Findings - CC - 2010 - CU-01-09 - Cup For Bank With Drive Up Service/0.971 Acre/80 E Riverside BEFORE THE EAGLE CITY COUNCIL -~ ['" ! {"'-,) l;l;.\"ll~ll ~..jJ ~ ~ ."-~ ! i L....... IN THE MATTER OF AN APPLICATION ) FOR A CONDITIONAL USE PERMIT FOR ) A BANK FACILITY WITH DRIVE UP ) SERVICE FOR CAPITAL EDUCATORS ) CREDIT UNION ) FINDINGS OF FACT AND CONCLUSIONS OF LAW CASE NUMBER CU-OI-09 The above-entitled conditional use permit application came before the Eagle City Council for their action on February 23, 2010, at which time testimony was taken and the public hearing was closed. The Eagle City Council having heard and taken oral and written testimony, and having duly considered the matter, makes the following Findings of Fact and Conclusions of Law; FINDINGS OF FACT: A. PROJECT SUMMARY: Capital Educators Credit Union, represented by Chad Slichter with Slichter Architects, is requesting condition use approval for a bank with drive up service. The 0.971-acre site is generally located at the northeast comer of the intersection of South Eagle Road and East Riverside Drive, Lot 2, Block 1, Mixed Use Subdivision No.2, at 80 East Riverside Drive. B. APPLICA TION SUBMITTAL: A Neighborhood Meeting was held at 462 E. Shore Drive (The Land Group) at 6:00 PM, November 19, 2009, in compliance with the application submittal requirement of Eagle City Code. The application for this item was received by the City of Eagle on November 23,2009. C. NOTICE OF PUBLIC HEARING: Notice of Public Hearing on the application for the Eagle Planning and Zoning Commission was published in accordance with the requirements of Title 67, Chapter 65, Idaho Code and the Eagle City Code on December 28,2009. Notice of this public hearing was mailed to property owners within three-hundred feet (300-feet) of the subject property in accordance with the requirements of Title 67, Chapter 65, Idaho Code and Eagle City Code on December 23,2009. The site was posted in accordance with the Eagle City Code on January 8, 2010. Requests for agencies' reviews were transmitted on December 7, 2009, in accordance with the requirements of the Eagle City Code. Notice of Public Hearing on the application for the Eagle Planning and Zoning Commission was published in accordance with the requirements of Title 67, Chapter 65, Idaho Code and the Eagle City Code on February 1, 2010. Notice of this public hearing was mailed to property owners within three-hundred feet (300-feet) of the subject property in accordance with the requirements of Title 67, Chapter 65, Idaho Code and Eagle City Code on January 26,2010. The site was posted in accordance with the Eagle City Code on February 13,2010. Page 1 of 14 K:\Planning Dept\Eagle Applications\CU\2009\CU-OI-09 ccfCapital Educators.doc D. HISTORY OF RELEVANT PREVIOUS ACTIONS: On January 25, 2000, the Eagle City Council approved a rezone with a development agreement (including a concept plan) for Eagle River Development (RZ-02-98). On April 24, 2001, the Eagle City Council approved a preliminary plat for Eagle River Development (PP-14-00). On May 8, 2001 the Eagle City Council approved a final plat application for Mixed Use Subdivision No. 1 (Eagle River Development) (FP-13-0 1). On September 13,2001, the Eagle City Council approved a design review application for the common area landscaping within the Eagle River Development (DR-70-00). On October 23, 2001, the Eagle City Council approved a combined preliminary plat and final plat for Mixed Use Subdivision No.2 (Eagle River Development) (PP/FP-OI-0l). E. COMPANION APPLICATIONS: Design review application to construct a 3,600-square foot bank facility with drive up service and ATM lanes for Capital Educators Credit Union bank facility (DR-41-09). Design review application to construct three (3) building wall signs for Capital Educators Credit Union bank facility (DR-42-09). F. COMPREHENSIVE PLAN LAND USE MAP AND ZONING MAP DESIGNATIONS: COMPPLAN ZONING LAND USE DESIGNATION DESIGNATION Existing Commercial C-3-DA (Highway Business Vacant District with Development Agreement) Proposed No Change No Change Bank with drive up service North ofsite Commercial C-3-DA (Highway Business Bank with drive up service District with Development Agreement) South of site Commercial C-3-DA (Highway Business Riverside Drive, bank with District with Development drive up service, Hilton Agreement) Garden Inn Hotel East of site Commercial C-3-DA (Highway Business Multi-tenant retail buildings District with Development Agreement) West of site Commercial C-l (Neighborhood Business Eagle Road/Channel Center District) Commercial Subdivision G. DESIGN REVIEW OVERLAY DISTRICT: Not in the DDA, TDA, CEDA, or DSDA. Page 2 of 14 K:\Planning Dept\Eagle Applications\CU\2009\CU-0 1-09 ccf Capital Educators,doc H. EXISTING SITE CHARACTERISTICS: The parcel is currently vacant with partial parking and drive aisle improvements completed with the construction of the Home Federal Bank to the north and the multi- tenant retail building to the east. Landscaping has been completed on the western and southern boundaries (improved with the development of