
Carry Forward
$ 300,000.00
For additional Information: hƩps://www.cityofeagle.org/1943/Eagle-ShooƟng-Sports-Park
P a g e I 57
FY 2024-2028 CAPITAL PLAN
T&P CP-2 AIKENS STREET
EXTENSION
Department: LRP&P
Staff: Nichoel Baird Spencer
$858K Requested
$113K Match from Eagle URA
ACHD Cost Share
Construction FY25
Augmentations to the ACHD project providing for 10-ft paver sidewalks,
street trees, and historic streetlights to the extension of Aikens Street from
1st street to 2nd street. The City has set-aside $745K to date and with the
EURA match ($113K) this project is fully funded but has been on hold for
nearly a decade due to ROW issues. While still a priority should the City
continue to hold funds for the project or leverage the money to complete
higher priority projects and replace these funds over time? The project does
not impact the General fund request for FY 24. City is holding funds for 1
more year to see if ROW or partnership can be achieved. If a path forward is
available the city will fund the remaining $65K.
Contingent on ACHD partnership.
Plan Years General Impact Fees Outside Total:
FY 24 $ $ $
FY 25 $ 65,000.00 $$ 113,000.00
FY 26 $ $ $ $ 858,000.00
FY 27 $ $ $
FY 28 $ $ $
Reserves
$
$
$
$
$
Carry Forward
$ 680,000.00
For additional Information: hƩps://engage.achdidaho.org/downtown-eagle-mobility-improvements-eagle-road-and-state-street
P a g e I 58
FY 2024-2028 CAPITAL PLAN
TRL CP-19
LINDER ROAD UNDERPASS AT
NORTH CHANNEL
Study Only
Department: LRP&P & PLANNING
Staff: Nichoel Baird Spencer &
Bill Vaughan
$15K Design Only
ACHD Cost Share
Study FY25
This is a study only that would augment the ACHD design for Linder
Road at the North Channel. The cost is minimal and is needed to es-
tablish a planned construction cost for future cost share with ACHD.
This is the highest ranked trail project in the plan and is eligible for up
to $132K in pathway impact fees. A construction savings project
should be programed in FY 26 to begin set aside for construction and
utilization of impact fees for construction.
Plan Years General Fund Impact Fees Outside Total:
FY 24 $ $ N/A
FY 25 $ 15,000.00 $N/A
FY 26 $ $ N/A $ 15,000.00
FY 27 $ $ N/A
FY 28 $ $ N/A
Reserves
$
$
$
$
$
Carry Forward FY23
$ -
For additional Information: hƩps://engage.achdidaho.org/linder-road-chinden-boulevard-to-state-highway-44
P a g e I 59
FY 2024-2028 CAPITAL PLAN
PW CP-13
CITY HALL FACILITY
PROJECTS
Department: Clerk/Treasure &
Public Works
Staff: Tracy Osborn, Kellie Rekow &
Eric Ziegenfuss
$425K Requested
Construction FY24
Merger of three City Hall facility projects into a single FY
24 expenditure - City Hall safety improvements, Clerks
Office Reconfiguration & Glass in Rec Center
Plan Years General Fund Impact Fees Outside
Source Total:
FY 24 $ 425,000.00 $ $
FY 25 $ $$
FY 26 $ $ $ $ 425,000.00
FY 27 $ $ $
FY 28 $ $ $
Reserves
$
$
$
$
$
Carry Forward
FY23
$ -
P a g e I 60
FY 2024-2028 CAPITAL PLAN
T&P CP-12 LINDER ROAD
(SH-44 to Floating Feather)
Department: LRP&P
Staff: Nichoel Baird Spencer
$1.2M Requested
ACHD Cost Share
Requested Year: 2022
Construction FY26
Augmentations to the ACHD project providing for en-
hanced sidewalks, street trees, and medians to Linder Road
north of SH-44 to Floating Feather Roads. This project will
move forward for construction by ACHD in FY 26. Either
the City participates and funds the design elements they
have requested (paver medians, planters and augmented
landscape) or ACHD defaults to their standard section with
the potential of a delay.
