Resolution - 2023 - 23-18 - Purchasing Policy - 06/13/2023 RESOLUTION NO. 23-18
A RESOLUTION OF THE CITY OF EAGLE, IDAHO, AMENDING THE CITY OF EAGLE
PURCHASING POLICY; AND PROVIDING AN EFFECTIVE DATE.
WHEREAS, the City Council recognizes that efficient and cost-effective procurement of
goods, services and public works construction is an important aspect of local government operations;
and
WHEREAS, the City Council desires to endeavor to buy goods, services and public works
construction by way of a public accountable process that respects the shared goals of economy and
quality, as contemplated by Idaho Code §§67-2801 et seq.; and
WHEREAS, the Mayor and Council wish to amend the Purchasing Policy to conform with
recent changes to Idaho State Legislature, Senate Bill No. 1083.
NOW, THEREFORE, BE IT RESOLVED BY THE MAYOR AND CITY COUNCIL OF
THE CITY OF EAGLE, IDAHO as follows:
Section 1: That the City of Eagle hereby rescinds Resolution 22-04;
Section 2: That the City of Eagle hereby amends the Purchasing Policy, which policy is
attached hereto as Exhibit A and incorporated herein by reference as if set forth in full.
Section 3: That this resolution shall be in full force and effect on July 1, 2023 upon its
adoption and approval.
A
ADOPTED by the Eagle City Council, Eagle, Idaho, this day of June, 2023.
APPROVED:
Jas Pie ce, Mayor
ATTEST:
E ••O
• P •;'�
Tracy E. orn, CMC o ° Q p
City Cld& W }
: �:• o co {;�• o ;
1
City of Eagle
Procurement Policy
Resolution 23-18
Adopted by City Council
Approval Date: June 13, 2023
Effective Date: July 1, 2023
1
TABLE OF CONTENTS
OVERVIEW ................................................................................................................................... 3
PURCHASES EXEMPT FROM COMPETITIVE BIDDING ....................................................... 3
PURCHASING SERVICES AND PERSONAL PROPERTY
Purchases under $5,000 ................................................................................................................ 4
Purchases $5,000 - $74,999 .......................................................................................................... 5
Purchases $75,000 - $150,000 ...................................................................................................... 5
Purchases Greater than $150,000
Competitive Sealed Bid option ................................................................................................ 5
Request for Proposal option ..................................................................................................... 7
JOINT PURCHASING AGREEMENTS ..................................................................................... 7
PURCHASING PUBLIC WORKS CONSTRUCTION
Public Works Contracts for Less than $50,000 .............................................................................8
Public Works Construction Projects $50,000 - $200,000............................................................. 8
Public Works Construction Projects greater than $200,000 ...........................................................
Option A: Formal Bidding .......................................................................................................... 8
Option B: Prequalified Bidders ................................................................................................ 10
Required Use of Licensed Public Works Contractors ............................................................... 13
Use of City Employees for Public Works Construction Projects ............................................... 15
EMERGENCY AND SOLE SOURCE PROCUREMENT ....................................................... 15
RECIPROCAL PURCHASING PREFERENCE LAW ............................................................. 16
SALES & USE TAX EXEMPTION ............................................................................................ 17
QUALIFICATIONS-BASED SELECTION OF DESIGN PROFESSIONALS
CONSTRUCTION MANAGERS AND PROFESSIONAL LAND SURVEYORS ................... 18
MISCELLANEOUS ..................................................................................................................... 19
Page 3 of 20
OVERVIEW
The purpose of this policy is to establish goals and clarify the procedures for purchasing
supplies, materials, and services by the City of Eagle and ensure compliance with Idaho
law. Procedures vary for bidding on public works; for purchasing materials and supplies
unrelated to public works; and for purchasing architectural, engineering or landscape
architectural services. There are also different thresholds that determine whether the City
may make purchases without going out for bid. These processes establish sound policies
and procedures in the pursuit of efficient and cost-effective procurement that will result in
the most beneficial outcome for the City. All City employees shall be diligent in practicing
good stewardship of public resources.
Throughout the entirety of this policy the following criteria shall be applied in addition to
the other processes and procedures identified.
Confirmation of budgeted item and fund availability: All purchases of goods or
services must be within the current year appropriated budget.
For purchases of goods or services over $5,000:
Mayor approval prior to purchase and confirmation of availability of funds must be
received by the City Treasurer or designee.
Contracts/Agreements:
The City Attorney shall review all contracts/agreements prior to Council action. Council
approval is required prior to the execution of the document by the Mayor.
