Service Solicited - 2023 - Fatbeam - Fatbeam Service Order #2 - Change Order DocuSign Envelope ID:AEA50D7B-37FC-448A-BCFE-622C32B275F7
509-344-1008 1 www.fatbeam.com
•:•:: •
fatbeam
January 3, 2023
Prepared for City of Eagle
DocuSign Envelope ID:AEA50D7B-37FC-448A-BCFE-622C32B275F7
�• • • 2065 W.Riverstone Dr.Suite 105
•••0 Coeur d'Alene,ID 83814
i T(509)344-1008
fatbe• F(509)344-1009
am www.fatbeam.com
Service Order # 2 — Change order
This Service Order#2,Change order("Service Order")is to update the completion dates for the installation of conduit
network("Service"), as more fully described below, pursuant to the terms and conditions of the Acceptable Use Policy,
Terms, and Master Service Agreement entered into by and between Fatbeam, LLC ("Fatbeam") and City of Eagle Idaho
("City")on January 25th 2022("Agreement"),and is effective as of July 6,2022,(Effective Date").Capitalized terms used
but not defined herein shall have the meaning set forth in the Agreement.
Billing address:660 E Civic Ln,Eagle,ID 83616
Build Details: (Location(s)where Service will be delivered)
Note: Fatbeam will be adhering to Ada County policy that requires all underground dry utilities be placed on the
or side of the road.
A)Joint Trench#1-Conduit will travel underground on at and travel to Build
is 11,864 feet. All per foot costs will be calculated at 11,864 feet.
o (2)- 1.25"conduits
o Dirt bore conditions are expected for entire 11,864 feet.
o Vaults-No vaults provided for this project
Item Description Cost Total Feet Extended Cost
Trench Per foot $ 4.00 0 $ -
Bore- Dirt Per foot $ 12.50 11864 $148,300.00
Bore-Cobble Per foot $ 18.25 0 $ -
1.25" Conduit Per foot, per conduit $ 0.75 11864 $ 17,796.00
Total Extended Cost $166,096.00
Start Date: September 2022
Completion Date:December 301h,2022-Due Date Change to: January 30th,2023
Fatbeam Internet I Updated 2018 2
DocuSign Envelope ID:AEA50D7B-37FC-448A-BCFE-622C32B275F7
B)Joint Trench#2-Conduit will travel underground on starting of and
travel to Build is 2,442 feet,all per foot costs will be calculated at 2,442 feet.
o (2)- 1.25"conduits
o Dirt bore conditions are expected for entire 2,442 feet.
o Vaults-No vaults provided for this project
Item Description Cost Total Feet Extended Cost
Trench Per foot $ 4.00 0 $ -
Bore- Dirt Per foot $ 12.50 2442 $ 30,525.00
Bore-Cobble Per foot $ 18.25 0 $ -
1.25" Conduit Per foot, per conduit $ 0.75 2442 $ 3,663.00
Total Extended Cost $ 34,188.00
Start Date: September 2022
Completion Date: December 301h,2022-Due Date Change to: March 3151,2023
C)Joint Trench#3-Conduit will travel underground on starting near traveling
to near Build is 4,782 feet,all per foot costs will be calculated at 4,782 feet.
o (2)- 1.25"conduits
o Dirt bore conditions are expected for entire 4,782 feet.
o Vaults-No vaults provided for this project
Item Description Cost Total Feet Extended Cost
Trench Perfoot $ 4.00 0 $ -
Bore- Dirt Per foot $ 12.50 4782 $ 59,775.00
Bore-Cobble Per foot $ 18.25 0 $ -
1.25" Conduit Per foot, per conduit $ 0.75 4782 $ 7,173.00
Total Extended Cost $ 66,948.00
Start Date:September 2022
Completion Date:December 30th,2022-Due Date Change to:March 3151,2023
Fatbeam Internet I Updated 2018 3
DocuSign Envelope ID:AEA50D7B-37FC-448A-BCFE-622C32B275F7
D)Joint Trench#4-Conduit will travel underground on ,travel to ,and
then to Build is 1,081 feet,all per foot costs will be calculated at 1081 feet.
o (2)- 1.25"conduits
o Dirt bore conditions are expected for entire 1,081 feet.
o Vaults-No vaults provided for this project
Item Description Cost Total Feet Extended Cost
Trench Perfoot $ 4.00 0 $ -
Bore- Dirt Per foot $ 12.50 1081 $ 13,512.50
Bore-Cobble Per foot $ 18.25 0 $ -
1.25" Conduit Per foot, per conduit $ 0.75 1081 $ 1,621.50
Total Extended Cost $ 15,134.00
Start Date:September 2022
Completion Date:December 301h,2022-Due Date Change to:January 315t,2023
E) Project-Build from to
1.Summary of Project:Fiber extensions from to
Fatbeam will pull fiber through the existing conduit from vault located behind
the From that point,Fatbeam will construct underground fiber optic cable to
2.Existing Conduit:Fatbeam will pull a 48-count fiber between the and the
existing located behind
3.Fiber Optic Electronics:Fatbeam will provide buried conduit with 144-count fiber
between the existing located behind to
4.Fiber Optic Hardware: Fatbeam will install fiber optic hardware( .
This hardware will provide connectivity from end to end,lighting the fiber.
Cost including construction and equipment.$153,620
Fatbeam Internet I Updated 2018 4
DocuSign Envelope ID:AEA50D7B-37FC-448A-BCFE-622C32B275F7
Ratification: This Service Order is requested by Customer and accurately describes the Service(s) being order and the
terms and conditions which govern the Service Order.Except as specifically set forth in this Service Order,the Agreement
is hereby ratified and affirmed in all respects and all other terms,covenants,and conditions of the Agreement shall remain
unchanged and shall continue in full force and effect.In case of an inconsistency or conflict between this Service Order
and the Agreement,the Agreement shall govern.All Exhibits are attached hereto and are incorporated herein by reference
and made a part of this Service Order.
IN WITNESS WHEREOF,the Parties have executed this document as of the date and year first above written.
IN WITNESS WHEREOF, Fatbeam and the City have each duly executed and delivered this Services
Agreement as of the Effective Date.
Fatbeam: The City:
Fatbeam, LLC City of Eagle
1E.
By:
by:
G,a.�
By: y:
Name: Graham Taylor Name: 14dr
Title: Director of Public Sector Title: m
Date: 1/3/2023 1 17:05 PST Date: �/a
ST: •` PGLE .
AT E c •••......•
O�•• �NTF
O •
Tracy E. O orn, City Clerk_ U; o '0• Qti ;
Fatbeam Internet Updated 2018 6