the Eagle River commercial development). I. SITE DESIGN INFORMATION: SITE DATA PROPOSED REQUIRED Total Acreage of Site .917-acre 1 ,300-square feet Percentage of Site Devoted to Building 9.01% 92% - maximum coverage Coverage Percentage of Site Devoted to 41.3% 10% - Minimum Landscaping Number of Parking Spaces 38 18 Front Setback 58- feet O-feet minimum Rear Setback 69- feet O-feet minimum Side Setback 41-feet - lO-inches O-feet minimum Side Setback 28-feet - 4-inches O-feet minimum J. GENERAL SITE DESIGN FEATURES: Number and Uses of Proposed Buildings: One building is proposed to be constructed for the operation of a bank facility with three (3) drive up service lanes. Height and Number of Stories of Proposed Buildings: A single story building is proposed, measuring approximately twenty-seven feet (27') in height. Gross Floor Area of Proposed Buildings: 3,600 square-feet On and Off-Site Circulation: Patrons will enter the bank site on drive aisles from East Riverside Drive or Inlet Bay Lane located north and south of the site. The existing drive aisles provide reciprocal ingress- egress access among the adjacent lots (Home Federal Bank and the multi-tenant retail building). The proposed drive up service located on the south elevation of the building is accessed from the drive aisle located on the north side of the building then proceeding south along the west side of the building to the area where the drive up service is to be located. The drive up aisle provides access to three (3) drive up service facilities located on the south elevation of the building. Patrons exiting the drive up service lanes enter into the drive aisle east of the bank and may proceed south to East Riverside Drive or north to Inlet Bay Lane. Page 3 of 14 K:\Planning Depl\Eagle Applications\CU\2009\CU-0 1-09 ccf Capital Educators,doc K. PUBLIC SERVICES AVAILABLE: Sewer service will be provided through the Eagle Sewer District. The applicant will be required to submit construction plans to the Eagle Sewer District, Eagle Fire Department and Ada County Highway District for review and approval prior to the issuance of a building permit. Approval from Eagle Water Company will be required prior to the issuance of any building permits for the site. L. PUBLIC USES PROPOSED: None M. PUBLIC USES SHOWN ON FUTURE ACQUISITIONS MAP: No map currently exists N. SPECIAL ON-SITE FEATURES: Areas of Critical Environmental Concern - none Evidence of Erosion - no Fish Habitat - no Floodplain - yes - the applicant will be required to meet the floodplain requirements approved with the Eagle River development and provide the required elevation certificates. Mature Trees - yes - street trees adjacent to Riverside Drive Riparian Vegetation - no Steep Slopes - no Stream/Creek - no Unique Animal Life - no Unique Plant Life - no Unstable Soils - no Wildlife Habitat - no O. SUMMARY OF REVIEW OF ENVIRONMENTAL ASSESSMENT PLAN: Not required P. AGENCY RESPONSES: The following agencies have responded and their correspondence is attached to the staff report. Comments, which appear to be of special concern, are noted below: Chevron Pipe Line - No conflict with the pipe line Division of Environmental Quality - Provided overview of Air Quality, Wastewater and Reuse, Drinking Water, Surface Water and Hazardous Waste and Ground Water Contamination concerns. Eagle Fire Department - No opposition to the application and requested a full set of construction plans for review and approval prior to issuance of a building permit. Idaho Transportation Department - No comment Q. LETTERS FROM THE PUBLIC: None received to date R. EAGLE CITY CODE 8-7-3-2 GENERAL STANDARDS FOR CONDITIONAL USES: The Commission/Council shall review the particular facts and circumstances of each proposed Conditional Use in terms of the following standards and shall find adequate evidence showing that such use at the proposed location: A. Will, in fact, constitute a conditional use as established in Section 8-2-3 of this title (Eagle City Code Title 8) for the zoning district involved; Page 4 of 14 K:\Planning Dept\Eagle Applications\CU\2009\CU-01-09 ccfCapital Educators,doc B. Will be harmonious with and in accordance with the general objectives or with any specific objective of the Comprehensive Plan and/or this title (Eagle City Code Title 8); C. Will be designed, constructed, operated and maintained to be harmonious and appropriate in appearance with the existing or intended character of the general vicinity and that such use will not change the essential character of the same area; D. Will not be hazardous or disturbing to existing or future neighborhood uses; E. Will be served adequately by essential public facilities such as highways, streets, police and fire protection, drainage structures, refuse disposal, water and sewer and schools; or that the persons or agencies responsible for the establishment of the proposed use shall be able to provide adequately any such services. F. Will not create excessive additional requirements at public cost for public facilities and services and will not be detrimental to the economic welfare of the