Loading...
Minutes - 2015 - Design Review - 08/12/2015 - RegularDESIGN REVIEW BOARD MINUTES The Design Review Board met in regular session, August 13, 2015, Chairman Grubb presiding. CALL TO ORDER: Chairman Grubb calls the meeting to order at 6:00 p.m. 2. ROLL CALL: The following members were present: GRUBB, SAYER, BRASHER, SCHAFER, BAER, ABSENT: HASH, MARTIN. A quorum is present. 3. CONSENT AGENDA ♦ Consent Agenda items are considered to be routine and are acted on with one motion. There will be no separate discussion on these items unless a Design Review Board member, City Staff, or a citizen requests an item to be removed from the Consent Agenda for discussion. Items removed from the Consent Agenda will be placed on the Regular Agenda in a sequence determined by the Rules of Order. ♦ Any item on the Consent Agenda that contains written recommendations from the City of Eagle shall be adopted as part of the Design Review's Consent Agenda approval motion unless specifically stated otherwise. A. Minutes of July 23, 2015. Brasher moves to approve the consent agenda. Seconded by Baer. ALL AYE ... MOTION CARRIES 4. UNFINISHED BUSINESS: A. DR -19 -13 MOD3 — Eagle Tennis Facility — Kara Hoge: Kara Hoge, represented by Eric Anderson with ALC Architecture, is requesting approval of the landscaping, temporary club house elevations, building and site lighting, and the building materials and colors to be used on the exterior of the tennis facility. The 12.12 -acre site is located near the southeast corner of State Highway 44 and South Edgewood Lane at 1650 East Riverside Drive. Member Schafer and Member Grubb recuse themselves from this item. Member Brasher takes over as Chair. Jeff Likes, with ALC Architecture, 1119 E. State St, Eagle, ID reviews the application. City Planner B. Williams reviews the application. Board discussion. John Rennison, 410 E. State Street, Eagle, addresses the Board. Brasher moves to approve DR- 19- 13MOD3 -Eagle Tennis Facility the responses the applicant has made to the site specific and standard conditions of approval with the following exception: Site specific condition #19, because LED lighting is not allowed per code and is not in the Boards purview to override the code, so that will need to be reviewed by staff and handled by City Council. Would like to make the following comments: K:�DESI_ REV\MIFNUTES Temporary Minutes Work Area\DR- 08- 13- 15MI714.doc Site specific #5: The landscape plan should be amended to clearly indicate the barbed wire along Hwy 55 should be removed. The parking lot drive aisle and spaces on the southern end of the property should be extended to the new property line as well as the interior sidewalk. Site specific condition #6: The mechanical units on the temporary buildings shall be painted to match the building. Site specific condition #7: No exterior restroom facilities were reviewed. Seconded by Baer. ALL AYE ... MOTION CARRIES. NEW BUSINESS: A. Plaza Drive Extension Landscape Design - City of Eagle: The City of Eagle is requesting Design Review Board review and recommendation on the Plaza Drive extension landscape design. The project includes a greenway and detached multi -use trail along the Spoils Bank Canal. The approximately 0.33 -mile long roadway extension will connect the intersection of East Plaza Drive and South 2nd Street to the terminus of East Plaza Drive located approximately 840 -feet west of East Iron Eagle Drive. Member Schafer and Member Grubb rejoin the meeting. Member Grubb takes over as Chair person. Member Baer recuses herself from this item. Talena Baer, Baer Design Group, 539 S. Fitness Place, Ste. 120, Eagle, reviews the application. Discussion with City Planner Nichoel Baird Spencer. Board discussion and comments. The Design Review Board recommends approval of the Plaza Street Extension landscape, lighting and irrigation design as follows: Recommend the use of the exercise stations and pursuing grant money for the purchase and installation of equipment. ACHD contract should include the construction of the concrete pads for the stations but nothing else. Recommend the use of Red Fescue within the drainage