Plan Years General Fund Impact Fees Outside Total:
FY 24 $ 400,000.00 $ $
FY 25 $ 400,000.00 $$
FY 26 $ 400,000.00 $ $ $ 1,200,000.00
FY 27 $ $ $
FY 28 $ $ $
Reserves
$
$
$
$
$
Carry Forward
$ -
For additional Information: hƩps://engage.achdidaho.org/linder-road-state-highway-44-to-floaƟng-feather
P a g e I 61
FY 2024-2028 CAPITAL PLAN
P&R CP-9 PARKS, TRAILS & OPEN
SPACE - Master Plan
Department: LRP&P
Staff: Nichoel Baird Spencer
$287K Requested
No-Match
Study FY24
Complete a city-wide plan for the provision of parks, trails and open space
within the community as well as establishing minimum standards and long-
term operation and maintenance responsibilities. This plan is funded in FY 23
and can be completed in FY 24 with carry forward dollars and no new alloca-
tion of general fund dollars. Based on comments from the Council about de-
laying new trail projects until the plan is completed, the majority of trail pro-
jects are listed as "unfunded" through FY28. This project requires $100K in
outside funding is from landowners in the foothills seeking options for impact
fee credits/reimbursements. The goal is to have this project to include up-
dates to the park & pathways impact fee studies.
Plan Years General Fund Impact Fees Outside Total:
FY 24 $ 100,000.00 $ $ 100,000.00
FY 25 $ $$
FY 26 $ $ $ $ 287,000.00
FY 27 $ $ $
FY 28 $ $ $
Reserves
$
$
$
$
$
Carry Forward FY23
$ 87,000.00
P a g e I 62
FY 2024-2028 CAPITAL PLAN
POL CP-1 POLICE
SUBSTATION
Department: Police
Staff: Chief Wilkie
$615K Requested
$350K from Impact Fees
Partnership with Eagle Fire
Construction TBD
As identified in the Police Impact Fee Capital Plan, begin the process of
identifying and constructing a police substation. The project is funded
solely through impact fees. City needs to determine feasibility of the
station prior to FY 27 and allocate collected funds or fund alternative
projects allowed in the Police Impact Fee CIP. If the Council adds offic-
ers in FY 24 the carry forward of $90K can be used for equipment pur-
chases for new officers ($2,300/officer).
Plan Years General Fund Impact Fees Outside
Source Total:
FY 24 $ $ $
FY 25 $ $$
FY 26 $ $ $ $ 90, 267.00
FY 27 $ $ $
FY 28 $ $ $
Reserves
$
$
$
$
$
Carry Forward
FY23
$90, 267.00
Study can be found at: hƩps://www.cityofeagle.org/DocumentCenter/View/3773/Eagle-Police-CIP--adopted-11-10-20-PDF?bidId=
P a g e I 63
FY 2024-2028 CAPITAL PLAN
P&R CP-7 CHARLIE WOOD
PARK
Department: LRP&P & Public Works
Staff: Nichoel Baird Spencer &
Eric Ziegenfuss
$500K Requested
Private Partnership up to 50%
Impact Fee Eligible up to $1.4M
Preliminary Design Completed in FY21
Wetlands Study Only FY 25
Develop a park on the north side of the north channel of the Boise River
just south of the prospectus of Edgewood Lane. The City completed
preliminary design for the park in FY 21, the current plan is to develop a
natural area an wetlands bank as contained within the park master plan.
The City needs to develop a prospectus for the wetland bank and then
could talk about leveraging the sale of wetlands credits to develop the
park site. Project is impact fee eligible up to $2.1M. The park impact fee
fund was diminished in 2022 and will need time to recover before it will
be able to support this project.