community; G. Will not involve uses, activities, processes, materials, equipment and conditions of operation that will be detrimental to any persons, property or the general welfare by reason of excessive production of traffic, noise, smoke, fumes, glare or odors; H. Will have vehicular approaches to the property which are designed as not to create an interference with traffic on surrounding public thoroughfares; and I. Will not result in the destruction, loss or damage of a natural, scenic or historic feature of major importance. STAFF ANALYSIS PROVIDED WITHIN THE STAFF REPORT: A. COMPREHENSIVE PLAN PROVISIONS, WHICH ARE OF SPECIAL CONCERN REGARDING THIS PROPOSAL: · The Comprehensive Plan Land Use Map (adopted 08-25-09) designates this site as: Commercial Suitable primarily for the development of a wide range of commercial activities including offices, retail and service establishments. Uses should complement uses within the central Business District. B. ZONING ORDINANCE PROVISIONS, WHICH ARE OF SPECIAL CONCERN REGARDING THIS PROPOSAL: · Eagle City Code Section 8-2-3 BanklFinancial Institution with drive up service requires the approval of a conditional use permit within the C-3 zoning district. · Eagle City Code Section 8-7-3-5 (F) A conditional use permit shall not be considered as establishing a binding precedent to grant other conditional use permits. Page 5 of 14 K:\Planning Dept\Eagle Applications\CU\2009\CU-0 1-09 ccf Capital Educators,doc C. DEVELOPMENT AGREEMENT PROVISIONS, WHICH ARE OF SPECIAL CONCERN REGARDING THIS PROPOSAL: 3.2.5 All development within the Property shall be consistent with the Site Design Guidelines ("Design Guidelines") attached hereto as Exhibit D and generally consistent with the Conceptual Plan attached hereto as Exhibit E. The Conceptual Plan attached hereto describe the general nature and relative location of certain elements fro the Property. The intent of this Agreement is to allow sufficient flexibility at the time of detailed planning and platting while still maintaining the general intent of the Conceptual Plan with the requirements set forth in this Development Agreement. D. DISCUSSION: · With the review of an application that includes the use of a drive up service, consideration should be given to surrounding uses and roadways due to noise and headlight glare created by the vehicles accessing the site. The pad is located within the existing Eagle River mixed use development. It should be considered that because existing commercial uses surround this site, there will be little impact on the adjacent properties and uses. The applicant is proposing to place the drive up service lanes on the south side of the building adjacent to East Riverside Drive. Although this location will allow for buffering the lanes from South Eagle Road and eliminate any potential vehicle headlight glare on South Eagle Road, there is still the potential of headlight glare on East Riverside Drive as the vehicles are queuing into the drive up service. The applicant should provide a minimum forty-eight inch (48") high berm, decorative block wall, cultured stone, decorative rock, or similarly designed concrete wall, landscaping, or combination thereof within the buffer area adjacent to the drive up service lane to reduce the impact of the vehicles utilizing the drive up service lane (i.e. vehicle headlights and vehicle queuing). · Typical bank facilities with drive up service lanes have outdoor intercom systems (for patrons) that may project sound outside of the bank's property boundaries. While this site is bounded on all sides by commercial property or roadways, this does not alleviate the creation of a possible nuisance to adjacent users. A public sidewalk is located approximately forty-five feet (45') south of the proposed drive up service lanes and adjacent to East Riverside Drive. The applicant has provided an audio system sound specification sheet showing the decibel levels (dB) associated with the proposed Diebold audio system. The specification sheet shows the audio system at a maximum level of output to be approximately 56 dBs at the sidewalk location without a vehicle present in the drive up service lane. This would be equivalent to a normal conversation at three feet (3 '). If a vehicle were present at the drive up service the dB level would be significantly reduced. · The proposed bank facility is proposed within an area of special flood hazard (ASFH). The applicant should be required to comply with Eagle City Code Title 10, Flood Control and the flood plain development requirements associated with the Eagle River development. The applicant should provide an Elevation Certificate (EC) prior to the issuance of a certificate of occupancy for the building. · Staff has reviewed the particular facts and circumstances of this proposed conditional use and, in terms of Eagle City Code Section 8-7-3-2 "A thru I" (required findings for approval of a conditional use), has made the following conclusions: Page 6 of 14 K:\Planning Dept\Eagle Applications\CU\2009\CU-0 1-09 ccf Capital Educators,doc The proposed conditional