PURCHASES EXEMPT FROM COMPETITIVE BIDDING
Exclusions from competitive bidding are established in Idaho State Code §67-2803 and
§67-2807 as follows:
§67-2803(1) The acquisition of personal property when the procurement duplicates
the price and substance of a contract for like goods or services that has
been competitively bid by the state of Idaho, one (1) of its political
subdivisions, or an agency of the federal government;
§67-2803(2) Contracts or purchases where expenditures to procure public works
construction are less than fifty thousand dollars ($50,000), or where
expenditures to procure services or personal property are less than
seventy-five thousand dollars ($75,000), provided such contracts or
purchases shall be guided by the best interests of the political
subdivision procuring the goods and services as determined by the
governing board;
§67-2803(3) Disbursement of wages or compensation to any employee, official or
agent of a political subdivision for the performance of personal
services for the political subdivision;
§67-2803(4) Procurement of personal or professional services to be performed by
Page 4 of 20
an independent contractor for the political subdivision;
§67-2803(5) Procurement of an interest in real property;
§67-2803(6) Procurement of insurance;
§67-2803(7) Costs of participation in a joint powers agreement with other units of
government;
§67-2803(8) Procurement of used personal property;
§67-2803(9) Procurement from federal government general services administration
(GSA) schedules or federal multiple award schedules (MAS);
§67-2803(10) Procurement of personal property or services through contracts
entered into by the division of purchasing of the department of
administration of the State of Idaho;
§67-2803(11) Procurement of goods for direct resale;
§67-2803 (12) Procurement of travel and training;
§67-2803(13) Procurement of goods and services from Idaho correctional industries;
§67-2803(14) Procurement of repair for heavy equipment;
§67-2803(15) Procurement of software maintenance, support and licenses of an
existing system or platform that was bid in compliance with state law;
§67-2803(16) Procurement of public utilities;
§67-2803(17) Procurement of food for use in jails or detention facilities; or
§67-2803 (18) Procurement of used equipment at an auction if authorized by the
governing board.
As a matter of practice, staff should consult the Idaho State Code section referenced above
to stay abreast of legislative changes.
COOPERATIVE PURCHASING
With the approval of its governing board, a political subdivision may participate in cooperative
purchasing agreements with the state of Idaho, other Idaho political subdivisions, other
government entities, or associations thereof. Political subdivisions may also participate in
cooperative purchasing programs established by any association that offers its goods or services
as a result of competitive solicitation processes. Goods or services procured by participation in
such cooperative agreements or programs shall be deemed to have been acquired in accordance
with the requirements of this chapter. I.C. 67-2807
PURCHASING SERVICES AND PERSONAL PROPERTY
Purchasing of services (e.g. janitorial services, landscape maintenance) and personal
property (e.g., automobiles, equipment, supplies) follows the process outlined as follows:
• For Purchases under $5,000 I.C. 67-2806
Department Supervisor approval is required for purchases under $5,000.
Department Supervisors are responsible for monitoring budget revenue and
expenditure balances and ensuring that all expenses are within the current year
appropriated budget. Additional internal controls may be implemented to ensure
Page 5 of 20
efficient, cost effective and responsible purchasing within each Department.
• For Purchases Between $5,000 and $74,999 I.C. 67-2806
If the price of the contract or purchase is estimated between $5,000 and $74,999 the City
has the discretion to purchase from any vendor believed to provide the best value.
Department Supervisors shall obtain Mayoral approval prior to the purchase. Purchases
must be within the current year appropriated budget, and confirmation of fund availability
confirmed with City Treasurer or designated representative. Additional internal controls
may be implemented to ensure efficient, cost effective and responsible purchasing within
each Department.
• For Purchases Between 75,000- $150,000 I.C. 67-2806(1)
o The city must make a written request for bids (by electronic or physical
delivery) to at least three (3) vendors. The request should describe: the
personal property or services to be purchased or leased; the method(s) for
vendors to submit their bids (again, by either electronic or physical delivery);
the date and time by which bids must be received by the clerk or other
authorized official; and a reasonable time to respond, with a minimum of at
least three (3) business days, except in an emergency.
o Written objections to specifications or bid procedures must be received by
the clerk or other authorized official at least one (1) business day before the
bids are scheduled to be received.
o When the bids are received, they are compiled and submitted to the city
council (or an official authorized by the council) for approval of the lowest
responsive bid or all bids are rejected, and the process starts over again.
o If the city determines that it is impractical or impossible to obtain three (3)
bids, the city may acquire the property (services or personal property) in any
manner the city deems best from the qualified vendor quoting the lowest
price. When fewer than three (3) bids are considered, the city must document
its efforts to obtain three (3) bids and maintain this documentation, along
with the written trail from solicitation to acceptance of bids, for at least six
(6) months after the purchase. If two (2) or more vendors tie for the lowest
bid, the council or its authorized official may select either vendor at its
discretion.
• For Purchases Greater than150,000: I.C. 67-2806(2)
There are two options for purchases greater than $150,000. Competitive Sealed
bid and Request for Proposal (RFP) Alternative.
Option A : Competitive Sealed Bid: For Purchases Greater than $150,000: I.C.
67-2806(2)
COMPETITIVE SEALED BID:
The purchase or lease must be made following a competitive sealed bid process
from the qualified vendor submitting the lowest bid in compliance with bidding
procedures and meeting the city’s specifications.
Page 6 of 20
Publication requirement: The process begins when the city publishes two (2)
notices soliciting bids in the official city newspaper, with the first notice at least
two (2) weeks before bid opening and the second notice at least a week prior to
bid opening.
The notice must succinctly describe the personal property or services to be
procured and must state that specifications, bid forms, instructions, contract
documents and other information are available upon request to any interested
bidder.