Plan Years General Fund Impact Fees Outside Total:
FY 24 $ $ $
FY 25 $ 190,000.00 $$
FY 26 $ $ $ $ 210,000.00
FY 27 $ $ $
FY 28 $ $ $
Reserves
$ 20,000.00
$
$
$
$
Carry Forward FY23
$ -
P a g e I 64
FY 2024-2028 CAPITAL PLAN
ED CP-6 Excess ROW State Street
Study Only
Department: Economic Development
Staff: TBD
$30K Study Only
No Match—Make a request to ACHD
Study FY25
Work Cooperatively with ACHD to look at options for the
excess highway Right Of Way in Downtown Eagle, west of
Olde Park Place and east of the Eagle Senior Center.
Options should include parking, medians, and other traffic
calming items that benefit the vitality of Downtown Eagle.
Plan Years General Fund Impact Fees Outside
Source Total:
FY 24 $ $ N/A
FY 25 $ 30,000.00 $N/A
FY 26 $ $ N/A $ 30,000.00
FY 27 $ $ N/A
FY 28 $ $ N/A
Reserves
$
$
$
$
$
Carry Forward FY23
$ -
P a g e I 65
FY 2024-2028 CAPITAL PLAN
P&R CP-10 PAMELA BAKER
PARK
Department: Public Works & LRP&P
Staff: Eric Ziegenfuss &
Nichoel Baird Spencer
$2.2M Requested
Private Partnership up to 50%
Impact Fee Eligible up to $390K
Construction FY25—FY27
Phased construction of Pamela Baker Park located in the Lakemoor Develop-
ment. The preliminary design for the park was completed and approved by the
Eagle Design Review Board in 2023. The City constructed the 1st phase in
FY 2020 (bathroom, parking and pathway). The funding for construction is
primarily from park impact fees. The fund was diminished in 2022 and will
need time to recover. The City completed the irrigation pump in FY 23 at
$100K. Earlier phases of the project utilized all but $413K of the eligible
park impact fees. The City will need to find an additional $1.7M to finish the
project. Project is impact fee eligible up to $413K.
Plan Years General Fund Impact Fees Outside Total:
FY 24 $ $ $
FY 25 $ 300,000.00 $$ 300,000.00
FY 26 $ 287,000.00 $ $ 287,000.00 $ 2,200,000.00
FY 27 $ 200,000.00 $ 413,000.00 $ 413,000.00
FY 28 $ $ $
Reserves
$
$
$
$
$
Carry Forward
$ -
P a g e I 66
FY 2024-2028 CAPITAL PLAN
ED CP-5
IDAHO STREET
STREETSCAPE IMPROVEMENTS
Department: Economic Development
Staff: TBD
$600K Requested
No Match
Requested Year: 2027
Study FY26 - Construction FY28
Install curb, gutter, and enhanced sidewalks with lighting
and street trees on Idaho Street between 2nd Street and
Eagle Road. $100K in FY26 for engineering/Design,
$500K for construction. Project requires cost share with
ACHD and/or EURA.
Contingent on EURA as a funding partner.
Plan Years General Fund Impact Fees Outside Total:
FY 24 $ $ $
FY 25 $ $$
FY 26 $ 100,000.00 $ $ $ 600,000.00
FY 27 $ $ $
FY 28 $ 500,000.00 $ $
Reserves
$
$
$
$
$
Carry Forward FY23
$ -
P a g e I 67
FY 2024-2028 CAPITAL PLAN
ED CP-3
1ST STREET FESTIVAL
STREET
Department: Economic Development
Staff: TBD
$1.147M Requested
No Match
Requested Year: FY 2024
Study FY26 - Construction FY27
Create a festival street similar to the Basque Block in Boise that can
be used for events and overflow from Heritage Park. Install rolled
curb, gutter, and enhanced sidewalks with lighting and planters on
1st Street from Aikens to Idaho Street. $100K in FY 26 for engi-
neering/Design, $500K for construction. Project requires cost
share with ACHD and/or EURA.
Contingent on EURA as a funding partner.