use; A. Will, in fact, constitute a conditional use as established in Section 8-2-3 of Eagle City Code Title 8 since a bank/financial institution with drive up service may be permitted in the C-3-DA (Highway Business District with a development agreement) zoning district if a conditional use permit is approved by the City Council; B. Will be harmonious with and in accordance with the general objectives or with any specific objective of the Comprehensive Plan and/or this title (Eagle City Code Title 8) since there are no inconsistencies with the Comprehensive Plan and since a bank/financial institution with drive up service is permitted with the approval of a conditional use within the C-3-DA (Highway Business District with a development agreement) zoning district and the Comprehensive Plan designates this site as Commercial; C. Will be designed, constructed, operated and maintained to be harmonious and appropriate in appearance with the existing or intended character of the general vicinity and that such use will not change the essential character of the same area since the bank/financial institution with drive up service is located within a commercial development which contains other bank/financial institutions with drive up service that are adjacent to this site and the design of the proposed structure must meet the City's design review requirements and the design requirements pursuant to the development agreement associated with the Eagle River development; D. Will not be hazardous or disturbing to existing or future neighborhood uses since the bank/financial institution with drive up service is to be located within a commercial development that currently has compatible commercial uses; E. Will be served adequately by essential public facilities that are currently available to the site such as highways, streets, police and fire protection, drainage structures, refuse disposal, sewer and schools; or that the persons or agencies responsible for the establishment of the proposed use shall be able to provide adequately any such services as noted in responses received by agencies providing the public services, or as conditioned herein; F. Will not create excessive additional requirements at public cost for public facilities and services and will not be detrimental to the economic welfare of the community since the site has been improved with essential public facilities such as streets, sewer and water services; G. Will not involve uses, activities, processes, materials, equipment and conditions of operation that will be detrimental to any persons, property or the general welfare by reason of excessive production of traffic, noise, smoke, fumes, glare or odors since the site will be required to provide outdoor communication systems that are designed to mitigate noise projection onto adjacent property, and the drive up service lanes have been placed on the south side of the building which buffers the lanes from South Eagle Road and eliminates any potential vehicle headlight glare on South Eagle Road and East Riverside Drive. H. Will have vehicular approaches to the property which are designed as not to create an interference with traffic on surrounding public thoroughfares as previously approved by the highway district having jurisdiction; and Page 7 of 14 K:\Planning Dept\Eagle Applications\CU\2009\CU-0 1-09 ccf Capital Educators,doc I. Will not result in the destruction, loss or damage of a natural, scenic or historic feature of major importance since none are apparent on this site. STAFF RECOMMENDATION PROVIDED WITHIN THE STAFF REPORT: Based upon the information provided to staff to date, staff recommends approval with the site specific conditions of approval and the standard conditions of approval provided within the staff report. PUBLIC HEARING OF THE COMMISSION: A. A public hearing on the application was held before the Planning and Zoning Commission on January 19 2010, at which time testimony was taken and the public hearing was closed. The Commission made their recommendation at that time. B. Oral testimony in opposition to this proposal was presented to the Planning and Zoning Commission by no one. C. Oral testimony in favor of this proposal was presented to the Planning and Zoning Commission by no one (not including the applicant/representative). COMMISSION DELIBERATION: Upon closing the public hearing the Commission indicated during deliberation that: · The proposed bank with drive up service is compatible with the uses adjacent to this site. · The Design Review Board will address the required buffering of the proposed drive up service lanes adjacent to East Riverside Drive. · There are no residential uses located in proximity to the site that will be impacted by the outdoor intercom system. COMMISSION DECISION: The Commission voted 4 to 0 (Smith absent) to recommend approval of CU-OI-09 for a conditional use permit for a bank facility with drive up service for Capital Educators Credit Union, with the site specific conditions of approval and standard conditions of approval as shown within their Findings of Fact and Conclusions of Law