Written objections by bidders concerning specifications or bidding procedures
must be received by the clerk or other authorized official at least three (3) business
days before the scheduled bid opening.
Bid Security: The city may require bid security of at least five percent (5%) of the
amount of the bid. If security is required, a bid may not be considered unless
security is provided in the form required by the city, including:
• Cash,
• Cashier’s check payable to the city,
• Certified check payable to the city, or
• Bidder’s bond executed by a qualified surety company payable to
the city.
Public Bid Opening: Any bid received by the city may not be withdrawn after the
time set for opening of bids. The sealed bids are opened in public at the date, time
and place specified in the published notices and thereafter are compiled and
submitted to the city council.
Contract Award: The city council may award the contract to the vendor
submitting the lowest responsive bid, reject all bids and go through the process
again, or it may decide that the goods or services can be purchased more
economically on the open market. If two (2)or more bids are the same and are the
lowest responsive bids, the city council may accept either in its discretion. The
city council may also preauthorize the purchase of equipment at public auction.
If the city council chooses to award to a bidder other than the apparent low bidder,
the council must declare its reasons on the record and must communicate these
reasons in writing to all vendors submitting bids.
Objections: Participating bidders have seven (7) calendar days from the date of
transmittal of the notice to respond in writing with their objections. If objections
are received, the purchase is stayed while the city council reviews its decision and
determines whether to affirm its prior award, modify the award or choose to re-
bid, stating its reasons. After completion of the review process, the city may
proceed as it determines is in the public interest.
Failure to execute contract: If the successful bidder fails to execute the contract,
Page 7 of 20
the bid security may be forfeited to the city at the discretion of the council and
the proceeds deposited in a designated fund out of which reasonable expenses of
procuring substitute performance are paid. Upon failure or refusal of the
successful bidder to execute the contract, the city may award to the next lowest
qualified bidder. The lowest bidder’s security may be applied by the city to the
difference between the two (2) bids. The surplus, if any, shall be returned to the
lowest bidder if cash or check is used, or to the surety on the bidder’s bond if a
bond is used, less reasonable administrative costs not to exceed twenty -five
percent (25%) of the amount of the bidder’s security. I.C. §67-2806
Option B: Request for Proposal Alternative (RFP) For Purchases Greater than
$150,000: I.C. 67-2806(2)
REQUEST FOR PROPOSAL ALTERNATIVE (RFP) I.C. §67-2806:
The city may utilize a request for proposal process as an alternative to the competitive
bid process for procurement of goods or services for which fixed specifications might
preclude discovery of a cost-effective solution, or where a problem may be amenable
to several solutions, or price is not the sole determining factor.
Evaluation of vendors: Evaluation of vendors can be based on a variety of
factors including innovative solutions, unique product features, price,
experience, financial stability, the ability to perform contract requirements in
a timely or efficient manner, the ability to meet product specifications, product
quality or performance records, past vendor performance, future product
maintenance or service requirements, and product warranties.
RFP required contents: The request for proposal should describe the
instructions of the process, the scope of work, the selection criteria, contract
terms and the scoring methodology to be applied.
Notification requirements: Notification, solicitation and consideration of
contests concerning the award of procurement pursuant to a request for proposal
shall be in accordance with the minimum requirements established in Idaho
Code §67- 2806 which states: The process begins when the city publishes two
(2) notices soliciting bids in the official city newspaper, with the first notice at
least two (2) weeks before bid opening and the second notice at least a week
prior to bid opening.
Scoring record retention: Records compiled during the scoring process shall
be made available for public inspection when the purchasing recommendation
is made to the city council. I.C. §67-2806
JOINT PURCHASING AGREEMENTS
A city may enter into joint purchasing agreements with the State of Idaho and other local
governments, and local governments may also participate in such agreements established
by nonprofit associations of local governments. Purchases of personal property by the joint
Page 8 of 20
purchasing programs must comply with the competitive bidding law. Goods and services
procured by participation in such purchasing agreements and programs shall be deemed as
having been acquired in accordance with the competitive bidding process. I.C. §67-2807
PURCHASING PUBLIC WORKS CONSTRUCTION
Cities are granted express authority to prequalify public works contractors, thus ensuring
that contractors have the requisite experience, equipment and personnel to undertake a
particular project.
Cities are required to use a licensed public works contractor for jobs over $50,000.
The competitive bidding thresholds for public works construction are as follows:
For Public Works Construction Projects Less Than $50,000 I.C. §67-2803:
The city can purchase from any public works contractor believed to provide the best
value.
For Construction Projects Between $50,000 & $200,000 I.C. §67-2805(1):
• The city must submit a written request (by electronic or physical delivery) for
bids, describing the work to be done, to at least three (3) licensed public works
contractors selected by the city. The request should also specify the method for
contractors to submit their bids (either by electronic or physical delivery) and
the date, time and place by which bids must be received. The city must allow a
reasonable time for bidders to respond at least three (3) business days, except
in an emergency.
• Prospective bidders may submit objections to the bidding procedures or
specifications up to one (1) business day before bids are scheduled to be
received.