Plan Years General Impact Fees Outside Total:
FY 24 $ $ $
FY 25 $ $$
FY 26 $ 100,000.00 $ $ $ 600,000.00
FY 27 $ 413,000.00 $ $
FY 28 $ $ $
Reserves
$
$
$
$ 87,000.00
$
Carry Forward FY23
$ -
P a g e I 69
FY 2024-2028 CAPITAL PLAN
PW CP-17 FLEET EXPANSION
Department: Public Works & Water
Staff: Eric Ziegenfuss
$50K Requested Annually
Purchase: As Needed
Funds will be used for fleet expansion on an as needed basis.
Funds will be carry forward each year until needed. Project
was brought back into the Capital Plan at the Mayor's
request.
Plan Years General Fund Impact Fees Outside Total:
FY 24 $ $ $
FY 25 $ $$
FY 26 $ 50,000.00 $ $ $ 250,000.00
FY 27 $ 50,000.00 $ $
FY 28 $ 50,000.00 $ $
Reserves
$ 50,000.00
$ 50,000.00
$
$
$
Carry Forward FY23
$ -
P a g e I 70
FY 2024-2028 CAPITAL PLAN
P&R CP-11 MACE PARK
Department: LRP&P & Public Works
Staff: Nichoel Baird Spencer &
Eric Ziegenfuss
$477K Requested
Impact Fee Eligible up to $23.5K
Engineering Design FY23
Construction FY24
Construct a greenbelt access, parking area, and native area on the southside
of the north channel of the Boise River, west of Eagle Road and the terminus
of the Eagle Road Ped/Bike Bridge. Project is 90% designed and ITD has
agreed to issue the permit and construct the improvements within the center
turn area of SH-55. Project is a good augmentation to the Ped/Bike bridge
completed in FY 23. Project is categorized as a park thus benefiting the
City's level of service. Project is impact fee eligible up to $577K. The park
impact fee fund was diminished in 2022 and will need time to recover and will
not be able to support this project.
Plan Years General Fund Impact Fees Outside Total:
FY 24 $ 500,000.00 $ $
FY 25 $ $$
FY 26 $ $ $ $ 500,000.00
FY 27 $ $ $
FY 28 $ $ $
Reserves
$
$
$
$
$
Carry Forward FY23
$ -
Project can be found at: hƩps://www.cityofeagle.org/2015/Mace-Park
P a g e I 71
FY 2024-2028 CAPITAL PLAN
T&P CP-8
T&P CP-9
PED/BIKE STUDIES
Floating Feather & Beacon Light Roads
Department: LRP&P
Staff: Nichoel Baird Spencer
$200K Requested Study Only
No Match - Seek ACHD Partnership
Study FY24
City is seeking ACHD support and partnership on complet-
ing Ped/Bike Plans for Floating Feather Road and Beacon
Light Road. This will include plans for pedestrian safety,
bike lanes/crossings, on street parking (as needed) and es-
tablishing mutually adopted cross sections for the two road-
ways between SH-16 & SH-55. Combined two projects into
a single study. Contingent on ACHD partnership.
Plan Years General Impact Fees Outside Total:
FY 24 $ $ $
FY 25 $ $$
FY 26 $ $ $ $ 200,000.00
FY 27 $ $ $
FY 28 $ $ $
Reserves
$ 200,000.00
$
$
$
$
Carry Forward FY23
$ -
P a g e I 72
FY 2024-2028 CAPITAL PLAN
P&R CP-12
MERRILL PARK
STORAGE BUILDING
Department: Public Works
Staff: Eric Ziegenfuss
$30K
No Match
Construction FY26
Construct a storage facility in Merrill Park
for park equipment and maintenance needs.