document, dated February 1,2010. PUBLIC HEARING OF THE COUNCIL: A. A public hearing on the application was held before the City Council on February 23,2010, at which time testimony was taken and the public hearing was closed. The Council made their decision at that time. B. Oral testimony in opposition to this proposal was presented to the City Council by no one. C. Oral testimony in favor of this proposal was presented to the City Council by no one (not including the applicant/representative ). D. Oral testimony neither in opposition nor in favor of the application was presented by one individual who had a concern with the width of the drive aisle located north of the subject site south of the Home Federal Bank site. It was indicated that the drive aisle does not meet the minimum twenty-four foot (24') width requirement. They indicated that when delivery trucks park in the drive-aisle or large pickups (extended or crew cab) are parked in the provided spaces they impede vehicles utilizing the drive aisle. They also indicated that large delivery trucks and pickups pulling recreation or construction equipment impact the drive aisle also. Page 8 of 14 K:\Planning Dept\Eagle Applications\CU\2009\CU-01-09 ccfCapital Educators,doc COUNCIL DECISION: The Council voted 4 to 0 to approve CU -01-09 for a conditional use permit for a bank facility with drive up service for Capital Educators Credit Union, with the following Planning and Zoning Commission recommended site specific conditions of approval and standard conditions of approval. SITE SPECIFIC CONDITIONS OF APPROVAL: 1. Only the use "BanklFinancial Institution with drive up service" is approved with the conditions noted herein. 2. Comply with all requirements of the development agreement dated, January 25, 2000, between the City of Eagle and Eagle River LLC, (instrument No. 100011692). 3. The applicant shall install measures to minimize the decibel level of the outdoor intercom system and its affects on adjacent properties (sound not to be audible at more than one-hundred feet from source). Details shall be submitted for review and approval by the Design Review Board prior to the issuance of any building permits. 4. The applicant shall provide a minimum forty-eight inch (48") high berm, decorative block wall, cultured stone, decorative rock, or similarly designed concrete wall, landscaping, or combination thereof within the buffer area adjacent to the drive up service lane to reduce the impact of the vehicles utilizing the drive up service lane (i.e. vehicle headlights and vehicle cueing). 5. The applicant shall be required to comply with Eagle City Code Title 10, Flood Control and the flood plain development requirements associated with the Eagle River development. The applicant shall provide a post construction Elevation Certificate (EC) (FEMA form 81-31) prior to the issuance of a certificate of occupancy for the building. 6. A building permit for this proposal shall be obtained within one year, otherwise the conditional use approval for a bank with drive up service shall be considered null and void. STANDARD CONDITIONS OF APPROVAL: I. The applicant shall comply with all requirements of the Ada County Highway District and/or the Idaho Transportation Department, including but not limited to approval of the drainage system, curbs, gutters, streets and sidewalks. A letter of approval from the highway district having jurisdiction shall be submitted to the City prior to issuance of any building permits or Certificate of Occupancy, whichever occurs first. 2. Idaho Department of Health & Welfare approval of the sewer and water facilities is required prior issuance of any building permits or Certificate of Occupancy, whichever occurs first. 3. All permits from Central District Health, Eagle Sewer District & Eagle Fire District, shall be secured prior to issuance of building permit or Certificate of Occupancy, whichever occurs first. 4. Written approval of all well water for any shared or commercial well shall be obtained from the Idaho Department of Water Resources shall be submitted to the City prior to issuance of any building permits or Certificate of Occupancy, whichever occurs first. 5. Unless septic tanks are permitted, wet line sewers will be required and the applicant will be required to furnish the City Engineer with a letter from the sewer entity serving the property, accepting the project for service, prior to issuance of any building permits or Certificate of Occupancy, whichever occurs firs t. Page 9 of 14 K:\Planning Dept\Eagle Applications\CU\2009\CU-0 1-09 ccf Capital Educators,doc 6. The applicant shall submit a letter from the appropriate drainage entity approving the drainage system and/or accepting said drainage; or submit a letter from a registered professional engineer certifYing that all drainage shall be retained on-site prior to issuance of any building permits or Certificate of Occupancy, whichever occurs first. A copy of the construction drawing(s) shall be submitted with the letter. 