swales with irrigation at the back of the sidewalk. Recommend changing street tree spacing from 35 ft. aligned to 40 -45 ft. and increase tree grate size from 4ft. to 5ft minimum to ensure healthier trees and to keep the costs neutral due to the increased cost of the larger tree grates. Leave the drainage district easement in native state. Spray annually to keep weeds down and mow 1 -2 times per year. The drainage districts practice of storing the canal spoils on the bank makes gravel and/or plant material an unnecessary investment, as they will be covered. Trucking of the spoils is cost prohibitive and would require additional driveway cuts along the trail. 6. REPORTS: A. Design Review Board: None. B. Staff. Next meeting discussion. KADESI_REV \MINUTES \Temporary Minutes Work Area\DR- 08- 13- 15MIN.doc 7• ADJOURNMENT: Brasher moves to adjourn at 7:22 pm. Seconded by Sayer. ALL AYE ... MOTION CARRIES. RESPECTFULLY SUBMITTED: SHAR N K. BERGM CITY CLERK/TREASURER APPROVED: OB UBB CHAIRMAN goP-A'M. V 04 F ♦c S P+A,,c o ,977E OF AN AUDIO RECORDING OF THIS MEETING IS AVAILABLE AT CITY HALL UPON REQUEST. K:`DESI _REV \MINUTES\Temp —,y Minutes Work A.— DR- 08 -13 -1 SMR,4 -d- Task Order No. 15-01, Plaza Dr. Extension August 13, 2015 Preliminary Construction Cost Estimate (gravel DD2 path) MOBILIZATION 1 LS $10,000.00 $10,000.00 EXCAVATION TOPSOIL SOIL AMENDMENTS 50D - BLUE/RYE SOD - CREEPING RED FESCUE ROCK MULCH (3" DEPTH) 1400 897 66 18600 CY CY $30.00 $8.65 $12,110.00 $26,916.67 CY $60.00 $3,944.44 SF $1.50 $27,900.00 14000 35 ROCK MULCH (IRR DIST. EASEMENT, 3" DEPTH) 250 WEED BARRIER 30000 PAVER SURFACE 780 12" CONCRETE MOWSTRIP 110 10' DETACHED CONCRETE SIDEWALK 8010 3' ATTACHED CONCRETE SIDEWALK (NORTH SIDE OF PLAZA) 3075 SF $2.00 $28,000.00 CY $65.00 $2,256.94 CY $60.00 $15,000.00 SF $0.35 $10,500.00 SF $17.50 $13,650.00 SF $6.50 $715.00 SF $6.00 $48,060.00 SF $6.00 $18,450.00 PERGOLA 1 EA $20,000.00 $20,000.00 - a BENCH 2 EA $1,500.00 $3,000.00 TRASH RECEPTICLE 1 EA $500.00 $500.00 EXERCISE EQUIPMENT 8 EA $2,500.00 $20,000.00 SHRUB (1 GAL) 110 EA $12.50 $1,375.00 SHRUB (2 GAL) - - - - 34 EA $25.00 $850.00 SHRUB (5 GAL) 24 j EA $36.00 $864.00 TREE GRATES 34 EA $3,000.00 $102,000.00 TREES - DECIDUOUS (2" CAL) $1 50 EA $350.00 $17,500.00 TREES - CONIFER (6'-8') 4 EA $360.00 $1,440.00 IRRIGATION 36350 SF $0.50 $18,175.00 HISTORIC STREET LIGHTS 14 EA $5,400.00 $75,600.00 HANGING BASKETS AT HISTORIC LIGHT POSTS 14 EA $75.00 $1,050 00 CONSTRUCTION COST ESTIMATE 1 Yr Warranty and Grow -In (5% of Landscape Items) 5% CONTINGENCY TOTAL ESTIMATE 1 of 2 $479,857.06 $3,896.45 $23,992.85 TOTAL $507,746.36 kis 0 i C 1E115- BAER o Task Order No. 15-01, Plaza Dr. Extension August 13, 2015 Preliminary Construction Cost Estimate (fescue DD2 path) ITEM DESCRIPTION ESTIMATED QUANTITY UNIT UNIT PRICE MOBILIZATION EXCAVATION TOPSOIL SOIL AMENDMENTS SOD - BLUE/RYE SOD - CREEPING RED FESCUE ROCK MULCH (3" DEPTH) 1 ITEM TOTAL LS $10,000.00 $10,000.00 1400 897 66 18600 CY CY CY SF $1.50 $27,900.00 $8.65 $12,110.00 $30.00 $26,916.67 $60.00 $3,944.44 14000 SF $2.00 $28,000.00 35 CY $65.00 $2,256.94 SEED - CREEPING RED FESCUE (DD2 PATH) 46500 WEED BARRIER 30000 PAVER SURFACE 780 SF $0.50 $13,250.00 SF $0.35 $10,500.00 SF $17.50 $13,650.00 12" CONCRETE MOWSTRIP 110 10' DETACHED CONCRETE SIDEWALK 8010 3' ATTACHED CONCRETE SIDEWALK (NORTH SIDE OF PLAZA) 3075 PERGOLA 1 BENCH 2 TRASH RECEPTICLE 1 EXERCISE EQUIPMENT SHRUB (1 GAL) SHRUB (2 GAL) SHRUB (5 GAL) TREE GRATES TREES - DECIDUOUS (2" CAL) TREES - CONIFER (6'-8') IRRIGATION HISTORIC STREET LIGHTS HANGING BASKETS AT HISTORIC LIGHT POSTS 8 110 34 24 34 50 4 36350 14 14 SF $6.50 $715.00 SF $6.00 $48,060.00 SF $6.00 $18,450.00 EA $20,000.00 $20,000.00 EA $1,500.00 $3,000.00 EA $500.00 $500.00 EA $2,500.00 $20,000.00 EA $12.50 $1,375.00 EA $25.00 $850.00 EA $36.00 $864.00 EA $3,000.00 $102,000.00 EA $350.00 $17,500.00 EA $360.00 $1,440.00 SF $0.50 $18,175.00 EA $5,400.00 $75,600.00 EA $75.00 $1,050.00 CONSTRUCTION COST ESTIMATE 1 Yr Warranty and Grow -In (5% of Landscape Items) 5% CONTINGENCY TOTAL ESTIMATE 1 of 2 $478,107.06 $3,896.45 $23,905.35 TOTAL $505,908.86