• The city must accept the lowest responsive bid of the licensed public works
contractors chosen by the city to submit bids or reject all bids and go through
the process again.
• If the city finds it is impractical or impossible to obtain three (3) bids, the city
may acquire the work in the manner it deems best from the qualified public
works contractor quoting the lowest price. When fewer than three (3) bids are
considered, the city needs to document its efforts to obtain three (3) bids, along
with the written trail from solicitation to acceptance of bids and must keep the
documentation for at least six (6) months after the contract is awarded. If two
(2) or more contractors submit the same low bid, the city council or its
authorized official may select whichever contractor it desires.
For Construction Projects Greater than $200,000 I.C. §67-2805(2):
Two Options are available:
Option A: Formal Bidding
Under this option, the city must accept bids from any licensed public works
contractor, and the city may only consider:
Page 9 of 20
a. The amount of the bid.
b. The bidder’s compliance with administrative requirements
c. Whether the bidder holds the requisite public works contractor’s license.
Publication requirement: The city must publish two (2) notices soliciting bids in
the official city newspaper, the first at least two (2) weeks before bid opening and
the second at least a week before bid opening. The notices must succinctly
describe the project to be constructed and inform prospective bidders that
specifications, bid forms, instructions, contract documents and other materials are
available upon request for a reasonable copying fee.
Written objections: Written objections to specifications or bidding procedures
must be received by the clerk or other authorized official at least three (3) business
days before scheduled bid opening. The clerk/authorized official or city council
must respond, in writing, to the objector and all other prospective bidders,
adjusting the timeframe for submission of bids if necessary.
Security: The city may require bid security of at least five percent (5%) of the
amount of the bid. If security is required, a bid may not be considered unless
security is provided in the form required by the city, which may include:
• Cash,
• Cashier’s check payable to the city,
• Certified check payable to the city, or
• Bidder’s bond executed by a qualified surety company payable to
the city.
Sealed bids: Submitted bids must be sealed, with an indication on the outside
identifying the project. Any bid received by the city may not be withdrawn after
the date and time of bid opening. The sealed bids are opened in public at the date,
time and place specified in the published notices and thereafter are compiled and
submitted to the city council.
Award of bid: The city council awards the contract to the qualified bidder
submitting the lowest responsive bid or may reject all bids and re-bid the project.
The city council may also, after determining it to be true, declare that the project
can be performed more economically by purchasing goods and services on the
open market. If identical bids are submitted and are the low bid, the city council
may choose the bidder it prefers. If no bids are received, the city council may
procure without further competitive bidding procedures.
If the city council chooses to award to a bidder other than the apparent low bidder,
the city council must declare its reasons on the record and must communicate
these reasons in writing to all those submitting bids.
Page 10 of 20
Objection to bid: Participating bidders have seven (7) calendar days from the date
of transmittal of the notice to respond in writing with their objections. The
procurement is stayed while the city council reviews its decision and determines
whether to affirm its prior award, modify the award or choose to re-bid, as it
deems to be in the public interest.
Failure to Execute Contract: If the successful bidder fails to execute the contract,
the bid security may be forfeited to the city and the proceeds may be deposited in
a designated fund out of which the expenses of procuring substitute performance
are to be paid. If the successful bidder refuses or fails to execute the contract, the
city may award the contract to the qualified bidder submitting the next lowest
responsive bid. If this occurs, the original contractor’s security may be applied to
the difference between the two (2) bids, and any surplus remaining must be
returned to the original contractor if cash or check is used or to the surety on the
bidder’s bond if a bond is used (less reasonable administrative costs not to exceed
twenty-five percent (25%) of the amount of the security).
Option B: Prequalifying Bidders:
Under this option, bidding is open only to those licensed public works contractors
meeting the required qualifications established by the city. This process consists
of two (2) stages:
a. The first establishing a list of prequalified contractors, and
b. The second where sealed bids are submitted from prequalified contractors.
Prequalification process: The city publishes notice of prequalification of
contractors twice (2) in the official newspaper, providing a date and time by which
statements of qualifications must be received and the standards for evaluating
qualifications of prospective bidders. The first publication must be at least two (2)
weeks before the deadline and the second publication at least one (1) week before
the deadline.
The city may establish prequalification standards based on the following criteria:
• Demonstrated technical competence;
• Experience constructing similar facilities;
• The contractor’s prior experiences with the city;
• The contractor’s available non-financial resources, equipment and
personnel as they relate to the particular project; and
• The contractor’s overall performance history.
Licensed contractors desiring to be prequalified must submit a written response to
the city’s request for qualifications. Written objections to prequalification
procedures must be received by the clerk or other authorized official at least three
(3) business days before statements of qualifications are due. The clerk/authorized
official or city council must respond to the objections in writing, to all those
seeking to prequalify, adjusting the timeframe for submission of statements of
Page 11 of 20
qualifications if necessary.