7. The applicant shall submit plans and calculations prepared by a registered professional engineer to handle the satisfactory disposal of all storm drainage on the applicant's site. Drainage system plans shall be submitted to the City Engineer for review and approval prior to issuance of any building permits or Certificate of Occupancy, whichever occurs first. The plans shall show how swales, or drain piping, will be developed in the drainage easements. The approved drainage system shall be constructed, or a performance bond shall be submitted to the City Clerk, prior to issuance of any building permits or Certificate of Occupancy, whichever occurs first. The lot shall be so graded that all runoff runs either over the curb, or to the drainage easement, and no runoff shall cross any lot line onto another lot except within a drainage easement. All design and calculations shall meet the requirements of Ada County Highway District. Construction of the storm drain disposal system shall be complete before an occupancy permit is issued. 8. No ditch, pipe or other structure or canal, for irrigation water or irrigation waste water owned by an organized irrigation district, canal company, ditch association, or other irrigation entity, shall be obstructed, routed, covered or changed in any way unless such obstruction, rerouting, covering or changing has first been approved in writing by the entity. A Registered Engineer shall certifY that any ditch rerouting, piping, covering or otherwise changing the existing irrigation or waste ditch (1) has been made in such a manner that the flow of water will not be impeded or increased beyond carrying capacity of the downstream ditch; (2) will not otherwise injure any person or persons using or interested in such ditch or their property; and (3) satisfied the Idaho Standards for Public Works Construction. A copy of such written approval and certification shall be filed with the construction drawing and submitted to the City prior to issuance of any building permits or Certificate of Occupancy, whichever occurs first. 9. Encroachments including, but not limited to, landscaping, fencing, lighting, and/or pathways shall not be located within any easement or right-of-way for any ditch, pipe or other structure, or canal used for irrigation water or irrigation waste water without the express written approval of the organized irrigation district, canal company, ditch association, or other irrigation entity associated with such ditch, pipe or other structure, or canal. The applicant shall submit a copy of the written approval from the irrigation entity prior to the City Clerk signing the final plat. 10. Street light plans shall be submitted and approved as to the location, height and wattage to the City Engineer (if applicable) prior to issuance of any building permits or Certificate of Occupancy, whichever occurs first. All construction shall comply with the City's specifications and standards. The applicant shall provide a recorded easement, acceptable to the City Engineer, for the purpose of installing and maintaining street light fixtures, conduit and wiring lying outside any dedicated public right-of-way, prior to issuance of any building permits or Certificate of Occupancy, whichever occurs first. The applicant shall pay applicable street light inspection fees prior to Certificate of Occupancy. II. Parking lot light plan shall be submitted and approved as to the location, height and wattage by the City Engineer. All construction shall comply with the City's specifications and standards. Lighting is required in the parking area and shall be properly illuminated to avoid accidents. Any lights used to illuminate the parking lot shall be so arranged as to reflect the light away from the Page 10 of 14 K:\Planning Dept\Eagle Applications\CU\2009\CU-01-09 ccfCapital Educators,doc adjoining property. 12. The parking area shall be paved and shall be maintained in good condition without holes and free of all dust, trash, weeds and other debris. 13. One set of building plans, for any non single-family residential use, shall be submitted to the Eagle Fire Department for approval. An approval letter from the Eagle Fire Department shall be submitted to the City prior to issuance of any building permits or Certificate of Occupancy, whichever occurs first. The letter shall include the following comments and minimum requirements, and any other items of concern as may be determined by the Eagle Fire Department officials: a. "The applicant has made arrangements to comply with all requirements ofthe Fire Department." b. The fire hydrant locations shall be reviewed and be approved in writing by the Eagle Fire Department prior to the City Engineer signing the final plat. c. Minimum flow per hydrant shall be 1,000 gallons per minute for one and two family dwellings, 1,500 gallons per minute for dwellings having a fire area in excess of 3,600 square feet, and 1,500 gallons per minute for non-residential uses (i.e.; Commercial, Industrial, Schools, etc.). Flow rates shall inspected in accordance with all agencies having jurisdiction, and shall be verified in writing by the Eagle Fire Department prior to issuance of any building permits or certificate of Occupancy, whichever occurs first. d. The proposed fire protection system shall be reviewed and approved by the Eagle Fire Department prior to issuance of a building permit or Certificate of Occupancy, whichever occurs first. 