Plan Years General Fund Impact Fees Outside Total:
FY 24 $ $ $
FY 25 $ $$
FY 26 $ 30,000.00 $ $ $ 30,000.00
FY 27 $ $ $
FY 28 $ $ $
Reserves
$
$
$
$
$
Carry Forward FY23
$ -
P a g e I 73
FY 2024-2028 CAPITAL PLAN
ED CP-7
DOWNTOWN FAÇADE
IMPROVEMENT
Department: Economic Development
Staff: RTBD
$50 Requested Annually
Requires 50% Match from Eagle URA
FY 23–27 Plan Year: $ 50K per year
Beginning in FY 26
Provide incentives to Downtown businesses to bring facades,
signage, and sidewalk improvements into new standards. The
City should work with the EURA to cost share on the project
City will fund at $25K/year starting in FY 26 and asking EURA
to match at $25K annually to full fund.
Contingent on Eagle Urban Renewal Agency as a funding
partner.
Plan Years General Fund Impact Fees Outside Total:
FY 24 $ $ $
FY 25 $ $$
FY 26 $ $ $ $ 75,000.00
FY 27 $ 25,000.00 $ $
FY 28 $ 25,000.00 $ $
Reserves
$
$
$ 25,000.00
$
$
Carry Forward FY23
$ -
P a g e I 74
FY 2024-2028 CAPITAL PLAN
PW CP-7 CITY ENTRY SIGN PLAN
Study Only
Department: Public Works
Staff: Eric Ziegenfuss
$10K Requested Study Only
$390K Construction
No Match
Study FY26
Re-evaluate the location of the City of Eagle Entry Arches to
determine if they are still in the appropriate locations or if they
need relocated. Consider any additional entry monumentation
locations for the City. This is a study only, the out come would
be a plan for new or relocated signs that will need funding in
future years.
Plan Years General Fund Impact Fees Outside Total:
FY 24 $ $ $
FY 25 $ $$
FY 26 $ $ $ $ 10,000.00
FY 27 $ $ $
FY 28 $ $ $
Reserves
$
$
$ 10,000.00
$
$
Carry Forward FY23
$ -
P a g e I 75
FY 2024-2028 CAPITAL PLAN
TRL CP-15
SOUTH CHANNEL @ EAGLE RD
PED/BIKE CROSSING
(Bridge & Underpass)
Department: PLANNING
Staff: Bill Vaughan
$100K Preliminary Design Only
Impact Fee Eligible
Study FY28
Begin the process, similar to the N. Channel, to conduct a feasibility
study of a ped/bike bridge across the S. Channel and a tunnel comment-
ing East/West across Eagle Road. Project should be submitted to
COMPASS as a Preliminary Development Plan and potential outside
funding of $50K for the study. The City should provide a $50K to bring
the project to full funding. COMPASS application needs to be made in
November of 2023 to fund in FY 28. Once complete City can deter-
mine timing of construction.
Contingent on COMPASS Project Development Funding.
Plan Years General Impact Fees Outside Total:
FY 24 $ $ $
FY 25 $ $$
FY 26 $ $ $ $ 100,000.00
FY 27 $ $ $
FY 28 $ 50,000.00 $ $ 50,000.00
Reserves
$
$
$
$
$
Carry Forward FY23
$ -
Similar project can be found at: hƩps://www.cityofeagle.org/2002/Eagle-Road-Pedestrian-and-Bicycle-Bridge
P a g e I 76
FY 2024-2028 CAPITAL PLAN
LIB CP-1
LIBRARY FACILITIES
MASTER PLAN
(Study Only)
Department: LIBRARY
Staff: Steve Baumgartner
$150K Study Only
Impact Fee Eligible
TBD
Begin saving for a Library Master Plan that will help direct investment,
expansion and the provision of services. This savings was set aside by the
Library Board before the Library became a City Dept. The project will
need to be ranked in future years for funding.
Plan Years General Impact Fees Outside Total:
FY 24 $ $ $
FY 25 $ $$
FY 26 $ $ $ $ 50,000.00
FY 27 $ $ $
FY 28 $ $ $
Reserves
$
$
$
$
$
Carry Forward FY23
$ 50,000.00
P a g e I 77