Selection of Qualified Contractors: After reviewing statements of qualifications,
the city may select the licensed contractors meeting its criteria. The city must
provide a written explanation to any licensed contractor that fails to meet the
prequalification standards. Any licensed contractor that fails the prequalification
stage can appeal to the city council within seven (7) days after transmittal of the
prequalification results. If the council upholds the decision, it must state its reasons
on the record. Decisions of the city council may be appealed to the public works
contractor licensing board no more than fourteen (14) days following any decision
on appeal made by the council. The board must decide the appeal within thirty -
five (35) days after an appeal is filed. The appealing contractor and the city can
participate in the hearing by either written or oral communication. The board shall
not substitute its judgment for that of the city, and the board’s review is limited to
determining the following:
• Was the city council’s decision consistent with the announced
prequalification standards?
• Do the prequalification standards meet the requirements of the law?
• Is the council’s decision supported by the entirety of the record?
The board must issue its decision in writing, outlining the reasons for its decision.
Any licensed contractor deemed unqualified by a decision of the board may seek
judicial review of the decision within twenty-eight (28) days after the board’s
decision. The prequalification process is stayed during a pending appeal to the
board, but in no instance for more than forty-nine (49) days after the council’s
appellate decision.
Post Prequalification of Bidders
Notice to Pre-qualified Prime Contractor: The bidding stage commences by a
notice of the time, date and place of the public opening of bids. If the city is seeking
a prequalified prime contractor, the notice is sent to the prequalified prime
contractors at least two (2) weeks prior to bid opening.
Notice to Pre-Qualified Specialty or subordinate contractor: If the city is seeking
a prequalified specialty or subordinate contractor, then the notice is published, with
the first publication at least two (2) weeks prior to bid opening and the secon d
publication at least one (1) week prior to bid opening. The notice must succinctly
describe the project and indicate that copies of specifications, bid forms,
instructions, contract documents and general and special instructions are available
upon request and payment of a reasonable copying fee.
Bid Submittal: Sealed bids must be presented to the clerk or other authorized
official, with a concise statement on the outside indicating the particular project.
Page 12 of 20
Bid Objections: Written objections to the specifications or bidding procedures
must be received by the clerk or other authorized official at least three (3) business
days before the scheduled bid opening.
Bid Security: The city may require bid security of at least five percent (5%) of the
amount of the bid. If security is required, a bid may not be considered unless
security is included in the form required by the city, including:
• Cash,
• Cashier’s check payable to the city,
• Certified check payable to the city, or
• Bidder’s bond executed by a qualified surety company payable to the city.
Bid opening: Any bid received by the city may not be withdrawn after the date and
time of bid opening. The sealed bids are opened in public at the date, time and
place specified in the notice, and are then compiled and submitted to the city
council for award.
Award of bids: The council awards to the prequalified bidder submitting the lowest
bid; rejects all bids and re-bids the project; or declares that the project can be
performed more economically by purchasing goods and services on the open
market. If identical low bids are received, the city council may choose the bidder
it prefers. If no bids are received, the council may purchase without further
competitive bidding.
If the city council chooses to award to a bidder other than the apparent low bidder,
the council must declare its reasons on the record and communicate these reasons
in writing to those submitting bids.
Objection to bid: Participating bidders have seven (7) calendar days from the date
of transmittal of the notice to respond in writing with their objections. The
procurement must be stayed while the city council reviews its decision and
determines whether to affirm its prior award, modify the award or choose to re-
bid, as it deems in the public interest, stating its reasons.
Failure to Execute contract: If the successful bidder fails to execute the contract,
the bid security may be forfeited to the city and the proceeds may be deposited in
a designated fund out of which the expenses of procuring substitute performance
are paid. The city may thereafter award the contract to the qualified bidder
submitting the next lowest responsive bid. If this occurs, the original contractor’s
security may be applied to the difference between the two (2) bids, and any surplus
remaining must be returned to the original contractor if cash or check is used or to
the surety on the bidder’s bond if a bond is used (less reasonable administrative
costs not to exceed twenty-five percent (25%) of the amount of the security). I.C.
§67-2805
Page 13 of 20
If a bidder has made a clerical or mathematical mistake on a bid, the bidder may
be eligible to be released from the bid provided the city receives written notice
within five calendar days of the opening of the bids. The city must be satisfied that
a material mistake has actually been made. The bidder will not be allowed to rebid
on that project. Any bid security will be returned by the city. Bidders failing to
execute a contract and not satisfying the conditions of a mistake shall forfeit any
bid security. If the city determines that a bidder is entitled to relief, it shall prepare
a written report documenting the facts. The report is to be available for inspection
as a public record and filed with the city. If the second lowest responsible bidder
fails or refuses to execute the contract, the city may likewise award it to the next
lowest responsible bidders. On the failure or refusal of the second or next lowest
responsible bidders to execute a contract, their bidder’s security shall be likewise
forfeited. A city may determine it is in its best interests to cancel and rebid the
public works project and retain any forfeited bid security. I.C. §54-1904C
Cities which contract for public works construction may not require that a
contractor, subcontractor, material supplier or carrier pay its employees a
predetermined wage rate or specific employee benefits unless required by state or
federal law. Cities shall ensure that neither they nor any agent working on their
behalf require or prohibit bidders to enter into or adhere to any agreement with
labor organizations. I.C. §67-2809
Required Use of Licensed Public Works Contractors
Idaho law requires state and local governments to use licensed public works contractors for
public works construction projects over $50,000. I.C. §54-1901(c)
Public works construction includes any or all of the following branches:
(i) Heavy construction, which is defined as constructing substantially in its entirety
any fixed works and structures (not including “building construction”), without
limitation, for any or all of the following divisions of subjects: irrigation, drainage,
sanitation, sewage, water power, water supply, reservoirs, flood control, reclamation,
inland waterways, railroads, grade separations, track elevation, elevated highways,
hydroelectric developments, aqueducts, transmission lines, duct lines, pipelines,
locks, dams, dikes, levees, revetments, channels, channel cutoffs, intakes, drainage,
excavation and disposal of earth and rocks, foundations, piers, abutments, retaining
walls, viaducts, shafts, tunnels, airports, air bases and airways, and other facilities
incidental to the same;
(ii) Highway construction, which is defined as all work included in highway
construction contracts, including, without limitation, highways, roads, streets,
bridges, tunnels, sewer and street grading, street paving, curb setting, surfacing and
other facilities incidental to any of the same;
(iii) Building construction, which is defined as all work in connection with any
structure now built, being built, or hereafter built, for the support, shelter and
enclosure of persons, chattels, personal and movable property of any kind, requiring
Page 14 of 20
in its construction the use of more than two (2) unrelated building trades or crafts.