14. Any recreation area, greenbelt area or pathway area along the Boise River, Dry Creek or any other area designated by the City Council or Eagle City Pathway/Greenbelt Committee for a path or walkway shall be approved in writing by the Eagle City Pathway/Greenbelt Committee prior to issuance of a building permit or Certificate of Occupancy, whichever occurs first. 15. Conservation, recreation and river access easements (if applicable) shall be approved by the Eagle City Pathway/Greenbelt Committee and shall be shown on the final plat prior to issuance of a building permit or Certificate of Occupancy, whichever occurs first. 16. The applicant shall comply with the provisions of the Eagle City Code, pertaining to floodplain and river protection regulations (if applicable) prior to issuance of a building permit or Certificate of Occupancy, whichever occurs first. 17. The applicant shall obtain written approval of the development relative to the effects of the Boise River Flood Plain (if applicable) from the Corps. of Engineers prior to issuance of a building permit or Certificate of Occupancy, whichever occurs first. 18. The applicant shall obtain approval of the development relative to its effects on wetlands or other natural waterways (if applicable) from the Corps. of Engineers and the Idaho Department of Water Resources and/or any other agency having jurisdiction prior to issuance of a building permit or Certificate of Occupancy, whichever occurs first. 19. Basements in the flood plain are prohibited. 20. The Americans with Disabilities Act, Uniform Building Code, Eagle City Code, and all applicable County, State and Federal Codes and Regulations shall be complied with. All design and construction shall be in accordance with all applicable City of Eagle Codes unless specifically approved by the Commission and/or Council. 21. New plans, which incorporate any required changes, shall be submitted for staff approval. Staff may elect to take those plans to the Design Review Board and/or the Planning and Zoning Commission for review and approval. Page 11 of 14 K:\Planning Dept\Eagle Applications\CU\2009\CU-0 1-09 ccf Capital Educators,doc 22. Any changes to the plans and specifications upon which this approval is based, other than those required by the above conditions, will require submittal of an application for modification and approval of that application prior to commencing any change. 23. Any change by the applicant in the planned use of the property which is the subject of this application, shall require the applicant to comply with all rules, regulations, ordinances, plans, or other regulatory and legal restrictions in force at the time the applicant or its successors in interest advises the City of Eagle of its intent to change the planned use of the subject property unless a waiver/variance of said requirements or other legal relief is granted pursuant to the law in effect at the time the change in use is sought. 24. No change in the terms and conditions of this approval shall be valid unless they are in writing and signed by the applicant or the applicant's authorized representative and an authorized representative of the City of Eagle. The burden shall be upon the applicant to obtain written confirmation of any change from the City of Eagle. 25. Approval of any Design Review shall expire without notice to the applicant on the date of expiration of the Design Review, as stipulated in Eagle City Code (one year from the Planning and Zoning Commission approval date). 26. The City's actions on the application does not grant the applicant any appropriation of water or interference with existing water rights. The applicant indemnifies and holds the City harmless for any and all water rights, claims in any way associated with this application. CONCLUSIONS OF LAW: 1. A Neighborhood Meeting was held at 462 E. Shore Drive (The Land Group) at 6:00 PM, November 19, 2009, in compliance with the application submittal requirement of Eagle City Code. The application for this item was received by the City of Eagle on November 23,2009. 2. Notice of Public Hearing on the application for the Eagle Planning and Zoning Commission was published in accordance with the requirements of Title 67, Chapter 65, Idaho Code and the Eagle City Code on December 28, 2009. Notice of this public hearing was mailed to property owners within three-hundred feet (300-feet) of the subject property in accordance with the requirements of Title 67, Chapter 65, Idaho Code and Eagle City Code on December 23, 2009. The site was posted in accordance with the Eagle City Code on January 8, 2010. Requests for agencies' reviews were transmitted on December 7,2009, in accordance with the requirements of the Eagle City Code. Notice of Public Hearing on the application for the Eagle City Council was published in accordance with the requirements of Title 67, Chapter 65, Idaho Code and the Eagle City Code on February I, 2010. Notice ofthis public hearing was mailed to property owners within three-hundred feet (300-feet) of the subject property in accordance with the requirements of Title 67, Chapter 65, Idaho Code and Eagle City Code on January 26,2010. The site was posted in accordance with the Eagle City Code on February 13,2010. 