Specialty construction, which is defined as any work in connection with any public
works construction, requiring special skill and the use of specially skilled trades or
crafts.
(iv) Specialty construction, which is defined as any work in connection with any
public works construction, requiring special skill and the use of specially skilled
trades or crafts. I.C. §54-1901(c)
Public Works Contracts for Less than $50,000
Since the state law requirement for use of a licensed public works contractor has increased
from $10,000 to $50,000, the number of small contracts that won’t require a licensed
contractor will increase substantially. This gives public owners more flexibility, but it now
opens up a new responsibility to be sure that everyone who contracts understands the
implications. Because public property is not subject to lien laws that protect contractors
from owners who won’t pay, the contracting parties need to engage their city attorneys or
use payment and performance bonds on small contracts (an expensive practice). Payment
and performance bonds exist as a substitute for lien remedies in public construction.
For public works construction contracts with a value less than $50,000, lien authority
should be expressly disclaimed. An alternative method to resolve performance and payment
disputes should be incorporated in the contracts for smaller public works projects. The types
of projects we are highlighting include building remodeling, small paving jobs,
landscaping, etc.
Naming of Subcontractors:
General contractors must include in their bids the names and addresses of the
subcontractors responsible for plumbing, heating and air conditioning, and electrical work
under the contract. Subcontractors named by the general contractor must possess the
appropriate licenses or certificates of competency issued by the state of Idaho covering
the contractor work classification in which each respective subcontractor is named. Failure
of a general contractor to name subcontractors renders any bid submitted by the contractor
unresponsive and void.
In the event the general contractor secures the contract and is unable to finalize the terms
of agreement with a subcontractor for any reason other than cost, the general contractor
names another subcontractor within ten (10) days of being awarded the contract. The
general contractor must disclose to the city the cost of work to be performed by the
substitute subcontractor, and if less than the original subcontractor’s bid, the reduction in
cost must be passed on to the city. I.C. §67-2310
Payment and Performance Bonds
Idaho law requires contractors selected for public works construction projects equal to or
greater than $50,000 to provide performance and payment bonds:
• Performance bond of at least 85% of the contract amount, conditioned upon
the faithful performance of the contract in accordance with plans,
specifications and conditions, solely for the protection of the city.
Page 15 of 20
• Payment bond of at least 85 % of the contract amount, solely for the protection
of persons supplying labor, materials or renting, leasing or otherwise supplying
equipment to the contractor or subcontractors.
• Cities requiring performance or payment bonds in excess of 50% of total
contract amount shall not withhold from the contractor or subcontractor any
amount exceeding 5% of the total amount payable as retainage. The city shall
release to the contractor any retainage for those portions of the project accepted
by the city and the contractors as complete with 30 days after such acceptance.
Bonds shall be executed by a surety company or companies authorized to do
business in Idaho, or the contractor may deposit any of the type of government
obligations listed in I.C. §54-1901(2)(h), in lieu of furnishing a surety
company performance or payment bond or bonds.
• It shall be illegal for the invitation for bids, or any person acting or purporting
to act, on behalf of the city to require that such bonds be furnished by or
through a particular source. I.C. §54-1926
Any city that fails to obtain the necessary payment bond is required to make payment, upon
demand, to all persons supplying materials or labor under the contract and such persons
have a right of action against the city for up to one (1) year after the materials and/or labor
were furnished. I.C. §54-1928
Use of City Employees for Public Works Construction Projects
Idaho law does not restrict cities’ ability to undertake public works construction projects
with city employees (whether permanent or temporary). City employees are exempt from
the requirements for public works contractor licensing. Since the local government
purchasing law expressly exempts “disbursement of wages” to any city employee from the
requirements for competitive bidding, the city is only required to go through the
competitive bidding process for any materials or equipment purchased for the project.
I.C. §67-2803
EMERGENCY AND SOLE SOURCE PROCUREMENT
Emergency Expenditures: In the case of emergency expenditures, the city council declares
that an emergency exists (reciting with some detail why that is the case) and that public
interest and necessity demand the immediate expenditure of public money, as a result of:
• A great public calamity, such as an extraordinary fire, flood, storm, epidemic
or other disaster.
• It is necessary to do emergency work to prepare for the national or local
defense.
• It is necessary to do emergency work to safeguard life, health or property.
Once the council declares an emergency, the city may proceed to purchase without
competitive bidding.
Page 16 of 20
Sole Source Procurement: In the case of sole source procurement, the council must declare
that there is only one (1) source reasonably available for the public works construction,
services or personal property to be acquired, which includes:
• Where public works construction, services or personal property is required to
respond to a life-threatening situation or a situation that is immediately
detrimental to the public welfare or property.
• Where the compatibility of equipment, components, accessories, computer
software, replacement parts or service is the paramount consideration.
• Where a sole supplier’s item is needed for trial use or testing.
• The purchase of mass-produced movies, videos, books or other copyrighted
materials.
• The purchase of public works construction, services or personal property for
which it is determined there is no functional equivalent.
• The purchase of public utility services.
• The purchase of products, merchandise or trademarked goods for resale at a
local government facility.
• Where competitive solicitation is impractical, disadvantageous or unreasonable
under the circumstances.
Publication Requirements for Sole Source Procurement: For sole source procurement,
the city council declares that there is only one (1) vendor for the public works construction,
services or personal property to be acquired, and then publishes notice of the sole source
procurement in the official newspaper at least fourteen (14) days before awarding the
contract (publication is not required in the case of a life-threatening situation or a situation
that is immediately detrimental to public welfare or property). I.C. §67-2808
RECIPROCAL PURCHASING PREFERENCE LAW
Several states and provinces have established “purchasing preference” laws, providing that
bids from out-of-state vendors/contractors automatically have a specified percentage added
to the bid for the purpose of determining the low bidder. Idaho operates under a “reciprocal
preference” system that adds to the bids of out-of-state bidders the same percentage that
the bidder’s home state provides as preference for in-state vendors. This applies to bids for
procurement of public works, materials, supplies, services or equipment. I.C. §67-2348,
I.C. §67-2349
For the purposes of this section, any bidder domiciled outside the boundaries of the state
of Idaho may be considered as an Idaho domiciled bidder, provided that there exists for a
period of one (1) year preceding the date of the bid a significant Idaho economic presence
as defined herein. A significant economic presence shall consist of the following:
a) That the bidder maintain in Idaho fully staffed offices, or fully staffed sales
offices or divisions, or fully staffed sales outlets, or manufacturing facilities,
or warehouses or other necessary related property; and
b) If a corporation be registered and licensed to do business in the state of Idaho
Page 17 of 20
with the office of the secretary of state.
In the evaluation of paper product bids, those items that meet recycled content standards
may be given not more than a five percent (5%) purchasing preference. As such, those
qualifying paper products may be considered to cost five percent (5%) less when choosing
the lowest responsible bidder. I.C. §67-2349
There are several important considerations to keep in mind when examining purchasing
preferences:
• Purchasing preferences only apply to purchases of materials, supplies,
equipment, services and public works construction that are competitively bid
(anything over $50,000 and any other purchases that the city decides to
competitively bid).
• Preferences do not apply to sole source or emergency purchases.
• State of domicile means: where a corporation is chartered or incorporated, or
where a sole proprietor or partnership is located or has its permanent
headquarters.
• The purchasing preference is only added to the amount of the bid for the
purpose of determining the low bidder, and the city does not pay that amount
to the low bidder.
SALES & USE TAX EXEMPTION
The State of Idaho and local governments are exempt from Idaho sales and use tax. Tax-
exempt entities must provide merchants with a completed Sales Tax Resale or Exemption
Certificate (ST-101). Merchants are required to keep a copy of this form in their records to
verify the tax-exempt status of the governmental entity. Once this form is on file with the
merchant, it covers all of the city’s future purchases. In addition to filling out the buyer and
seller information in the boxes on the top of this form, the buyer must checkmark the
“Federal/Idaho Government Entity” box in Paragraph 3, “Exempt Buyers.” Finally, the
buyer must sign, indicate a title, fill in the city’s Federal EIN and date the form at the
bottom. For tax-exempt cash purchases, a form ST-104G must be filled out for the vendor
and must be signed by the purchasing agent as well as the buyer.
Costs of hotel rooms for city officials on city business are exempt from sales tax when the
hotel is charged to a city credit card (form ST-104-HM is required)—cash payments,
payments with personal credit cards and payments reimbursed to the traveler are subject to
sales tax.
Purchases made by cities from out-of-state vendors that are delivered within Idaho are tax-
exempt. If the out-of-state vendor is registered to collect Idaho state sales tax, the city must
provide a valid, completed ST-101 to the vendor. Under no circumstances should a city
Page 18 of 20
pay sales tax to another state when the product is delivered in Idaho by the out-of-state
vendor or a common carrier. If items are purchased in another state and possession is taken
in that state, then the tax laws of that state determine what tax, if any, is owed. For example,
Oregon and Montana have no sales tax, but Washington allows no tax exemptions for
government agencies.