3. The Council reviewed the particular facts and circumstances of this proposed conditional use permit application (CU-OI-09) with regard to Eagle City Code Section 8-7-5 "Action by the Commission and Council", and based upon the information provided concludes that the proposed conditional use permit is in accordance with the Eagle City Code because: The proposed conditional use; A. Will, in fact, constitute a conditional use as established in Section 8-2-3 of Eagle City Code Title 8 since a bank/financial institution with drive up service may be permitted in the C-3-DA (Highway Business District with a development agreement) zoning district if a conditional use permit is approved by the City Council; Page 12 of 14 K:\Planning Dept\Eagle Applications\CU\2009\CU-01-09 ccfCapital Educators,doc B. Will be harmonious with and in accordance with the general objectives or with any specific objective of the Comprehensive Plan and/or this title (Eagle City Code Title 8) since there are no inconsistencies with the Comprehensive Plan and since a bank/financial institution with drive up service is permitted with the approval of a conditional use within the C-3-DA (Highway Business District with a development agreement) zoning district and the Comprehensive Plan designates this site as Commercial; C. Will be designed, constructed, operated and maintained to be harmonious and appropriate in appearance with the existing or intended character of the general vicinity and that such use will not change the essential character ofthe same area since the bank/financial institution with drive up service is located within a commercial development which contains other bank/financial institutions with drive up service that are adjacent to this site and the design of the proposed structure must meet the City's design review requirements and the design requirements pursuant to the development agreement associated with the Eagle River development; D. Will not be hazardous or disturbing to existing or future neighborhood uses since the bank/financial institution with drive up service is to be located within a commercial development that currently has compatible commercial uses; E. Will be served adequately by essential public facilities that are currently available to the site such as highways, streets, police and fire protection, drainage structures, refuse disposal, sewer and schools; or that the persons or agencies responsible for the establishment of the proposed use shall be able to provide adequately any such services as noted in responses received by agencies providing the public services, or as conditioned herein; F. Will not create excessive additional requirements at public cost for public facilities and services and will not be detrimental to the economic welfare of the community since the site has been improved with essential public facilities such as streets, sewer and water services; G. Will not involve uses, activities, processes, materials, equipment and conditions of operation that will be detrimental to any persons, property or the general welfare by reason of excessive production of traffic, noise, smoke, fumes, glare or odors since the site will be required to provide outdoor communication systems that are designed to mitigate noise projection onto adjacent property, and the drive up service lanes have been placed on the south side of the building which buffers the lanes from South Eagle Road and eliminates any potential vehicle headlight glare on South Eagle Road and East Riverside Drive. H. Will have vehicular approaches to the property which are designed as not to create an interference with traffic on surrounding public thoroughfares as previously approved by the highway district having jurisdiction; and I. Will not result in the destruction, loss or damage of a natural, scenic or historic feature of major importance since none are apparent on this site. 4. Pursuant to Eagle City Code 8-7-3-5 (F), a conditional use permit shall not be considered as establishing a binding precedent to grant other conditional use permits. Page 13 of 14 K:\Planning Dept\Eagle Applications\CU\2009\CU-01-09 ccfCapital Educators,doc DATED this 9th day of March 2010. CITY COUNCIL OF THE CITY OF EAGLE A J:y, Idaho ATTEST: "111111',,, ", "I ..... .-(' <0{ 0 F b '" .. \\- C.-d', ...' t'" ....... ~ 10 ' ... v.. _. . ...... .. '/ -.,. ~ .. aRPOI\' . "'-...... '. : * .. (, .., /> .. V' ':. :: ti\~ : : : ....... : : -: d, ~'i S l::' It L : * : -:,V~..00 .c'rl, 1\....... : -;. e.+,b ,0,.- ~ ...... "1/> ...01/ A Tr.O... 0 ...... '" .f! ...... ~ ,...' ", OF ID ~ ..' III". 111111"'" Page 14 of 14 K:\Planning Dept\Eagle Applications\CU\2009\CU-01-09 ccfCapital Educators,doc