A prime or subcontractor is not exempt from sales and use tax simply because it is
performing a service for a government agency. The contractor must pay sales tax to the
vendor upon purchase of supplies or equipment or must pay use tax to the state if items are
purchased without paying tax or materials are directly received from a governmental entity.
QUALIIFICATIONS-BASED SELECTION OF:
DESIGN PROFESSIONALS, CONSTRUCTION MANAGERS AND
PROFESSIONAL LAND SURVEYORS I.C. §67-2806 and I.C. § 67-2320
Idaho law requires “qualifications-based selection” (QBS) of design professionals,
including architects, engineers, landscape architects, land surveyors, and construction
managers. All contracts/agreements for services must be approved by the City Council
prior to the execution of the document by the Mayor.
The QBS process differs from competitive bidding in that selection is based on
qualifications and demonstrated competence, not merely submission of the lowest bid.
For projects under $25,000:
If the price of the service is estimated under $25,000 the City has the discretion to
purchase from any vendor believed to provide the best value. Department
Supervisors shall obtain Mayoral approval prior to the purchase. Purchases must be
within the current year appropriated budget, and confirmation of fund availability
confirmed with City Treasurer or designated representative. Additional internal
controls may be implemented to ensure efficient, cost effective and responsible
purchasing within each Department.
For projects over $25,000: The city is required to use the QBS process outlined below.
Request for Qualifications Publication Requirements: Establishes the criteria, procedures
and qualifications for the services being sought. Publish a Request for Qualifications
(RFQ) twice, the first publication at least two (2) weeks before the deadline for submission
of statements of qualifications, the second publication at least one (1) week before the
deadline, in the official newspaper. The RFQ does not include price information, since this
is negotiated with the top-ranked firm once the scope of the project has been fully defined.
RFQ Contents:
A brief description specifying the type, scope and location of the project, along with
the projected project completion date.
A description of the professional services required.
Page 19 of 20
The criteria used to evaluate firms submitting statements of qualifications,
specifically: prior experience in similar projects, familiarity with federal and state
laws and regulations, experience with certain types of grants, etc.
That specifications, instructions and other documents are available to interested
persons.
That interested persons should submit statements of qualifications including: a brief
history of the firm; experience in similar projects; capability to undertake the project;
the names and qualifications of the project team; familiarity with the city; project
approach and preliminary schedule.
The deadline for submission of statements of qualifications, the physical address
and/or e-mail address to which statements should be sent and the name of a contact
person to answer questions and provide specifications and instructions.
The city may request information regarding a person’s or firm’s rates, overhead and
multipliers, if any, but shall not use the information provided for the purpose of
ranking in order of preference.
Selection of Firm:
The city selects the individual or firm it determines to be best qualified to provide the
required services, ranked in order of preference, according to the established criteria.
• The city negotiates with the highest-ranking individual/firm to perform the
services at a price determined by the city.
• If the city and the preferred individual/firm are unable to agree on contract
terms, including price, the city may repeat the process with the second ranked
individual/firm. If necessary, the process is repeated by continuing down the
list until the city reaches an agreement.
Allowance for Pre-Qualified Individuals/Firms:
Cities are also permitted to establish a list of prequalified individuals/firms for different
types of projects. The list must have at least two prequalified individuals/firms, and the
city is required to provide public notice of the prequalification process in the same manner
as for the RFQ process (outlined above). When a project comes up, the city can choose the
top ranked individual/firm from the prequalified list, rather than going through the public
notice and RFQ process each time. I.C. §67-2320
Prequalified lists should be updated every three (3) years, following the method prescribed
above.
MISCELLANEOUS
Donations
The City Council, with recommendation of the Mayor shall approve acceptance of all
donations of land and any donation of equipment or services valued over $5,000 including
those that may require expenditures of City funds for installation, maintenance, etc.
Page 20 of 20
Surplus Property
When the economic or useful life of property owned by the City is less than the cost of
maintenance, transportation, storage or other requirements, that property may be deemed
“surplus property”. These procedures do not address the disposal of real property.
Note: Disposal of real property is addressed in Title 50 Chapter 14, Idaho Code -. The
procedures established therein shall be followed.
• Property with a value of less than $1,000 requires Department Supervisor and
Mayor approval prior to be declared surplus and disposal action is taken.
• Property with a value of over $1,000 requires recommendation of declaration
of surplus property by the Department Supervisor, Mayor and adoption of a
resolution by the City Council.
•
Surplus property will be disposed of in a variety of methods which may include the
following:
• Donation to a charitable organization that qualifies under qualifies under
Section 501-C and 501-C(19) of the Internal Revenue Service or to any state
or local government,
• Surplus property may be transferred to a state or local government.
• Sold at public auction conducted by a licensed auctioneer.
• Sold to the highest bidder in response to notice of public sale advertised for at
least two (2) weeks in a newspaper of general circulation prior to such offering.
• The item(s) may be disposed of at a local refuse site.
• Be removed by an outside party willing to pay for its removal.